What does earned value analysis tell us about this project

Assignment Help Operation Management
Reference no: EM132250491

You are working as an intern and have 10 cases to review. It is estimated that it will take you 5 hours per case and you are scheduled to work 5 hours a day. You are paid $10 per hour. After 6 work days you have spent 15 hours and completed 5 cases.

Calculate the following:

BAC

PV

EV

AC

SV

SPI

CV

CPI

EAC = BAC / CPI

VAC

ETC = EAC –AC

TCPI

What does Earned Value Analysis tell us about this project? If appropriate, what corrective action would you recommend?

Reference no: EM132250491

Questions Cloud

What was stalin interpretation of the munich conference : What was Stalin’s interpretation of the Munich Conference? Name at least two issues of disagreement between the Allies and the USSR during the war.
Relationship in artificial intelligence and game theory : What is the relationship between Artificial Intelligence (AI) and Game Theory?
Reason that sales promotion is growing : Which of the following is a reason that sales promotion is growing? Which of the following is NOT a risk of sales promotions?
The flow-time efficiency of patient for major treatment : What percentage is the flow-time efficiency of a patient for major treatment?
What does earned value analysis tell us about this project : You are working as an intern and have 10 cases to review. What does Earned Value Analysis tell us about this project?
Most relevant influence tactics discussed in the text : Explain how you might use the three of the nine most relevant influence tactics discussed in the text.
Ads in google search are exclusively geotargeted : Google discounts ads to just one cent less than average cost per click. Ads in Google search are exclusively geotargeted based on GPS data.
Five qualities associated with humble leadership : Did Barra demonstrate any of the five qualities associated with humble leadership? Explain
Types of transformational leadership behavior : Which of the four types of transformational leadership behavior were displayed by Barra? Provide examples.

Reviews

Write a Review

Operation Management Questions & Answers

  Book review - the goal

Operations Management is about a book review. Title of the book is "Goal". This book has been written by Dr. Eliyahu Goldartt. The book has been appreciated by many as one of those books which offers an insight into the operations and strategic capac..

  Operational plan in hospitality enterprise

Operational plan pertaining to a hospitality enterprise is given in detail in the solution. The operational plan is an important plan or preparation which gives guidelines regarding the role and responsibilities of each and every operation at all lev..

  Managing operations and information

Recognise the importance of a strategic approach to the development and deployment of organisational information systems. Demonstrate an understanding of the importance of databases and their integration to the organisation's overall information mana..

  A make-or-buy analysis

An analysis of the holding costs, including the appropriate annual holding cost rate.

  Evolution and contributor of operations management

Briefly explain Evolution and contributor of Operations management.

  Functions and responsibilities of an operations manager

A number of drivers of change have transformed the roles, functions and responsibilities of an operations manager over recent years. These drivers have not only been based on technological innovations but also on the need for organisations to develop..

  Compute the optimal order quantity

Compute the Optimal Order quantity of DVD players. Determine the appropriate reorder point.

  Relationship to operations practice in the organisation

Evaluate problems in operations and identify approaches to overcoming them. Critically evaluate operating plans and identify areas for improvement. Justify, implement and evaluate changes to operations in line with modern approaches.

  A make or buy analysis

Develop a report for Figi Fabricating that will address the question of whether the company should continue to purchase the part from the supplier or begin to produce the part itself.

  Prepare a staffing plan

Prepare a staffing plan showing the change of your unit from medical/surgical staffing to oncology staffing.

  Leadership styles in different organizations

Ccompare the effectiveness of different leadership styles in different organizations

  Risk management tools and models

Be able to understand the concept of risk, roles and responsibilities for risk management and risk management tools and models.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd