The case of the never ending scope creep

Assignment Help Operation Management
Reference no: EM132163078

Case Study: The Case of the Never Ending Scope Creep

In 1999, the XY Department of the Federal Government reviewed its Year 2000 Date Turnover Computer Risks and found that its outdated computer systems for managing public clients needed replacing. A business case was prepared for funding the replacement while at the same time implementing some improvements. The total budget requested was $2.3 million.

In view of a shortage of funds around at the time, government did not approve this amount. Only $1.5 million was authorized. However, the XY Department accepted this amount after they decided that they could maybe do the work for around the $1.5 m.

Accordingly, a project was scoped and planned, with specific milestones for implementing the hardware and, subsequently the software, across 87 sites within its jurisdiction. A final completion date of 30th June 2001 was projected. The original business case had loosely identified some risks to the project that were also included in the project plan. A project steering committee was established, with the department chief (CEO) as the sponsor, and representation by influential managers with differing outcome needs to suit their particular work environment. The project commenced in July 1999.

In view of the shortfall on its original budget request, the committee decided not to employ a project manager. Instead it assigned this responsibility to its Finance Manager, who would undertake the work along with his normal duties.

A Company, called "Good Programs" was contracted to supply the software and assist in the implementation. This company recognized the marketing opportunities of this project, as the XY Department was its biggest client in the region. As a result, they offered, free of charge, many more features that were not in the original scope, provided the department allowed them to be, in essence a research and development (R&D) site. This would assist Good Programs to more readily sell their products elsewhere around the world, while providing the XY Departmentwith additional functionality and benefits.

Initially, the steering committee met regularly, but as new versions of the resulting software were being implemented regularly, meetings became less frequent and Good Programs were left to do more and more of the day to day management of the new version implementations.

These new versions were developed after consultation with the various individual managers to accommodate requested new features with little consultation amongst all of the managers. All the XY Department and steering committee had to do was to identify problems with the software and to make the system testers available for new versions. However, the effect was an unanticipated overhead for the department.

Sometime after the original project was scoped and commenced, both the original CEO and finance manager had been moved out of the department and new officers have been appointed.

At this time, the new CEO has been advised that about $185,000 more is needed for the project, which is not in his current budget. The original project has not been signed off, indeed, it is evident that it has not been completed. The new CEO of the department is not sure of the original scope of the project, what aspects have been implemented, nor what has been spent for which parts. There do not seem to be any reliable reports available as to original scope, scope changes, schedule or budget.

The CEO is concerned that the project has become more of a career than a project, with version 16.5 of the client management system now being tested with yet more features. In addition, there are some past software problems that are still outstanding. Nevertheless, Good Systems have promised that problems will be fixed in the next version ... .

You are a senior consultant with PM Right Track (PMRT), a competent project management consulting company. The CEO has called you in for advice. The information is brief, but this is all the information that he and the new finance manager are able to provide. The CEO's mandate to you is to:

1. Report your assessment of the current project status.

2. Compare your assessment with sound project management practices.

3. Recommend steps to bring the project to a close.

4. Recommend improvements to the XY Department's future project management practices.

5. If a very similar project had to be done again, what attributes and/or skill sets would you recommend in selecting a project manager?

6. What other advice might you give to the CEO?

Reference no: EM132163078

Questions Cloud

Review technique with the critical path method : Compare and contrast the project evaluation and review technique (PERT) with the critical path method (CPM).
Description can focus on existing service : Your description can focus on an existing service, e.g. an accommodation provided by WIUT for students etc.
Describe the elements necessary to prove libel : List and briefly describe the elements necessary to prove libel.
Your choice on hofstede dimensions of culture : Compare how the United States differs from another country of your choice on Hofstede's dimensions of culture.
The case of the never ending scope creep : Project was scoped and planned, with specific milestones for implementing the hardware and, subsequently the software, across 87 sites within its jurisdiction.
Using rational or nonrational means of persuasion : Nussbaum is clearly trying to persuade us. Is she using a rational or a nonrational means of persuasion? Explain your answer.
Consultant presents many different benefits to organization : Instructions Hiring a consultant presents many different benefits to the organization.
Quality according to the traditional view with modern view : Explain at least 5 basic concepts of difference from the notion of quality according to the traditional view with the modern view?
Interact with regularly and list as many different systems : Choose an organization that you interact with regularly and list as many different “systems” as you can that are used to process transactions

Reviews

Write a Review

Operation Management Questions & Answers

  Book review - the goal

Operations Management is about a book review. Title of the book is "Goal". This book has been written by Dr. Eliyahu Goldartt. The book has been appreciated by many as one of those books which offers an insight into the operations and strategic capac..

  Operational plan in hospitality enterprise

Operational plan pertaining to a hospitality enterprise is given in detail in the solution. The operational plan is an important plan or preparation which gives guidelines regarding the role and responsibilities of each and every operation at all lev..

  Managing operations and information

Recognise the importance of a strategic approach to the development and deployment of organisational information systems. Demonstrate an understanding of the importance of databases and their integration to the organisation's overall information mana..

  A make-or-buy analysis

An analysis of the holding costs, including the appropriate annual holding cost rate.

  Evolution and contributor of operations management

Briefly explain Evolution and contributor of Operations management.

  Functions and responsibilities of an operations manager

A number of drivers of change have transformed the roles, functions and responsibilities of an operations manager over recent years. These drivers have not only been based on technological innovations but also on the need for organisations to develop..

  Compute the optimal order quantity

Compute the Optimal Order quantity of DVD players. Determine the appropriate reorder point.

  Relationship to operations practice in the organisation

Evaluate problems in operations and identify approaches to overcoming them. Critically evaluate operating plans and identify areas for improvement. Justify, implement and evaluate changes to operations in line with modern approaches.

  A make or buy analysis

Develop a report for Figi Fabricating that will address the question of whether the company should continue to purchase the part from the supplier or begin to produce the part itself.

  Prepare a staffing plan

Prepare a staffing plan showing the change of your unit from medical/surgical staffing to oncology staffing.

  Leadership styles in different organizations

Ccompare the effectiveness of different leadership styles in different organizations

  Risk management tools and models

Be able to understand the concept of risk, roles and responsibilities for risk management and risk management tools and models.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd