Supply chain has the following jobs waiting to be processed

Assignment Help Operation Management
Reference no: EM13710200

41. (7 points) A distribution center in a supply chain has the following jobs waiting to be processed. All jobs (sets of products requiring repackaging) must first be sorted into groups at one workstation, then packaged at a second workstation.

Job J1 J2 J3 J4 J5
Cleaning Time 9 4 5 3 8
Waxing Time 6 5 10 2 3

a. The distribution center would like to repackage the products for these five jobs in the shortest total time possible. What processing sequence will minimize the makespan for these jobs?

b. What is the minimum makespan for this set of five jobs?

43. (7 points) From a process known to be in control, 5 samples of 7 units each were taken at random intervals and the units in the samples were weighed. The mean (Xbar) and range (R) for each of the six samples are given in the following table.

Sample Mean Range
1 7.1 0.5
2 7.5 1.0
3 7.0 1.1
4 7.4 0.9
5 7.3 0.6
_
a. Calculate the 3? X-chart and R-chart control limits.

b. Calculate the mean (X) and range (R) for the following sample, which was taken from the same process at a later time.

Item number: 1 2 3 4 5 6 7
Weight: 7.6 7.9 8.1 7.6 7.5 7.7 8.0


44. (7 points) A company stocks a component that costs $6 per unit. Annual usage of this item is expected to be 3640 units. The firm is open for business 52 weeks per year, so weekly demand is 70 units per week, with a standard deviation of 10 units. The firm's cost accountants have estimated that it costs $80 every time an order is placed for more components, and that carrying the item in inventory costs about $15 per unit per year. Past experience with their supplier indicates that the time from ordering more items to receipt of the shipment of those items is 21 days (assume they are open 7 days per week).

a. What quantity should be ordered each time? (Assume that the EOQ assumptions apply.)

b. What is the minimum total annual cost (ordering + holding + purchase) for managing this inventory item?


c. If the company decided that their JIT program required frequent small orders and deliveries (assume that this would mean ordering a quantity of 20 units every other day, instead of the EOQ quantity on a less frequent basis), and the costs remain the same as described above, how much higher would the total annual cost be for this item?


d. If a 90% service level is required, what reorder point should be used?

45.  The following table represents the set of activities required to complete a project, along with their time estimates for PERT calculations.

a. Using the data, calculate the expected time and variance for each activity.

Job Number Predecessor Job(s) a m b ET variance
A --- 1 2 3
B A 4 5 6
C A 1 4 7
D B 1 3 5
E B, C 3 4 11
F D,E 2 4 6

b. Sketch the network diagram for the project.

c. Indicate the critical path. (You can do this by inspecting the paths - you do not have to calculate ES, EF, LS, LF). What is the expected completion time for the project?

d. What is the probability that the project will take more than 19 days to complete?

46.  Of the topics that we covered in this course, which one or ones were the most interesting and/or useful to you? Why?

Reference no: EM13710200

Questions Cloud

List the nine major hazard classes as outlined by the u.s : List the nine major hazard classes as outlined by the U.S Department of Transportation (D.O.T.). Research a news article that covers one of the nine major hazard classes. Identify the hazard and explain how the hazard created the dangerous sit..
Describe costs of home care vs. facility care for seniors : Explain the costs of home care vs. facility care for seniors and describe whether home care for the aging is more cost effective than care provided in skilled nursing facilities.
Assumptions underlie the bcg growth-share matrix : Response to Discussion Questions due by midnight on Thursday. 2 Sources Required in APA format. 1.What concepts or assumptions underlie the BCG growth-share matrix? Are these concepts valid? Why or why not?
A company is going to introduce a new cell phone : A company is going to introduce a new cell phone.  ABC Cell Services is going to sell the phones and has established specification limits of 5.0 ounces
Supply chain has the following jobs waiting to be processed : 41. A distribution center in a supply chain has the following jobs waiting to be processed. All jobs (sets of products requiring repackaging) must first be sorted into groups at one workstation, then packaged at a second workstation.
Describe the indigenous people and assimilation : What is an issue indigenous people face regarding assimilation. Describe this issue and any effort made to mitigate it. How effective were these efforts.
Explain the effects of downsizing the us military : Can anyone find me an interesting article or two on where the US Military will be downsizing troops- officers, enlisted etc.
Compare and contrast job design approaches : Compare and contrast job design approaches and their relevance to an employee's job performance. Identify and discuss the five core job characteristics in the Job Characteristics Model, and describe the three strategies for improving employee ..
Explore the design method : Why is qualitative, quantitative and mixed method design necessary in management research. What benefits doe's management research provide for organizations.

Reviews

Write a Review

Operation Management Questions & Answers

  Explain why goods analogy of a supply chain is inappropriate

Explain why the goods analogy of a supply chain is inappropriate for services (400-500 words)

  At maximum operator speed how long will it take each device

How many can you test completely in an 8 hour shift with a 30 minute luch break?

  Briefly describe the processes and practices

Briefly describe the processes and practices to help new employees get set up at either your current or a previous company. Was there a formal orientation process? If so, what did it include and what did it omit, and which elements of the process ..

  Calculate the average number of boats

The new Fore and Aft Marina is to be located on the Ohio River near Madison, Indiana. Assume that Fore and Aft decides to build a docking facility where one boat at a time can stop for gas and servicing.

  What annual rate of interest is being earned on this fund

On January 1, 2005, a person's savings account was worth $200, 000. Every month thereafter, this person makes a cash contribution of $676 to the account. If the fund is expected to be worth $400,000 on January 1, 2010, what annual rate of interest..

  What is the project completion date

Bowman Builders manufactures steel storage sheds for commercial use, Joe Bowman, president of Bowman Builders, is contemplating producing sheds for home use. The activities necessary to build an experimental model and related data are given in the..

  Prepare a balance sheet from the list of assets

Explain how the balance sheet will change for each of the following transactions. Prepare a balance sheet from the following list of assets and liabilities, regarding the ownership interest as the missing item.

  Identified that joe has a high need for achievement

You manage a department of four employees. You have identified that Joe has a high need for achievement. Mary has a high need for power, and Tim has a high need for affiliation

  Verify the prospective partners capabilities

approach prospective clients to get their perpective on the agreement and esure that there is a market for the new technology they want to develop.

  List three significant items that belong in a project

list three important items that belong within a project management plan and the importance of breaking the project into

  Calculating the yield to maturity

What is the yield to maturity of a 16-year bond that pays a coupon rate of 8% per year, has a $1,000 par value, and is currently priced at $916?

  Conducting an important business meeting

You are in a crowded conference room conducting an important business meeting when the ceiling springs a major leak and water falls from the ceiling tiles all over the conference table.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd