What is the annual total annual stocking cost

Assignment Help Operation Management
Reference no: EM13960792

The Ohio Electric generating plant in Cincinnati buys coal to generate electricty. Coal is supplied by rail cars at the rate of 9,000 tons per day at a price of $16.50 per ton and is used at a rate of 1,400 tons per day. The plant operates 365 days per year, and its annual carrying cost for the coal is 28% of the average value of its inventory of coal. The ordering cost for a shipment of coal is $675. Ohio Electric would like to use the EOQ (Economic Ordering Quantity) model.

a. What quantity of coal should Ohio Electric order each time it places an order?

b. What is the annual TSC (Total Annual Stocking Cost) that Ohio Electric should expect?

c. How many days should it take to receive one shipment after it starts arriving?

d. What is the maximum inventory level of coal that should be expected?

Reference no: EM13960792

Questions Cloud

Undifferentiated marketing and differentiated marketing : What are the similarities and differences among concentrated marketing, undifferentiated marketing, and differentiated marketing?
Write complete addition and multiplication tables for field : You should give sufficient detail for the arithmetic operations to be carried out but you do not need to write down the complete addition and multiplication tables for the field.
Determine order quantities-what is economic order quantity : A distributor of large appliances needs to determine the order quantities and reorder points for the various products it carries. The following data refer to a specific refrigerator in its product line: What is the economic order quantity?
Briefly describe the major earth science programs : Find an online source and discuss dye tracing in relation to caves. Briefly describe the major earth science programs of the following governmental agencies: USGS: www.usgs.gov and U.S. Department of Interior Bureau of Ocean Energy Management, Regula..
What is the annual total annual stocking cost : The Ohio Electric generating plant in Cincinnati buys coal to generate electricty. Coal is supplied by rail cars at the rate of 9,000 tons per day at a price of $16.50 per ton and is used at a rate of 1,400 tons per day. What quantity of coal should ..
How are business consumers similar to final consumers : How are business consumers similar to final consumers? Different from final consumers? Include the concept of derived demand in your response. Cite FIVE criteria for successful segmentation. Comment on the majority fallacy in your answer.
Study the relationship between wine consumption : A marketing research firm wishes to study the relationship between wine consumption and whether a person likes to watch professional tennis on television. One hundred randomly selected people are asked whether they drink wine and whether they watch t..
Total annual stocking cost and economic order quantity : If the annual demand for a product is 200,000 units, then the annual carrying cost rate is 30 percent of the cost of the unit, the product costs $37.50 per unit to purchase, and each time the product is ordered the related ordering cost is $96.00. Wh..
How would the japanese seismologists pinpoint the epicenter : The major earthquake that struck Japan was not far offshore, triggering a devastating tsunami. If that earthquake had originated hundreds of miles offshore, how would the Japanese seismologists pinpoint the epicenter, using their seismograph stati..

Reviews

Write a Review

Operation Management Questions & Answers

  These products or services should come from a range of

Choose four products or services that you are interested in learning more about.These products or services should come from a range of industries (such as consumer products, financial services, automotive, entertainment, etc)

  What is the material handling total of assigning

Departments A, B, C, and D need to be assigned to four rooms 1, 2, 3, and 4. These rooms are arranged in a row, in that order, with 20 meters between each. The departmental work flows are contained in the table below.

  Who needs to be comprised in decisions as they pertain to

what trade-offs are involved in a sharing information with other organizations in a supply chain and b the acquisition

  How do you determine the bottleneck of the process

How do you determine the bottleneck of the process? (activities 4 and 5 can be done in parallel) How do you determine what is the utilization of server 2? Assume demand= bottleneck capacity. Assuming demand = bottleneck capacity, What is the average ..

  Explain what supply-chain management

Explain what supply-chain management is. What does it include? How has information technology impacted supply-chain management?

  Why does the ucc allow for the buyer to sue for breach

Why does the UCC allow for the buyer to sue for breach of warranty? In your opinion, are the protections necessary? Why, or why not?

  Analyze the significance of abraham lincolns presidency

Evaluate Union and Confederate strategies during the Civil War

  Find the reorder point

The annual demand for a product is 14,200 units. The weekly demand is 273 units with a standard deviation of 95 units. The cost to place an order is $32.00, and the time from ordering to receipt is four weeks.

  Describe how to control the process to ensure

Continue the analysis of Apple Inc. through a Six Sigma review of processes and how these processes deliver customer satisfaction.

  Identify real life examples of a project

Identify real life examples of a project that would fit each of the following priority scenarios:

  A virus is rapidly becoming pandemic

A virus is rapidly becoming a pandemic. You are in charge of the CDC and have been given the authority to distribute a rare, but effective, cure. The problem is that it takes a considerable amount of time to produce the medication. Currently, there a..

  If we drew a random sample of federal employees from this

In early years of twenty-first century, annual salaries for federal employees in Upper Midwest averaged approximately $42,000, with a population standard deviation.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd