Reference no: EM132308459
1. The project environment includes not only the physical space where the team will work, but also the project culture as well. True or False
2. Projects are planned organizational change. Therefore, the project manager and team do not need to worry about the political climate within the organization because top management has a firm understanding of the organization’s culture, environment, politics, etc. True False
3. After a brain storming session, you realize that it will take additional work to record the assumptions the risk. you believe it is worth the time to do so in order to:
1. Comply with legal requirements
2. avoid anomalies from inconsistent assumptions
3. keep the project manager busy
4. The process that includes generating a list of risks and their characteristics is called:
Plan Procurement
Plan Risk Responses
Identify Risks
5. you are concerned that the hypotheses scenarios on which the detailed WBS and task list were created may have changed. To identify risks that may result from inaccurate or inconsistent or incomplete understanding of this elements, you would use:
an influence diagram
assumptions analysis
documentation reviews