Page Engineering designs and constructs air conditioning and heating systems for hospitals and clinics. Currently, the company's staff is overloaded with design work. There is a major design project due in 8 weeks. The penalty for completing the design late is $14 000 per week, since any delay will cause the facility to open later than anticipated, and cost the client significant revenue. If the company uses its inside engineers to complete the design, it will have to pay them overtime for all work. Page has estimated that it will cost $12 000 per week (wages and overhead), including late weeks, to have company engineers complete the design. Page is also considering having an outside engineering firm do the design. A bid of $92 000 has been received for the completed design. Yet another option for completing the design is to conduct a joint design by having a third engineering company complete all electromechanical components of the design at a cost of $56 000. Page would then complete the rest of the design and control systems at an estimated cost of $30 000.
Page has estimated the following probabilities of completing the project within various time frames when using each of the three options. Those estimates are shown in the following table:
Option On Time Week Late 2Weeks Late 3Weeks Late
Internal Engineers .4 .5 .1 -
External Engineers .2 .4 .3 .1
Joint Design .1 .3 .4 .2
What is the best decision based on an expected monetary value criterion? (Note: You want the lowest EMV because we are dealing with costs in this problem.)
Illustrate what can a manager learn from characteristics also activities of this particular team. Elucidate how might factors which contribute to this team's success be adopted in a business setting.
Due to the physical separation of these 2 steps, an additional delay of 0.5 days is allowed for transportation. If daily demand = 13 units, Elucidate what is the production. Lead Time between Steps 1 also 2.
Compute the multifactor productivity before and after purchasing the new equipment. Use labour cost and overhead cost to derive multifactor productivity.
Explain how might a global capital market function differently from present-day international market.
Describe what happens with likelihood of a risk event occurring also cost of fixing risk event as a project proceeds through its life cycle.
Having been exposed to introductory material about ergonomics, can you imagine an analytical approach to documenting problem reported by drivers.
Explain why manager believe that fundamental contradiction to be encountered in organizational life also especially in health care organizations.
Illustrate what information does Flextronic have which its clients do not. Explain how can Flextronic leverage this information. Explain how does IBM manage its suppliers in order to make its pull strategy more effective.
This solution exemplifies how to select the correct constraint which is based upon the information given in linear programming problem. This is all addressed in under 50 words.
How is fast tracking also crashing different? How are they similar. Provide examples. Choose a business also evaluate beneficial influences of changing technological forces on that business.
Steel co has received an order for exactly 125 tons of steel. Steel co wishes to minimize cost for filling order. Explain how many tons from each Alloy should be in order.
The opening inventory is 100 units; an increase to 130 units is expected by the end of the plan. The demands for each month is given in illustrate what follows. Compute the total production, daily production also production also ending inventory f..
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +1-415-670-9521
Phone: +1-415-670-9521
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd