What conditions may a project manager accept change request

Assignment Help Operation Management
Reference no: EM131688199

1. If the latest time you can start a task is five hours into the project, and the earliest time is three and a half hours into the project, how much slack (also called float) does the task have?

    a. 0.5 hours

    b. 1.5 hours

    c. 2.5 hours

    d. 8.5 hours

2. Top-down estimates (also called parametric estimates):

    a. Are based on historical trends

    b. Can be derived from the WBS

    c. Can be determined by analyzing work packages

    d. Provide accurate assessments of project costs

3. The resource planning tool that enables us to identify who we need to carry out what tasks is called:

    a. A resource Gantt chart

    b. A resource matrix (also called the responsibility chart)

    c. A resource ogive

    d. A resource loading chart (also called a resource histogram)

4. The critical path:

    a. Provides the duration of a project

    b. Has the shortest duration on a project

    c. Is the most expensive path to implement

    d. Contains the project's most significant tasks

5. Good functional requirements

    a. Describe how the deliverable should be developed

    b. Provide detailed technical insights into what the deliverable will do

    c. Describe what the deliverable looks like and what it should do

    d. Are created after development of the technical specifications

6. Under what conditions may a project manager accept a change request?

    a. If the request has no effect on project objectives, deadlines, or resources

    b. If the request has no effect on project objectives, although it has effects on deadlines and resources

    c. If the request is coming from a valued customer

    d. If the request is from the Chief Executive Officer

7. What is the function of a change control board (CCB) in configuration management?

    a. To assess the management impacts of change requests

    b. To initiate changes needed on the project

    c. To focus on the technical implication of change requests

    d. To approve change requests coming from senior management

8. A key characteristic of an effective project team is that:

    a. Members have graduate degrees in project management

    b. Members come from the same professional background

    c. Members see themselves as stakeholders in the project

    d. Members adhere to a prescribed pecking order

9. The type of management whose focus is on activities whose variances lie outside the acceptable range is:

    a. Management by Objectives

    b. Management by Exception

    c. Management by Walking Around

    d. Management by Control Limits

10. A work package is to be found at the summary level of the WBS.

    a. true

    b. false

11. Which of the following shows resource allocation over time?

    a. Resource Gantt chart

    b. Resource matrix

    c. S-Curve

    d. Resource leveling

Reference no: EM131688199

Questions Cloud

Compliance with legislative acts and valuing diversity : What is the relationship between compliance with legislative acts and valuing diversity?
Redefining learning as change in behavior : The revolution began by redefining "learning" as "change in behavior," which connected "learning and doing."
Construct standardized medical terminology : discuss three challenges you foresee in attempting to construct a standardized medical terminology to be used in hospitals, physicians’ offices,
Human resources influence organizational performance : Explain how a firm's human resources influence organizational performance.
What conditions may a project manager accept change request : Top-down estimates (also called parametric estimates). Under what conditions may a project manager accept a change request?
Recognition is first stage of needs-requirement life cycle : Needs recognition is the first stage of the needs-requirement life cycle. Definitive estimates are generally derived from. Rapid prototyping is methodology for.
What is communication : Define communication in your own words. Also, state how important communication is in your personal life.
Trade theory-how is the health of its export business : Trade theory-How is the health of its export business? Explain.
Process has upper and lower specifications : Suppose that a process has upper and lower specifications at USL = 62 and LSL = 38, and a Target = 50.

Reviews

Write a Review

Operation Management Questions & Answers

  Book review - the goal

Operations Management is about a book review. Title of the book is "Goal". This book has been written by Dr. Eliyahu Goldartt. The book has been appreciated by many as one of those books which offers an insight into the operations and strategic capac..

  Operational plan in hospitality enterprise

Operational plan pertaining to a hospitality enterprise is given in detail in the solution. The operational plan is an important plan or preparation which gives guidelines regarding the role and responsibilities of each and every operation at all lev..

  Managing operations and information

Recognise the importance of a strategic approach to the development and deployment of organisational information systems. Demonstrate an understanding of the importance of databases and their integration to the organisation's overall information mana..

  A make-or-buy analysis

An analysis of the holding costs, including the appropriate annual holding cost rate.

  Evolution and contributor of operations management

Briefly explain Evolution and contributor of Operations management.

  Functions and responsibilities of an operations manager

A number of drivers of change have transformed the roles, functions and responsibilities of an operations manager over recent years. These drivers have not only been based on technological innovations but also on the need for organisations to develop..

  Compute the optimal order quantity

Compute the Optimal Order quantity of DVD players. Determine the appropriate reorder point.

  Relationship to operations practice in the organisation

Evaluate problems in operations and identify approaches to overcoming them. Critically evaluate operating plans and identify areas for improvement. Justify, implement and evaluate changes to operations in line with modern approaches.

  A make or buy analysis

Develop a report for Figi Fabricating that will address the question of whether the company should continue to purchase the part from the supplier or begin to produce the part itself.

  Prepare a staffing plan

Prepare a staffing plan showing the change of your unit from medical/surgical staffing to oncology staffing.

  Leadership styles in different organizations

Ccompare the effectiveness of different leadership styles in different organizations

  Risk management tools and models

Be able to understand the concept of risk, roles and responsibilities for risk management and risk management tools and models.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd