What are the savings with this new schedule

Assignment Help Operation Management
Reference no: EM13228982

production and management Brunswick, read an article on time-phased requirements planning. He was curious about how this technique might work in scheduling Brunswick's engine assembly operations and decided to prepare an example to illustrate the use of time-phased requirements planning. Phil's first step was to prepare a master schedule for one of the engine types produced by Brunswick: the Model 1000 engine. This schedule indicates the number of units of the Model 1000 engine to be assembled each week during the last 12 weeks and is shown in Figure 1. Next, Phil decided to simplify his requirements planning example by considering only two of the many components that are needed to complete the assembly of the Model 1000 engine. These two components, the gear box and the input shaft, are shown in the product structure diagram in Figure 2. Phil noted that the Gear Box is assembled by the subassembly Department and subsequently is sent to the main engine assembly line. The Input Shaft is one of several component parts manufactured by Brunswick that are needed to produce a Gear Box sub-assembly. Thus, levels 0, 1, and 2 are included in Figure 2 to indicate the three manufacturing stages that are involved in producing an engine: The Engine Assembly Department, the Sub-Assembly Department, and the Machine Shop. Figure 1 Model 1000 Master Schedule Week 1 2 3 4 5 6 7 8 9 10 11 12 Quantity 15 5 7 10 0 15 20 10 0 8 2 16 The manufacturing lead times required to produce the Gear Box and the Input Shaft components are also indicated in Figure 2. Note that two weeks are required to produce a batch of Gear Boxes and that all of the Gear Boxes must be delivered to the assembly line parts stockroom before Monday morning of the week in which they are to be used. Likewise, it takes three weeks to produce a lot of Input Shafts, and all of the shafts that are needed for the production of Gear Boxes in a given week must be delivered to the Sub- Assembly Department stockroom before Monday morning of that week. In preparing the MRP example, Phil planned to use the attached worksheets and to make the following assumptions: 1. Seventeen Gear Boxes are on hand at the beginning of week 1 and five Gear Boxes are currently on order to be delivered at the start of week 2. 2. Forty input shafts are on hand at the start of week 1, and 22 are scheduled for delivery at the beginning of week 2. ASSIGNMENT: 1. Initially, assume that Phil wants to minimize his inventory requirements. Assume that each order will be only for what is required for a single period. Using the following forms, calculate the net requirements and planned order releases for the gear boxes and input shafts. Assume that lot sizing is done using lot-for-lot. 2. Phil would like to consider the costs that his accountants are currently using for inventory carrying and setup for the gear boxes and input shafts. There costs are as follows: PART COST Gear Box Setup=$90/order Inventory carrying cost=$2/unit/week Input Shaft Setup=$45/order Inventory carrying cost=$1/unit/week Given the cost structure, evaluate the cost of the schedule from (1). Assume inventory is valued at the end of each week. 3. Calculate a schedule using least-total-cost lot sizing. What are the savings with this new Schedule?

Reference no: EM13228982

Questions Cloud

What would you tell the hr manager : The HR manager asks your opinion on the job application. What would you tell the HR manager? Would you have any suggestions about the department of your company where the chemist should work, if hired?
Illustrate validity of the gaussian theorem : suppose the one dimensional field. A-=Kx ax- exist in a region. illustrate the validity of Gaussian theorem by evaluating its volume and surface integral inside and on the rectangular parallelelpiped bounded by the surfaces:
Explain solid sodium hydroxide is added to the buffer system : (1.) Determine the pH of this buffer. (2.) Some solid sodium hydroxide is added to this buffer system and the new pH is measured as 4.74. How many grams of NaOH were added? (Assume the total volume remains unchanged)
Determine the energy in the signals odd part : A signal x(t) can be represented as x(t)=xe(t)+xo(t) where xe(t)=(1/2){x(t)+x(-t)} is the even part, and xo(t)=(1/2){x(t)-x(-t)} is the odd part of the signal. Let x(t) be an energy signal with an energy of 20 Joules. Suppose the even part of x(t) is..
What are the savings with this new schedule : Assume inventory is valued at the end of each week. 3. Calculate a schedule using least-total-cost lot sizing. What are the savings with this new Schedule?
Explain 1-bromopropane and 1-chloropropane : A sample consisting of 1-bromopropane and 1-chloropropane isinjected into a gas chromatograph quipped with a nonpolar column.which compound has the shorter retention time? Explaine the answer.
What are the differences between bottom-up and top-down : What are the differences between bottom-up and top-down estimating approaches? Determine advantages and disadvantages for using each approach. Under what conditions would you prefer one over the other? Provide a specific example to support your re..
Find the values of q and r : Substitute a Type 2 service level criterion of 98% for the stock-out cost. Assume that Q is given by the EOQ. Find the values of Q and R.
Find the max and min skew values : There are 2 stages of pipeline. 1st stage: max delay 6.5ns, min delay 2.5ns. 2nd stage: max delay 5ns, min delay 2ns. Setup time, hold time and flip flop delays = 0.1ns.

Reviews

Write a Review

Operation Management Questions & Answers

  What should marketers consider when pricing products

What should marketers consider when pricing products in different locations around the world?

  Assist with finding advertising appeals and persuading

What two ways would you appeal to the buying behaviors of this target market, and why? Based on this information, discuss with your colleagues the ways in which your company should segment the targeted customer groups to assist with finding adverti..

  Explain how much could industry save annually in ordering

Currently manager orders once a month. Explain how much could industry save annually in ordering and carrying costs by using EOQ.

  The attitudes and bargaining behaviors of the participants

Do you think the attitudes and bargaining behaviors of the participants in collective bargaining negotiations are more or less important in the final outcome than economic conditions and factors

  What are the total annual holding and ordering costs

What are the total annual holding and ordering costs associated with your recommended EOQ?

  What is the maximum utilization of days

A nursing home contracts with an HMO for skilled nursing care at $2.00 PMPM. If costs are expected to average $120 per day, what is the maximum utilization of days per 1,000 members that the nursing home can experience before it begins to lose mon..

  Electrical appliance a consists of three major components

An electrical appliance A consists of three major components: B, C and D. One unit of A consists of two units of B, one unit of C, and three units of D

  Which of the following is not a particular characteristic

Which of the following is not a particular characteristic of the experience economy?

  Crisis leadership different from leading normal circumstance

How is crisis leadership different from leading under normal circumstance? If leaders wanted to fine-tune crisis leadership style, how would you suggest they practice without creating havoc to do so?

  Against the regulation of derivatives

Examine the argument for and against the regulation of derivatives. Suggest at least two (2) reasons the government should or should not regulate the trading of derivatives. Provide a rationale for your suggestions.

  Develop a brief business plan

develop a brief business plan that highlight thefinancial,marketing and organization aspects

  Developing personal skills in making

Developing personal skills in making, assessing and communicating recommendations on how to improve development and commercialization organizations

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd