Supply-chain challenges in post-earthquake japan

Assignment Help Operation Management
Reference no: EM131472747

Supply-Chain Challenges in Post-Earthquake Japan

Japanese automakers have long been known for the quality of their products, and especially for the efficiency of their stream-lined manufacturing and supply processes. Thus, few people could have predicted how severely the destructive earthquake and tsunami that struck Japan in March 2011 would disrupt the country’s entire auto industry. Matters were further compli-cated by the damage the quake and floodwaters caused to one of Japan’s nuclear power plants, interrupting power supplies around the country and creating a dangerous radiation zone for miles around the plant.

Following the quake and ensuing floods, most automotive factories in Japan were closed for at least several weeks, bring-ing to a halt about 13% of worldwide auto production. Toyota, Honda, and Mazda shut down many of their parts and manu-facturing plants in Japan, and Toyota also announced plans to

suspend production in at least one North American plant be-cause of parts shortages. The company said it would make plant improvements and run training programs in its other U.S. facil-ities while the assembly lines were idle or run operations on a part -time basis to conserve its parts inventory. Honda, Nissan, and Subaru also reduced their North American output as they anticipated and tried to deal with expected parts shortages.

Since one of the guiding principles of Lean production is to keep parts inventories as low as possible, it wasn’t long before these shortages occurred. “The supply chain in the automotive industry is so fragile,” said one legal advisor to the global auto industry. “It’s based on just-in-time principles, where you don’t have a lot of inventories built up, so you leave yourself without much margin for error when a supply interruption happens.”

Industry observers predicted that about half of Japan’s auto capacity would remain closed for at least eight weeks after the disaster, which would eventually put about one -third of world-wide production in jeopardy, as the effects of parts shortages made themselves increasingly felt in manufacturing facilities far from Japan. One auto industry research firm predicted that about five million cars that the industry had expected to sell in 2011 would never be made.The disaster zone in Kesennuma, Miyagi prefecture, 100 days after a mas-sive 9.0-magnitude earthquake and tsunami devastated the northeastern coast of Japan.

By spring and summer 2011, in fact, U.S. auto dealers were reporting what one called “a lot of emptiness” in their show-rooms. Many logged dwindling sales as supplies fell to as little as one- fifth their normal levels, and popular cars such as the Honda Civic and Accord went out of stock. Without new cars to sell, even trade- in sales were slowing. Honda posted a 27% decline in sales for August 2011, and Toyota anticipated a dra-matic 31% profit decline for the year. Although the Japanese auto industry worked hard to quickly return to full capacity, output was still not fully restored some six months after the di-saster. The disaster’s long-lasting ripple effects thus motivated industry executives to consider some changes in their vaunted manufacturing and supply operations. Traditionally, Toyota had used a single source for many parts that were common to more than one of its car models. Although the company locally sources about 85% to 90% of parts and materials needed for its North American manufacturing operations, a strategy that should make it less vulnerable to supply interruptions in Japan, it actually builds a larger proportion of its vehicles in Japan than do the other automakers, so the 2011 disaster was a seri-ous blow.

In response to these problems, Toyota’s management be-gan work to “foolproof ” the supply chain so that it could re-cover from major interruptions in as little as two weeks. The plan had three parts. First, Toyota would increase standard-ization of auto parts so all Japanese carmakers could share the supply. These parts would be made in several locations to ensure uninterrupted supply. Next, the company asked its upstream suppliers of highly specialized parts, or parts that are sourced from only one location, to hold larger inventories than they had been carrying, as and opened up new options for manufacturing such parts to reduce its dependence on single sources. Finally, and perhaps most ambitiously, Toyota took steps to make each of its global regions independent of the others in terms of parts supply, so supply chain disrup-tions in one area will not spill over into the operations of any other areas.

Questions

1. What are some of the advantages of the supply chain used in the Japanese auto industry before the March 2011 earth-quake and tsunami? What were some of its disadvantages?

2. Is Toyota’s plan for a “foolproof ” supply chain consistent with the Lean production philosophy? Explain.

3. Can you think of any additional ways Toyota (and its competitors in the Japanese auto industry) can improve upon the company’s plan to create a “foolproof ” supply chain?

4. What impact do you think Toyota’s plan will have on the way it handles relationship management in its supply chain?

Reference no: EM131472747

Questions Cloud

What is the applicable legal standard courts : What is the applicable legal standard courts use to determine whether copyright infringement has occurred?
Similarities between a mission-vision and value statement : Explain the differences and similarities between a mission, vision, and value statement.
Once or twice during the strategic planning process : Once or twice during strategic planning process, stepping back to take overall look at what has been accomplished.
Lead to human error in the human factors theory : Discuss the factors that lead to human error in the human factors theory.
Supply-chain challenges in post-earthquake japan : Japanese automakers have long been known for quality of their products and especially for efficiency of their stream-lined manufacturing and supply processes
Resistance and encourage employees to exercise self-control : How can a supervisor help overcome such resistance and encourage employees to exercise self-control?
When you think about an entrepreneur : What is the first thing that comes to your mind when you think about an Entrepreneur?
Seven barriers to rational analysis of disruption in project : “Seven Barriers.” There are seven (7) barriers to rational analysis of disruption in the project.
What is the porter hypothesis : What is the Porter Hypothesis (PH)? How is the PH inconsistent with traditional microeconomic theory?

Reviews

Write a Review

Operation Management Questions & Answers

  Book review - the goal

Operations Management is about a book review. Title of the book is "Goal". This book has been written by Dr. Eliyahu Goldartt. The book has been appreciated by many as one of those books which offers an insight into the operations and strategic capac..

  Operational plan in hospitality enterprise

Operational plan pertaining to a hospitality enterprise is given in detail in the solution. The operational plan is an important plan or preparation which gives guidelines regarding the role and responsibilities of each and every operation at all lev..

  Managing operations and information

Recognise the importance of a strategic approach to the development and deployment of organisational information systems. Demonstrate an understanding of the importance of databases and their integration to the organisation's overall information mana..

  A make-or-buy analysis

An analysis of the holding costs, including the appropriate annual holding cost rate.

  Evolution and contributor of operations management

Briefly explain Evolution and contributor of Operations management.

  Functions and responsibilities of an operations manager

A number of drivers of change have transformed the roles, functions and responsibilities of an operations manager over recent years. These drivers have not only been based on technological innovations but also on the need for organisations to develop..

  Compute the optimal order quantity

Compute the Optimal Order quantity of DVD players. Determine the appropriate reorder point.

  Relationship to operations practice in the organisation

Evaluate problems in operations and identify approaches to overcoming them. Critically evaluate operating plans and identify areas for improvement. Justify, implement and evaluate changes to operations in line with modern approaches.

  A make or buy analysis

Develop a report for Figi Fabricating that will address the question of whether the company should continue to purchase the part from the supplier or begin to produce the part itself.

  Prepare a staffing plan

Prepare a staffing plan showing the change of your unit from medical/surgical staffing to oncology staffing.

  Leadership styles in different organizations

Ccompare the effectiveness of different leadership styles in different organizations

  Risk management tools and models

Be able to understand the concept of risk, roles and responsibilities for risk management and risk management tools and models.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd