MULTIPLE CHOICE 

1.If x = 23 ounces, σ = 0.4 ounces, and n = 16, the ±3σ control limits will be 

1.a. 21.8 to 24.2 ounces 

2.b. 23 ounces 

3.c. 22.70 to 23.30 ounces 

4.d. 22.25 to 23.75 ounces 

5.e. none of the above 

2.The usual purpose of an R-chart is to signal whether there has been a 

1.a. gain or loss in dispersion 

2.b. change in the percent defective in a sample 

3.c. change in the central tendency of the process output 

4.d. change in the number of defects in a sample 

5.e. none of the above 

3.A manager wishes to build a 3σ range chart for a process. The sample size is five, the mean of sample means is 16.01, and the average range is 5.3. From Table S6.1, the appropriate value of D3 is 0, and D4 is 2.115. The UCL and LCL for this range chart are 

1.a. 33.9 and 11.2 

2.b. 33.9 and 0 

3.c. 11.2 and 0

4. d. 6.3 and 0 

5.e. 31.91 and 0.11 

4.Plots of sample ranges indicate that the most recent value is below the lower control limit. What course of action would you recommend? 

1.a. Since there is no obvious pattern in the measurements, variability is in control. 

2.b. One value outside the control limits is insufficient to warrant any action. 

3.c. Lower than expected dispersion is a desirable condition; there is no reason to investigate. 

4.d. The process is out of control; reject the last units produced. 

5.e. Variation is not in control; investigate what created this condition. 

5.To set x-chart upper and lower control limits, one must know the process central line, which is the 

1.a. average of the sample means 

2.b. total number of defects in the population 

3.c. percent defects in the population 

4.d. size of the population

5. e. average range 

6.According to the text, the most common choice of limits for control charts is usually 

1.a. ± 1 standard deviation 

2.b. ± 2 standard deviations 

3.c. ± 3 standard deviations 

4.d. ± 3 standard deviations for means and ± 2 standard deviations for ranges 

5.e. none of the above 

7.Which of the following is true of a p-chart? 

1.a. The lower control limit is found by subtracting a fraction from the average number of defects. 

2.b. The lower control limit indicates the minimum acceptable number of defects. 

3.c. The lower control limit may be below zero. 

4.d. The lower control limit may be at zero. 

5.e. The lower control limit is the same as the lot tolerance percent defective. 

8.The normal application of a p-chart is in 

1.a. process sampling by variables 

2.b. acceptance sampling by variables 

3.c. process sampling by attributes 

4.d. acceptance sampling by attributes 

5.e. none of the above 

9.The statistical process chart used to control the number of defects per unit of output is the 

1.a. x-chart 

2.b. R-chart

3. c. p-chart 

4.d. AOQ chart

5. e c-chart

10.The c-chart signals whether there has been a  

1.a. gain or loss in uniformity 

2.b. change in the number of defects per unit 

3.c. change in the central tendency of the process output 

4.d. change in the percent defective in a sample 

5.e. change in the AOQ 

11.The local newspaper receives several complaints per day about typographic errors. Over a seven-day period, the publisher has received calls from readers reporting the following number of errors: 4, 3, 2, 6, 7, 3, and 9. Based on these data alone, what type of control chart(s) should the publisher use?

1. a. p-chart 

2.b. c-chart

3. c. x-chart 

4.d. R-chart

5. e. x-and R-charts 

12.A manufacturer uses statistical process control to control the quality of the firm's products. Samples of 50 of Product A are taken, and a defective/acceptable decision is made on each unit sampled. For Product B, the number of flaws per unit is counted. What type(s) of control charts should be used? 

1.a. p-charts for A and B 

2.b. p-chart for A, c-chart for B 

3.c. c-charts for both A and B 

4.d. p-chart for A, mean and range charts for B 

5.e. c-chart for A, mean and range charts for B 

13.A nationwide parcel delivery service keeps track of the number of late deliveries (more than 30 minutes past the time promised to clients) per day. They plan on using a control chart to plot their results. Which type of control chart(s) would you recommend? 

1.a. x-and R-charts 

2.b. p-charts 

3.c. c-charts 

4.d. x-, but not R-charts 

5.e. both p- and c-charts 

14.A run test is used 

1.a. to examine variability in acceptance sampling plans 

2.b. in acceptance sampling to establish control 

3.c. to examine points in a control chart to check for natural variability 

4.d. to examine points in a control chart to check for nonrandom variability 

5.e. none of the above 

15.Which of the following is true regarding the process capability index Cpk? 

1.a. A Cpk index value of 1 is ideal, meaning all units meet specifications. 

2.b. The larger the Cpk, the more units meet specifications. 

3.c. The Cpk index can only be used when the process centerline is also the specification centerline. 

4.d. Positive values of the Cpk index are good; negative values are bad. 

5.e. None of the above is true. 

16.If the Cpk index exceeds 1 

1.a.the AQL must be smaller than the LTPD 

2.b.σ must be less than one-third of the difference between the specification and the process mean 

3.c.the x-bar chart must indicate that the process is in control 

4.d.the process is capable of Six Sigma quality 

5.e.the process is characterized as "not capable" 

17.The statistical definition of Six Sigma allows for 3.4 defects per million. This is achieved by a Cpk index of 

1.a. 0 

2.b.1 

3.c.1.33

4. d.1.67

5. e.2 

18.A Cpk index of 1.00 equates to a defect rate of  

1.a. five percent 

2.b. 3.4 defects per million 

3.c. 2.7 per 1,000 items

4. d.97.23 percent 

5.e. one percent 

Reference no: EM13519502

Questions Cloud

Augustine believes corruptible objects : Augustine believes corruptible objects? Two traits of God concerned by the problem of evil are? What does Nietzsche mean when he said “God is dead”?
Analyze the economic feasibility of building the railroad : Analyze the economic feasibility of building the railroad, and outline arguments the company could present to the municipal town councils, the territorial government and the federal government in order to acquire permission to build the railroad and ..
Percent of the time the sample averages will fall inside : If a process has only natural variations, _________ percent of the time the sample averages will fall inside the ± 3σ  n (or ± 3σ x ) control limits.
What is the mean of the sampling distribution : Jars of pickles are sampled and weighed. Sample measures are plotted on control charts. The ideal weight should be precisely 11 oz. Which type of chart(s) would you recommend?
The statistical definition of six sigma allows : The statistical definition of Six Sigma allows for 3.4 defects per million. This is achieved by a Cpk index of
Regarding the average outgoing quality level : Which of the following statements about acceptance sampling is true
Acceptance sampling accepts or rejects an entire lot based : In acceptance sampling, a manager can reach the wrong conclusion if the sample is not representative of the population it was drawn from.
Averages of small samples not individual measurements : Mean charts and range charts complement one another, one detecting shifts in process average, the other detecting shifts in process dispersion.
Which of the types of auction would you recommend : If an auction house is selling products to risk neutral buyers, which of the types of auction would you recommend? If you are a potential buyer, what might your strategy be? Support your answers using economic analysis learned in this course.

Reviews

Write a Review

Finance Basics Questions & Answers

  Estimate the project net present value

What other major factor must be considered to estimate the project's Net Present Value? Why?

  Present value of a perpetuity

Find out the present value of a perpetuity of $100 per year if the appropriate discount rate is 7%?

  In other words determine the impact on interest rates of

in your market view you will refer to the market marker from the country you have chosen e.g. for sibor but also to the

  What is the irr for the gold mine

the cash inflows are projected to grow at 2 percent per year for the next 10 years. After 11 years, the mine will be abandoned. Abandonment costs will be $119,000 at the end of year 11.

  Should the hospital agree to the discount proposal

Now, assume that 20 percent of the hospital's inpatients come from a managed care plan that wants a 25 percent discount from charges. Should the hospital agree to the discount proposal?

  Determine firms fundamental, or intrinsic value

What is a company's fundamental, or intrinsic, value? What might cause a company's intrinsic value to be different than its actual market value?

  Futures contracts and portfolio management

Suppose you can earn 6% riskfree forever. You will need $100,000 in 12 years. A hypothetical riskfree zero coupon bond will "bullet immunize" this cash requirement.

  What is mias self-employment tax

Mia is self employed as a consultant, During 2011, Mia earned $180,000 in self employment income. What is mia's self-employment tax?

  Information about exchange rate calculations

On May 16, the exchange rate of a German mark was $.58. On May 20, the exchange rate is $.57. Which of the following statements is true?

  Selected financial data of two competitors target and

selected financial data of two competitors target and wal-mart are presented here. all dollars are in

  Explore the expected gdp growth of each country and the

questioninvestigate and back up your decision on the question of whether or not it would be more ethical to invest the

  Describe the alternative plans

Assuming the investment banking firm is willing to distribute your securities, describe the alternative plans that might be included in a contract with the banking firm.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd