The project duration and identifies the critical path

Assignment Help Other Subject
Reference no: EM13230751

SerDoc is a company that manufactures customised medical equipment for hospitals and is about to initiate a project for building a new machine for a recent order from a hospital. The project involves the following six phases: initiating, requirements gathering, design, development and testing, documentation, deployment and testing. The project is scheduled to start on 15 October.

The duration and precedence relationships (or sequencing) between the tasks of the project are provided in the table below:

Phase

Task Name

Task ID

Immediate Predecessor

Time (Days)

Initiating

Defining the scope of the project

1


5

Initiating

Analysing the existing product which is being produced by SerDoc

2


10

Requirements Gathering

Preparing the requirements document and a high-level design

3

1, 2

15

Requirements Gathering

Conducting a proof of concept to validate the approach

4

3

7

Requirements Gathering

Signoff of requirements and a high-level design from the customers who have ordered the machine

5

3

4

Design

Design of hardware components

6

5, 4

20

Design

Detailed product specifications

7

5

30

Design

Detailed program design*

8

7

20

Development and Testing

Manufacturing of the shell of the machine

9

7, 8

40

Development and Testing

Assembling of the electronic components of the machine

10

7

10

Development and Testing

Testing of the circuit for accuracy of responses

11

9, 10

40

Development and Testing

Testing of the manufactured machine and calibration to standards

12

11

15

Documentation

Preparing an installation and user manual

13

Finishes with 8, 12

30

Deployment and Testing

Installation of the machine at the hospital

14

12

5

Deployment and Testing

Conducting trials and checking all functionality at the hospital after installation

15

12, 14

10

Deployment and Testing

Getting client signoff

16

13, 15

0

Deployment and Testing

Training hospital technicians for using the machine

17

12

15

Deployment and Testing

Commissioning of the machine at the hospital

18

8

9

Part

On the basis of the above information, use Microsoft Project to create a project plan that lists project tasks, establishes precedence relationships between tasks, sets precedence relationships, calculates the project duration, and identifies the critical path. While preparing the project plan, categorise the project tasks in the different phases of initiating, requirements gathering, design, development and testing, documentation, and deployment and testing.

What is the end date of the project?

Reference no: EM13230751

Questions Cloud

Describe the additional factors that impact global supply : Based on the concept of globalization, many businesses operate and compete in a global environment. Describe the additional factors that affect/impact global supply chains.
Explain the genetic variation : How would the research programs of the two schools have influenced their perceptions about the amount of genetic variation present in the wild?
Estimate the electron and hole drift velocity : Consider an n-Si with doping of 9*10^16cm^-3. In a certain region of this sample, there is an electric field of 1000V/cm. Estimate the electron and hole drift velocity and the total drift current density in that region.
What is the maximum possible output per week for this line : An assembly line with 7 tasks is to be balanced. The longest task is 8 minutes, the shortest task is 2 minutes, and the sum of the task times is 53 minutes. The line will operate for 6 hours per shift, 1 shifts per day, 6 days per week.
The project duration and identifies the critical path : Calculates the project duration, and identifies the critical path. While preparing the project plan, categorise the project tasks in the different phases of initiating, requirements gathering, design, development and testing, documentation, and de..
Compute the molar mass of the unknown gas : Calculate the molar mass of the unknown gas. Remember that the faster the rate of effusion, the shorter the time required for effusion; that is, rate and time are inversely proportional.
Compute the equilibrium carrier concentrations : Compute the equilibrium carrier concentrations and the position of the Fermi level with respect to the conduction band edge for a uniformly doped Si region with N_D=1*10^16 cm^-3 and N_A = 1*10^17 cm^-3 at room temperature.
What is the minimum sales quantity that would justify : What is the minimum sales quantity that would justify the purchase of new equipment?
State standardized against a standard solution of hcl : If 1L of .15M NaOH is unprotected from mmol of CO2, what will be its new molarity when it is standardized agains a standard solution of HCl using

Reviews

Write a Review

Other Subject Questions & Answers

  Sociology-locus of control

In 500 words, explain what intake you can get from a sociology class. Show how to apply locus of control and how you take the external and make it as internal.

  Antisocial personality disorder multi-axial diagnosis

I've the following case study to diagnose. I'm sure it is 301.7 Antisocial Personality Disorder. But often there're other disorders that accompany this. Any thoughts or suggestions that I may have overlooked would be appreciated.

  Example of a healthcare partnership

Discuss an example of a healthcare partnership in your community and specifically cite examples that show how nurses, both individually and collectively, influenced the care provided.

  Personal model of helping

Make a paper APA formatted on your personal model of helping. Incorporate learning from this course and describe how and why you have, at this point in your development, formed your viewpoint.

  Engagement with foreign policy strategies

Write a 200 to 300-word response comparing Nixon’s policies of engagement with foreign policy strategies used during the Cold War.

  Anarchy and state response

What are the effects of anarchy on state behavior according to Neo-Realists? Do you agree? Be sure to provide examples and discuss alternative views.

  Major disaster event

Identify a major disaster event. Describe the event and compare local, state, and federal response. Identify and provide an analysis of specific emergency management functions that appear to have been executed well and those that may not have be..

  Sumarize victims cause-signs-symptoms

A way to sumarize victims causes/signs/symptoms, whos to blam, and prevention all into one sentence for my reasearch paper on teen suicide.

  Marriage ritual in brazil

You are required to write a paper (10-12 double-spaced pages) that is based on both library research and fieldwork conducted on the topic selected. This means I am expecting a minimum of 3 scholarly researches about your topic in the bibliography,..

  Discuss the difficulties facing eastern european countries

Discuss the difficulties facing the eastern european countries accession to the EU in 2004 and 2007. Have accession being in the best interest of EU citizens and businesses

  Describe the language and rhetoric

Provide an explanation of whether these groups invoke the same image to all persons, and if the stereotypes are positive, negative, or both. Describe the language and rhetoric that is used to reinforce the stereotype of each group.

  Dialogue between three philopshers

Develop a dialogue between three philopshers in which they discuss the following question: The epistemology of relativism is assumed to be true by many people.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd