What are the cost and schedule variances for the project

Assignment Help Business Management
Reference no: EM131302854

Problem 1. A project in its 26th week has an actual cost of $270,000. It was scheduled to have spent $261,000. For the work performed to date, the budgeted value is $272,000. What are the cost and schedule variances for the project? What are the SPI and CPI?

Problem 2. A project has just completed its 87th item in the project plan. It was scheduled to have spent $168,000 at this point in the plan, but has actually spent only $156,000. The project manager estimates that the value of the work actually finished is nearly $162,000. What are the spending and schedule variances for the project? What are the SPI and CPI?

Problem 3. The following project is at the end of its 6th week. Find the cost and schedule variances. Also find the CPI and SPI. Then find the critical ratio of the project using earned value calculations. Finally, calculate the ETC and EAC for the project.

Activity

Predecessor

Duration (wks)

Budget ($)

Actual Cost ($)

%Complete

a

-

2

300

400

100

b

-

3

200

180

100

c

A

2

250

300

100

d

A

5

600

400

20

e

b,c

4

400

200

20

Problem 4.  

Using the concepts from Session 11 reading (textbook and reserved readings), respond to following with a thorough explanation. Include any citations for references used to support your answer.

1. What are some reasons that a failing project still might not be terminated?

2. Who would make the best auditors: outside unbiased auditors or inside auditors who are more familiar with the organization, its procedures, and the project?  Why?

3. Under what circumstances would you change your answer to the previous question?

4. Should the results of an evaluation or audit be shared with the project team?

5. What are the major purposes served by an after-the-fact project evaluation?

Problem 5. Solve the following Case:

Stoneworth Paving Company specializes in highway paving jobs for state of Virginia. When the State first awarded Stoneworth the contract, they stipulated a 1% penalty for each week Stoneworth was late on a completion date. Preston Flintrock, the project coordinator for Stoneworth, began to notice that the last two jobs were three weeks late, and the paving job that was due to be completed in the next two weeks was behind schedule. When Preston went in the field to investigate, he found the job to be understaffed, supplier delays, and a high work rejection/repaving needed. As a result, Preston decided to establish a better system of project control and present it to the boss.

Question 1: If you were Preston, what characteristics would you be looking for in a new control system? Explain

Question 2: Will a new control system be adequate for the problem? Explain

Reference no: EM131302854

Questions Cloud

What is the cross-rate of swiss francs to euros : Suppose the exchange rate between U.S. dollars and Swiss francs is SF 1.143 = $1.00, and the exchange rate between the U.S. dollar and the euro is $1.00 = 1.1033 euros. What is the cross-rate of Swiss francs to euros (SF/Euro)? Enter your answer roun..
What are the total shortage costs : ABC Company sells 2,995 chairs a year at an average price per chair of $198. The carrying cost per unit is $27.77. The company orders 330 chairs at a time and has a fixed order cost of $31 per order. The chairs are sold out before they are restocked...
What are organizational controls : What is organizational structure and what are organizational controls? What are the differences between strategic controls and financial controls? What is the importance of these differences?
Do businesses have social responsibilities : Do businesses have social responsibilities? Why or why not? What can be some social aspects of businesses?
What are the cost and schedule variances for the project : Problem 1. A project in its 26th week has an actual cost of $270,000. It was scheduled to have spent $261,000. For the work performed to date, the budgeted value is $272,000. What are the cost and schedule variances for the project? What are the S..
What type of adjustments must advertising agencies make : What type of adjustments must advertising agencies make as more companies want "one sight, one sound, one sell" campaigns? Use examples if possible.
Lowers expected rate of return on foreign currency deposits : Briefly explain your answer. No credit without explanation. Support your answer with a graph if needed. Depreciation of the domestic currency today (i.e. EH/F in class) lowers the expected rate of return on foreign currency deposits.
Propose a type of message appeal to be used in advertising : Propose a type of message appeal to be used in the advertising, making sure to explain rationale behind appeal. Analyze different cultures product will appeal to and make recommendations on which three would be best choice.
How can you assess and address risk factors : Can risk be eliminated if the project is well and carefully planned? How do you calculate acceptable risks? How can you assess and address risk factors? Please explain. Use a specific example to support your answer.200 words

Reviews

Write a Review

Business Management Questions & Answers

  Attribute employees most want to see in their managers

Research consistently indicates that the attribute employees most want to see in their managers is-freedom-honesty-passion-hard work-none of the above

  Write the marketing recommendations

Write the marketing recommendations you would like implemented for the non-profit organization you are pursuing

  Explain your mne with a brief business plan

Create a fictional MNE which manufactures an imaginary product and choose a country in which to conduct FDI. Explain your MNE with a brief business plan.

  The airline industry using excel solver

During the month of July, Pittsburgh resident Bill Fly must make 4 round-trip flights between Pittsburgh and Chicago. These are the dates of the meetings Bill must attend:

  1 strategic financing decisions - cost of retained

1. strategic financing decisions - cost of retained earningsschweser satellites inc. produces satellites earth stations

  Quade is an expert in twentieth-century art

1.Quade is an expert in twentieth-century art. Rachel visits Quade's gallery, seeking to buy artwork as an investment. Quade shows her a painting that in his opinion is by Picasso. Quade's statement is a.an express warranty.b.an implied warranty.c.a..

  Critical of corporations that earn growing profits

Why are some groups extremely critical of corporations that earn growing profits?

  Consider recent events and the prevailing politicak

Consider recent events and the prevailing politicak and economic conditions in the Russian Federation. As a manager who has been considering investment there, how do you assess the political and economic risks

  Account for joint production costs

What do you think is the best way to account for joint production costs before and after the split off point? Give a specific example and explain why you think the method selected is the best?

  Ethical considerations in communication and crisis

How do ethical considerations impact an organization's communications process throughout a crisis? How does the choice of spokesperson impact the organization's credibility?

  Detailed explanation to transformational leadership

Detailed Explanation to Transformational Leadership and briefly explain a possible group or organization to belong and If you were the leader of this group.

  Concept of the business and other particulars

Create a Word document of 3-4 pages on your proposed business. Include the concept of the business and other particulars that would sell this idea to the investors. Explain why it would be advantageous for the investors to advance. Include an anal..

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd