Quiz - PMIF

Question 1

Which of the following documents is not defined in the text as one of the four critical documents for preliminary planning?

a. Specifications

b. SOW

c. Network Diagrams

d. WBS

Question 2

Which of the following would be the first item to be discussed in the initial kickoff meeting for a project?

a. Understanding of the budget

b. Understanding of the schedule

c. Understanding of the plan

d. Understanding of the requirements

Question 3

Which of the following is often overlooked when planning and budgeting a project?

a. Cost and size of contractual documentation

b. Customer's milestones

c. Number of meetings with the customer

d. Timing of the deliverables

Question 4

Which of the following is normally not addressed in a change control board meeting to approve a scope change?

a. Value-added opportunity for the client

b. Impact on the schedule

c. Which functional unit will perform the change

d. Cost of the change

Question 5

A project manager desires a work breakdown structure that goes through six levels of detail. Level 3 through level 6 would most likely be prepared by the:

a. Project sponsor

b. Project manager

c. Subject matter experts

d. Customer

Question 6

Plans such as the cost plan, schedule plan and quality plan are referred to as:

a. Subsidiary plans

b. Integration plans

c. Specialized plans

d. Functional plans

Question 7

_____ involves working with stakeholders to create the document that formally authorizes a project.

a. Developing the project management plan

b. Performing integrated change control

c. Developing the project charter

d. Developing the preliminary project scope statement

Question 8

The outputs of the _____ process include change request status updates, project management plan updates, and project document updates.

a. monitoring and controlling

b. executing

c. initiating

d. planning

Question 9

What is a project charter? Discuss the inputs that can aid the development of a project charter. Identify 5 key inputs needed when developing the project charter.

Question 10

A customer is unhappy with the performance thus far on a project. The customer states that, unless scope changes are made at the contractor's expense, the contractor would be removed from the customer's preferred bidders list for future contracts. The contractor would most likely:

a. Refuse to perform the scope changes.

b. Perform the scope changes at the contractor's expense.

c. Take no action and hope that the customer will forget about the scope change request.

d. Perform the scope changes and then submit an invoice for payment to the customer.

Reference no: EM132146476

Questions Cloud

Explain two ways of making sense of a visual text : For this assignment, you will write a paper that informs readers about a common way of understanding a film (or a TV show, or even a video game).
What is the public policy exception to employment at will : What's an example of a termination that may be construed as an exception to employment at will based on public policy.
How well do members of her group get along with each other : a. How well do members of her group get along with each other? b. What is she getting out of the group's activities?
How a woman in the story dresses and acts : The first-person narrator comments on how a woman in the story dresses and acts. How does this relate to the conflicts in the story?
What is a project charter : Which of the following documents is not defined in the text as one of the four critical documents for preliminary planning?
5-forces broken down on a separate sheet : Using the 5-Forces broken down on a separate sheet, summarize how your company competes and creates profit within your industry.
Order the end of power and politics in their organizations : Can management order the end of power and politics in their organizations?
Describe and evaluate the selected online course offered : Evaluate an online course offered by a corporate organization for training purposes, academic course, or a virtual high school course.
Synergistic effects between intrinsic and extrinsic : Lawrence believes there can be synergistic effects between intrinsic and extrinsic motivation. He gives his employees 25% of their work time to work on projects

Reviews

Write a Review

Operation Management Questions & Answers

  Book review - the goal

Operations Management is about a book review. Title of the book is "Goal". This book has been written by Dr. Eliyahu Goldartt. The book has been appreciated by many as one of those books which offers an insight into the operations and strategic capac..

  Operational plan in hospitality enterprise

Operational plan pertaining to a hospitality enterprise is given in detail in the solution. The operational plan is an important plan or preparation which gives guidelines regarding the role and responsibilities of each and every operation at all lev..

  Managing operations and information

Recognise the importance of a strategic approach to the development and deployment of organisational information systems. Demonstrate an understanding of the importance of databases and their integration to the organisation's overall information mana..

  A make-or-buy analysis

An analysis of the holding costs, including the appropriate annual holding cost rate.

  Evolution and contributor of operations management

Briefly explain Evolution and contributor of Operations management.

  Functions and responsibilities of an operations manager

A number of drivers of change have transformed the roles, functions and responsibilities of an operations manager over recent years. These drivers have not only been based on technological innovations but also on the need for organisations to develop..

  Compute the optimal order quantity

Compute the Optimal Order quantity of DVD players. Determine the appropriate reorder point.

  Relationship to operations practice in the organisation

Evaluate problems in operations and identify approaches to overcoming them. Critically evaluate operating plans and identify areas for improvement. Justify, implement and evaluate changes to operations in line with modern approaches.

  A make or buy analysis

Develop a report for Figi Fabricating that will address the question of whether the company should continue to purchase the part from the supplier or begin to produce the part itself.

  Prepare a staffing plan

Prepare a staffing plan showing the change of your unit from medical/surgical staffing to oncology staffing.

  Leadership styles in different organizations

Ccompare the effectiveness of different leadership styles in different organizations

  Risk management tools and models

Be able to understand the concept of risk, roles and responsibilities for risk management and risk management tools and models.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd