A company stocks a component that costs $20 per unit. Annual usage of this item is expected to be 3640 units. The firm is open for business 52 weeks per year, so weekly demand is 70 units per week, with a standard deviation of 20 units. The firm's cost accountants have estimated that it costs $50 every time an order is placed for more components, and that carrying the item in inventory costs about $10 per unit per year. Past experience with their supplier indicates that the time from ordering more items to receipt of the shipment of those items is 21 days (assume that they are open 7 days per week.)
a. What quantity should be ordered each time? (Assume that the EOQ assumptions apply.)
b. What is the minimum total annual cost (ordering + holding + purchase) for managing this inventory item?
c. If the company decided that their JIT program required frequent small orders and deliveries (assume that this would mean ordering a quantity of 20 units every other day, instead of the EOQ quantity on a less frequent basis), and the costs remain the same as described above, how much higher would the total annual cost be for this item?
d. If a 94% service level is required, what reorder point should be used?
Shirley Hopkins is developing a program in leadership training for middle-level managers. Shirley has listed a number of activities that must be completed before a training program of this nature can be conducted.
External Environmental Analysis: Identify key external forces with immediate strategic implications for Alaska Coffee Company.
Complete the cumulative Business Research Report by combining Parts 1-5 into a paper by collaborating with your team to include the following-
Task time estimates for the modification of an assembly line at Jim Goodale's Carbondale, Illinois, Draw the project network using AON.
A large hospital's nursery uses disposable diapers for its newborn babies at a rate of 60 cases per day. Ordering costs have been estimated at $50 per order. The hospital's Accounting Department has assigned a holding costs fraction of 0.15 to the nu..
Define the standards and parameters that health care professionals must have in order to work within their scope of practice. Describe the responsibility health care professionals must have in order to work within their scope of practice. Explain th..
for an organization the following project schedule is given. assume that all times are in days.taskpredecessornormal
Tom Schriber, a director of personnel of Management Resources, Inc., is in the process of designing a program that its customers can use in the job-finding process.
Describe the source of competitive advantage for your product. Evaluate how sustainable is this source of advantage. Assess the long-term sustainability of the source of differentiation and competitive advantage.
How does Amazon's strategy for slow moving, low-volume products and fast moving, high-volume items fit within its push-pull strategy (Simchi-Levi, Kaminsky, & Simchi-Levi, 2008, 203)? What competitive advantages does Amazon realize with its integrate..
What are strategic objectives? What is the purpose of strategic objectives? What makes an effective strategic objective?
Complete the Process Design Matrix. Pick one service with which you are familiar. Complete three to five line items such as production line, self-service, or personal attention approach, on the Process Design Matrix.
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +1-415-670-9521
Phone: +1-415-670-9521
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd