A manufacturer of high-quality small appliances intended for home use is currently working on the development of a new kitchen appliance that will chill foods quickly much as a microwave oven heats them quickly, although the technology involved is quite different. R&D engineers now have a working prototype and are satisfied that, with the cooperation from the production and marketing people, the product can be ready in time for the summer buying season. A target date has been set for product introduction that is 24 weeks away. One of the current issues for the company is that a competitor is also in the process of developing a similar product, which it intends to bring out at almost exactly the same time. The manager of the company is wondering whether it would be possible to expedite the usual product introduction process in order to beat the competition to the market. If possible, the manager would like to get a six week jump on the completion; this would put the product introduction date only 18 weeks away. Since the product of the company has been through the production-introduction process a number of times, the manager has developed a list of the tasks that must be accomplished and the order in which they must be completed. Although the duration and costs vary depending on the particular product, the basic process does not. The list of activities, the precedence relationships, activity durations, and costs estimates are presented in Table below. Note that some of the activities can be completed on crash basis, with an associated increase in cost. The company need to decide whether to bring the product to the market 18 weeks from now as the manager is recommending. For the project, indirect costs have been estimated at $5,500 per week. However, after week 18, if the product is not fully on the market, with each additional week the project investment value will reduce by $20,000. For every week the project is shortened to week 18 the manufacturer saves one week of investment value and indirect cost, or $25,500. For reduction beyond week 18, the savings are only the weekly indirect costs of $5,500. As the project manager specialist you have been asked to answer the following questions.

a. Develop an AON network diagram for the product and determine the number of paths and the critical path. How long does the project take using normal durations? What is the total cost required for completing the project on normal time?

b. Is it possible to complete the project in 18 weeks? What would the associated additional costs be? Which activities would need to be completed on a crash basis? What is the net savings from crashing the project to 18 weeks? What is the total cost required for completing the project in 18 weeks?

c. Is there some timeframe shorter than the 18 weeks recommended by the manager that would make sense in terms benefit-cost (i.e., what is the minimum-cost schedule?). What would be the total cost for completing in this timeframe?

d. What is the slack (in days) associated with noncritical paths through the project?

Reference no: EM13845630

Questions Cloud

Financial performance problems : How do the five competitive forces in Porter's model affect the average profitability of the industry? For example, in what way might weak forces increase industry profits, and in what way do strong forces reduce industry profits? Identify an industr..
Generic strategies of overall cost leadership : Apply Porter’s generic strategies of overall cost leadership, differentiation, and focus appropriately to an organization with which you are familiar or interested. During the application of the generic strategy, select and justify its appropriatenes..
Product mix is product assortment : A Product mix is a product assortment; Let's analyze the use of the word Length as opposed to Breadth. Are they really the same thing? Which term do you think captures the essence of its true meaning?
Law of the fifth discipline : Select a Law of the Fifth Discipline we covered and discuss how you have seen, or experienced its success. Then select a second and different law, and discuss where you may have seen it, or are experiencing it currently, and how you might change the ..
Total cost required for completing project on normal time : A manufacturer of high-quality small appliances intended for home use is currently working on the development of a new kitchen appliance that will chill foods quickly much as a microwave oven heats them quickly, although the technology involved is qu..
Competitive advantage is so highly recommended in field : Evaluate why needing to have a competitive advantage is so highly recommended in the field of strategic management. Using an example of a specific organization, what might that organization do (or have they done) if they need to change or find a turn..
Describe your four strong and weak leadership qualities : Identify and describe your four strong and weak leadership qualities. Which is your exemplary leadership style and why? How you have applied successfully?
Highly recommended in the field of strategic management : Evaluate why needing to have a competitive advantage is so highly recommended in the field of strategic management. Using an example of a specific organization, what might that organization do (or have they done) if they need to change or find a turn..

Reviews

Write a Review

Operation Management Questions & Answers

  Compute the optimal order quantity

To ensure a full line of outdoor clothing and accessories, the marketing department at Teddy Bower insists that they also sell waterproof hunting boots. Teddy Bower contacted several Taiwanese suppliers to request quotes. (1) Find Cu. (2) Find Co. (3..

  What are some major capacity considerations in a hospital

1. what are some capacity balance problems faced by the following organizations or facilities?a. an airline terminalb.

  List the series of steps involved in converting rural land

a). List the series of steps involved in converting rural land into development. b). Indicate the points in this process where actions of government agencies intersect with (or influence or exert control over)

  What was its capacity utilization rate last month

Both production lines can produce all the different types of nozzles. The bronze machines needed for the bronze sprinklers require two operators and can produce up to 12,000 sprinklers.

  Function performed in scheduling and controlling operation

Which of the following is not a function performed in scheduling and controlling an operation?

  Description of breastfeeding accommodations in the workplace

Description of Breastfeeding Accommodations in the Workplace which include an overview of the concept.

  Case study - mcdonald corporation

This case discusses McDonald's Corporation and the situation it faced in 2001. After many years of double?digit growth in sales and net revenue, the company's sales grew only 1.12 percent and net revenue dropped 17.2 percent from 2000 to 2001.

  Should your company buy equipment or lease it

Suppose your company is trying to decide whether it should buy special equipment to prepare some of its high-quality publications itself or lease equipment from another company. Should your company buy equipment or lease it.

  Theoretical minimum for the number of work

What is the cycle time? B) What is the theoretical minimum for the number of work stations that Rosenberg can achieve in this assmebly line?

  What environmental forces could be at work in middleburg

What environmental forces could be at work in Middleburg and Uniontown that Shoemaker should consider? What are the possible distinctive competencies of Grandmothers?

  Explain how to create a work breakdown structure

Explain how to create a work breakdown structure and how a project manager breaks down the overall project into packages.

  Calculate the start and finish times for each activity

calculate the start and finish times for each activity and determine the minimum number of weeks for completing the project Identify slack in tghe activities not on the project critical path

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd