The standard deviation of activity

Assignment Help Applied Statistics
Reference no: EM13144806

Question 1

A GANTT chart represents mainly

Answer

an immediate identification of predecessor task.

a record-keeping device used in scheduling activities.

a general identifier.

the number of workers directly involved in the project.

Question 2

A PERT/CPM activity has an optimistic time estimate of 3 days, a most likely time estimate of 8 days, and a pessimistic time estimate of 10 days. The expected time (in days) of this activity is:
Answer

7.0

7.5

8.0

8.5

Question 3

A PERT/CPM activity has an optimistic time estimate of 4 days, a most likely time estimate of 6 days, and a pessimistic time estimate of 10 days. The standard deviation of this activity is:
Answer

7/6

1/3

2/3

1.0

Question 4

A list of the tasks, broken down into modules, components, and individual tasks, is called a
Answer

work breakdown structure (WBS).

PERT.

planning matrix.

critical path.

Question 5

A work breakdown structure breaks down a project into
Answer

weeks.

areas.

arcs.

modules.

Question 6

Consider the following project.

 

What is the critical path?
Answer

ACFG

ADFG

BEG

ACDFG

Question 7

Consider the following project.

 

What is the minimum possible time for completing this project?
Answer

15 days

16 days

18 days

20 days

Question 8

Consider the following project.

Compute the slack time for activity C.
Answer

0

4

2

3

Question 9

Consider the following project.

What is the latest possible time that Activity E can be started without delaying the completion of the project?
Answer

8

3

7

9

Question 10

Consider the following project.

What is the latest time that activity B can start without delaying the project?
Answer

0

8

4

7

Question 11

Consider the following project.

What is the latest time that activity B can finish without delaying any other activities?
Answer

0

8

9

4

Question 12

Consider the following project.

Determine the critical path.
Answer

ACEH

BCEH

BDFH

BDGH

Question 13

Consider the following project.

Determine the estimated completion time of the project.
Answer

23 days

22 days

25 days

20 days

Question 14

Consider the following project.

 

Determine the slack for activity D.
Answer

2 days

4 days

6 days

5 days

Question 15

Consider the following project.

Determine the slack for activity F.
Answer

2 days

3 days

4 days

5 days

Question 16

Consider the following project.

How much can activity F be delayed without delaying the project completion?
Answer

1 day

2 days

3 days

4 days

Question 17

Elements of project planning include
Answer

defining project objectives.

identifying activities to crash.

calculating expected times and standard deviations.

conducting a "lessons learned" session.

Question 18

If an activity cannot be delayed without affecting the entire project, then it is a ________ activity.
Answer

completed

critical

crashed

normal

Question 19

If t is the expected completion time for a given activity, then:
Answer

LF = LS - t

EF = ES - t

EF = ES + t

EF = LS - t

Question 20

In a CPM/PERT network the critical path is the
Answer

lowest path through the network.

highest path through the network.

shortest path through the network.

longest path through the network.

Question 21

Joe used a project management software package and has determined the following results for a given project:

What is the probability of completing the project within 20 days?
Answer

0.3849

0.8849

0.1151

0.7642

Question 22

Joe used a project management software package and has determined the following results for a given project.:

What is the probability of completing the project over 20 days?
Answer

0.3849

0.8849

0.1151

0.7642

Question 23


Once a project is underway, the project manager is responsible for the
Answer

people.

cost.

time.

All of these

Question 24


Project control involves
Answer

crashing.

three time estimates.

a backward or forward pass.

earned value analysis.

Question 25

Project management differs from management of more traditional day-to-day activities because
Answer

it has limited time frame.

it has an unlimited budget.

it is more expensive.

it involves more of the workforce.

Question 26

The LS and LF are calculated using the
Answer

backward pass through the network.

forward pass through the network.

values for ES and EF.

backward and forward pass through the network.

Question 27


The activities that must be completed prior to the start of an activity in question are called the immediate ________ of the activity in question.
Answer

successors

predecessors

successors and predecessors

followers

Question 28

The critical path is the ________ path through the network.
Answer

longest

shortest

straightest

most expensive

Question 29


The normal cost for an activity is $7,000 and the crash cost is $12,000. The normal time to complete this activity is 8 days and crash time is 4 days. If this activity is crashed by 2 days it will cost an additional:
Answer

$1000

$1250

$2000

$2500

Question 30


Which of these statements regarding project crashing is true?
Answer

Crashing is not possible unless there are multiple critical paths.

Activities not on the critical path cannot become critical after crashing.

Crashing shortens the project duration by assigning more resources to one or more of the critical tasks.

Crashing a project often reduces the time it takes for lengthy or complex, but noncritical activities.

Save and Submit

Click Save and Submit to save and submit. Click Save All Answers to save all answers. Click Close Window to close window.

Reference no: EM13144806

Questions Cloud

Determine the variable cost component per machine hour : Utilities are typically a ‘mixed cost,' containing both a fixed and variable element. Given the following history of electric bills and machine hours, use the "High/Low Method" to determine the variable cost component per machine hour:
What is the concentration : A urine sample contains 46.5mgL-1 of ethanol. The density of ethanol is 0.79gcm-3. What is the concentration expressed as %v/v
Find mean square-significance of f and omega2 values : Purchase likelihood was measured on a 7-point scale. Complete the table by calculating the mean square, F, significance of F, and Omega2 values.
What is the mass percent of oxygen : A compound contains 14.5 g of magnesium and 3.5 g of oxygen. What is the mass percent of oxygen in the compound?
The standard deviation of activity : What is the latest possible time that Activity E can be started without delaying the completion of the project and what is the latest time that activity B can start without delaying the project
Discuss how research might address these gaps : Discuss how research might address these gaps. Focus on biological or public health hypotheses rather than study designs or logistics.
Statement regarding fixed and variable costs : Which of the following statements is true regarding Fixed and Variable Costs?:
What is the difference between cell and amoeba : What is the difference between cell and amoeba? Please provide five difference?
Calculate the category means and the grand mean : The data obtained from the 30 respondents are shown in the table. Calculate the category means and the grand mean. Show Calculations. Calculate SSy, SSx, and SSerror. Show Calculations.

Reviews

Write a Review

Applied Statistics Questions & Answers

  Calculate the maximum reduction in the standard deviation

Calculate the maximum reduction in the standard deviation

  Study design

What level of evidence does this study design represent?

  Construct a bayesian network for the object recognition

Determine whether this data already provides an expected relative error introduced by the simulation of below 5%. If not, compute how many new simulations you should run in order to reduce the expected relative error introduced by the simulation b..

  Find the prediction interval

what portion of variation in stock price percentage change is explained by the percent change in profit and what is the approximate predicted value for tips if the total bill is $100?

  Calculate the expected value, variance, and standard deviati

Calculate the expected value, variance, and standard deviation of the total income

  Statistical studies

Locate the original poll, summarize the poling procedure (background on how information was gathered), the sample surveyed.

  Compute the mean and sd of the probability

Compute the mean and SD of the probability of the mean and determine the test statistic

  Calculate mortgage rates and production lot size

Calculate mortgage rates, production lot size, forecast the demand for the products, track epidemics and their spread, help solve crimes, even help estimate tax revenues.

  Define the hypothesis and find the standard error

Define the hypothesis and find the standard error of the difference in the means also find the test statistic - Determine the required sample size to be able to use a 99% confidence interval.

  Quantitative analysis for decision making

Internet and the articles database in the library for a real-life illustration of simulation. For hint, type the word "Simulation" followed by a topic of interest to you. Carefully review the search item.

  Compute all relevant summary statistics

You are expected to complete a project related to inferential statistics - show that the random variable X is exponential and compute the probability of the wait time when it is greater

  Calculate the mean and standard deviation

Calculate the mean and standard deviation and Based on these statistics, describe how these anthropometric data compare to the US male and Chinese female populations.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd