The average time for the 20 missile guidance controls

Assignment Help Operation Management
Reference no: EM13321260

United Research Associates (URA) had received a contract to produce two units of a new cruise missile guidance control. The first unit took 4,000 hours to complete and cost $30,000 in materials and equipment usage. The second took 3,200 hours and cost $21,000 in materials and equipment usage. Labor cost is charged at $18 per hour.

The prime contractor has now approached URA and asked to submit a bid for the cost of producing another 20 guidance controls.

a. What will the last unit cost to build?

b. What will be the average time for the 20 missile guidance controls?

c. What will the average cost be for guidance control for the 20 in the contract?

Reference no: EM13321260

Questions Cloud

Suppose you hold a corporate bond that is convertible into : Suppose you hold a corporate bond that is convertible into the firm"s stock. Stock prices are falling and interest rates are also falling. Would it be a good idea to exercise your conversion option under these conditions? Why?
Evaluate the pressure of oxygen for a system in equilibrium : Calculate the pressure of oxygen for a system in equilibrium in which [NH4+] = [NO3-] at pH 7.00
Find his expected yield assuming the bond is sold in 2 year : David Hoffman purchases a $1,000 20-year bond with an 8 percent coupon rate (annual payments). Yields on comparable bonds are 10 percent. David expects that
Derive equation for the torque in terms including resistance : A movable cone fits inside a stationary conical depression. If a torque is applied to the cone, the cone will rotate at a certain speed depending on the angles θ and β, the radius r o, and the viscosity μ of the liquid.
The average time for the 20 missile guidance controls : What will be the average time for the 20 missile guidance controls
Explain the two types of interest rate risk : Define interest rate risk. Explain the two types of interest rate risk. How can an investor with a given holding period use duration to reduce interest rate risk?
Explain when mg is added directly to the beaker of hcl : What quantity of useful work can be obtained when Mg is added directly to the beaker of HCl. How can you harness this reaction to do useful work
How different is your answer from the actual price change : Calculate the duration for a $1,000, 4-year bond with a 4.5 percent annual coupon, currently selling at par. Use the bond"s duration to estimate the percentage change in the bond"s price for a decrease
Discuss how the nec3 form of contract provides stimulus : Discuss how the NEC3 form of contract provides stimulus to good management and compare and contrast this where possible with other forms of contract.

Reviews

Write a Review

Operation Management Questions & Answers

  Determine the crossover point for the two options

The owner of a motel is considering outsourcing the daily room cleanup to Duffy's Maid Service. The manager rents an average of 50 rooms for each of 365 nights.

  Examine the uncertainty regarding the success or failure

he is likely to be optimistic about the others as well. For you simulation, this means that if on probability increases, the others are likely to increase. How might you incorporate this information into your simulation?

  What actions the company should take to better satisfy

Describe the potential strategies that are revealed by aligning Henkel's internal strengths and weaknesses with existing opportunities and threats in the external environment.

  What organizational systems are impacted by the cycle

What organizational systems are impacted by the cycle of change? Explain. What systems are not as easily impacted by change? Why or why not?

  What steps would you suggest to manage the transition

What steps would you suggest to manage the transition from the old organizational structure to the new, How would you assess the external environment and integrate this into the turn-around plan

  Describe and discuss the cost and value benefits of pet elam

Describe and discuss the cost and value benefits of Pet Elam's products and services to its customers?

  Inform top management of the concerns expressed

Inform top management of the concerns expressed by the employees and design a set of recommended steps that management can follow to deal with the challenges of downsizing.

  Business with customers in developing nations

Companies that do business with customers in developing nations that lack access to hard currencies are likely to make extensive use of:

  How an organization use different component of marketing mix

Select an organization with which you are familiar. How does your selected organization use the different components of the marketing mix?

  What is the optimal order size

The jewelry firm operates 200 days per year. Usage rate is 25 stones per day, and ordering costs are $48. If annual carrying costs are 30 percent of unit cost, what is the optimal order size?

  One way to empower buyer and seller

Procurement." One way to empower buyer and seller organizations to approve all project transactions is to include a caveat that lawyers from both sides must agree on a set of terms and conditions.

  The dilemma of an inactive business line

"Managers at iGlobal, an IT solutions company, are faced with the dilemma of an inactive business line. The product line was launched seven years back but it could not respond to changing demands and trends

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd