HYDROSUB’S UNFLOATABLE AMPHIBIOUS ASSAULT VEHICLE

Kathleen Johnson started her new job as chief buyer at Hydrosub in San Francisco. Her day was without incident until she received the following telephone call. Voice on phone: Good afternoon, Ms. Johnson. I am Burt Lauderas, project supervisor at Bolger Shipyards in Tacoma. The design changes for the A.A.V. are not part of our current contract. We need to renegotiate the contract before instituting the changes. Completion of the A.A.V. will be delayed an additional four weeks. Kathleen Johnson (mildly concerned): Is it really necessary to renegotiate the current contract before beginning the work? Voice on phone: Yes, Ms. Johnson, the contract states that every design change must be renegotiated. Kathleen Johnson (more concerned): Why will it take four additional weeks to complete the project? Voice on phone: It will take time to renegotiate the contract and hire replacement welders, and approximately two weeks to do the rework. Kathleen Johnson (completely bewildered): Thank you for calling, Mr. Lauderas. I’ll contact you tomorrow. After recovering her composure, she opened the A.A.V. file and started the formation of her first ulcer. Status reports showed that progress toward completion had been slow. The last chief buyer had been “retired” when costs exceeded the original estimate of $9 million. Revised cost estimates revealed expected expenditures to exceed $23 million. Particularly despairing was the fact that the completion date had already been revised four times and the current completion date was listed as “unknown. After hours of reviewing the A.A.V. project file, Kathleen understood Burt Lauderas’s concerns. The project involved building a prototype amphibious assault vehicle for the U.S. government. It had been Hydrosub’s intent to build a premium product, without concern for cost. If Hydrosub received the subsequent production contract, the company’s financial stability would be greatly enhanced. However, due to in-house capacity problems, Bolger Shipyards had been contracted to build the prototype. Hydrosub engineers designed the prints and specifications for the prototype. These specifications incorporated the latest in high tech design and utilized the best materials available. Design specifications had changed innumerable times over the project’s life. Continual rework and time delays had hampered progress. Bolger had reported design errors that necessitated the refitting of complex equipment and rework of the aluminum welding. Materials requirements included the use of welded aluminum. Bolger normally employed only steel welders; aluminum welders were in short supply and impatient during work stoppages. On the A.A.V. project, Bolger Shipyards currently employed 150 people on two shifts. Often Bolger required overtime work. The Bolger contract was cost-based plus a fixed fee. A particularly disturbing problem was Bolger’s cost reporting system. Bolger contract negotiators waited for up to three weeks for cost data. Weekly time cards, bimonthly reporting, and periodic analysis greatly hindered preparation for the contract talks. As Kathleen Johnson reflected on the facts, her phone rang again. Voice on phone: Hello, Ms. Johnson, welcome to Hydrosub. This is George Rope, president of Hydrosub. Kathleen Johnson: Thank you, Mr. Rope. 205 George Rope: Mr. Johnson, I feel uneasy burdening you with the Bolger Shipyards problem, but I haven’t any other choice. Your hiring was based on your tremendous qualifications. We had hoped to acclimate you to your responsibilities; unfortunately, there is no time. The A.A.V. project must be concluded soon. Over 100 Hydrosub employees are currently working on this project; they are discouraged. The government is very anxious, and we are competing for the future sales of this product. Utilize all your expertise and finish the prototype.

1. Who is responsible for the poor performance of the Bolger contract?

2. What caused the production delays and cost miscalculations?

3. What can Kathleen Johnson do now to ensure completion of the project and prevent further problems?

4. How should Hydrosub’s staff have prepared for negotiations with suppliers on this contract?

Reference no: EM132098694

Questions Cloud

How economies of scale are particularly important : Explain how economies of scale are particularly important to a monopolist, be they real (in reality, there are very few examples of monopoly in the real economy
Related to marginal product of labor : How is production function related to marginal product of labor?
Motivate companies to expand internationally : Discuss in detail the three primary factors that motivate companies to expand internationally.
Is starbucks bucking the bandwagon effect : How do you explain this difference? Is Starbucks bucking the bandwagon effect, or is something else going on?
What caused the production delays and cost miscalculations : What caused the production delays and cost miscalculations? How should Hydrosub’s staff have prepared for negotiations with suppliers on this contract?
Characteristics of a tragedy of the commons : What are the characteristics of a "tragedy of the commons"? Can the emission of greenhouse gases (causing global warming)
What does mfc-mrp mean : What does MFC
Total number to be prepared in the internet business : Given a 96% service level on the latest sale of a product X, What will be the safety stock and total number to be prepared in the internet business?
How four sociological concepts learned in class apply : Analyze how at least four sociological concepts learned in class apply to the field log observations.

Reviews

Write a Review

Operation Management Questions & Answers

  Explain the purpose associated with the punishment

Explain the purpose associated with the punishment that was imposed.

  Metrics in a supply chain

Metrics in a supply chain: a. are governed by the International Metric Commission. b. are measurements of performance. c. are a charge passed on to customers. d. are not used on transportation. e. do not apply to the supply chain.

  Leadership training and development

Leadership training and development throughout all levels of the organization. From your experience discuss the importance this component and why?

  Summarizes the legal and regulatory issues

Identifies and summarizes the legal/regulatory issues that the bank should be aware of as they address this situation,

  What role does information technology play in the management

What role does information technology play in the management of transportation planning, execution, and analysis?

  Common equity on the firm balance sheet

Ebersoll Mining has $11 million in sales, its ROE is 11%, and its total assets turnover is 2.5x. Common equity on the firm's balance sheet is 65% of its total assets. What is its net income?

  Most osha inspections are initiated by employer complaints

Explain how you would go about determining whether a job candidate is being honest with you. In detail. The leading cause of workplace injuries was overexertion, such as lifting, carrying, pushing, and pulling. Most OSHA inspections are initiated by ..

  Estimate the loss for quality characteristic

A quality characteristic has a manufacturing specification (in cm) of 0.200 ± 0.05. Historical data indicate that if the quality characteristic takes on values larger than 0.25 cm or smaller than 0.15 cm.

  Discuss any potential policy implications for the issue

Rationing Issues in Healthcare The concept of rationing healthcare is dealt with on a daily basis. Healthcare rationing in the United States exists in various forms. Access to private health insurance is rationed based on price and ability to pay. Di..

  What is trustworthiness

What is trustworthiness? Explain how employees can gauge the "track record" of their supervisors.

  Administrative home for projects

Identify and discuss three major advantages and disadvantages of using the pure project organization as the administrative home for projects.

  Which of the given is considered an organizational

which of the following is considered an organizational blueprint which prescribes the quantity and time frame for when

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd