Show this operation on a linear schedule

Assignment Help Civil Engineering
Reference no: EM13564904

A project consists of replacing the track on an existing railroad line, involving 3000 feet of track. The old track can be removed at a rate of 70 feet per hour. The old railroad ties can be removed at a rate of 200 feet (measured along the track) per hour. The new ties can be installed at a rate of 25 feet per hour and the replacement track can be installed at a rate of 40 feet per hour. Show this operation on a linear schedule. Assume that the minimum float for an activity at any location is one day.

Reference no: EM13564904

Questions Cloud

Determine the improvement in efficiency and circulation rate : Now you want to improve the efficiency and circulation rate. You suggest operaing the cycle utilizing two reversible tubines with saturated vapor exit streams. All conditions remain the same except that the feed to the first turbine is steam at 450 C..
Estimate the flow rate of water required to make the outflow : A mixing chamber has two steady streams and one steady stream. The properties of the first stream is superheated steam at T1 = 400oF, h1 = 1,239 Btu/lbm and flow rate m1 = 20 lbm/h. The second stream is compressed liquid at T2 = 70oF, h2 = 38 Btu/lbm..
Determine the volume flow rate of the steam at the nozzle : A steady-state, well-insulated turbine operates in two stages in series using steam. the first stage has an efficiency of 85% and the second stage 90%. Steam enters the first stage at 400 C and 4 MPa and exits at 1.5 MPa.
Determine the volume flow rate for this particular water : Everyone has experienced using a water fountain that produces a bit too much water pressure. In fact, the drinking fountain on the 3rd floor of Dana Hall at the south end of the hallway shoots a pretty good jet of water
Show this operation on a linear schedule : A project consists of replacing the track on an existing railroad line, involving 3000 feet of track. The old track can be removed at a rate of 70 feet per hour. The old railroad ties can be removed at a rate of 200 feet (measured along the track) pe..
What is the project duration if no activities are to be : A 1500-foot subdivision street is to be constructed. The layout will be completed in three days; the fill will be brought in over the course of eight days; the compaction/grading will be completed in five days
Find the effective angle of shearing resistance of sand : An adiabatic compressor is used to bring saturated water vapor at a pressure of 103 lbf/in^2 up to 1000 lbf/in^2, where the actual exit temperatureis 1000 F. Find the compressor fficiency an the entropy generation. Is there a improvement by reducing ..
Estimate the angle through which the part rotates : A machine part rotates at an angular speed of 0.60 rad/s; itsspeed is then increased to 2.2 rad/s at an angular acceletation of0.70 rad/s2
What is the increase in tempterature of the water : The apparatus show in firgure P11.8 was used by Joule tomeasure the mechanical equivalent of heat. what is the increase in tempterature of the water

Reviews

Write a Review

Civil Engineering Questions & Answers

  Estimate the power in watts that can be produced by

An engineer is considering the development of a small wind turbine(D=1.25m) for home applications.The design wind speed is 15mph at T=10 degree celsus and p=0.9 bar.The efficiency of the turbine is n=20%,meaning that 20% of the kinetic energy in the ..

  How long will it take the water in the aquifer to travel

A truck spils 1 gallon of benzene into an aquifer with an area= 50ft^2 Benzene has a solubility of 1750 ppm, and a specific gravity of 0.873. The aquifer ahs a porosity of 0.25, a hydraulic gradient of 0.004 and a hydraulic conductivity of 1000 gpd/f..

  X y and z coordinates of point b for radial readings taken

Calculate the X, Y and Z coordinates of point B for radial readings taken to B from occupied station A, if the backsight azimuth at A is 25°32'48", the elevation of A = 610.098 m, and hi = 1.45 m

  Determine the maximum value of the average normal stress

Knowing that each member has a 2 3 4-in. rectangular cross section and that each pin has a 12 -in. diameter, determine the maximum value of the average normal stress (a) in member BE, (b) in member CF.

  What is velocity in the channel before the hydraulic jump

Water flows uniformly at a depth of y1 = 40 cm in the rectangular troweled concrete channel shown, which is 10 m wide and has a bed slope of So = 0.040 . What is the velocity in the channel before the hydraulic jump

  Find the probability that the student

Suppose that in a senior college class of 500 students it is found that 210 smoke, 258 drink alcoholic beverages, 216 eat between meals, 122 smoke and drink alcoholic beverages

  Determine what is the resulting solids concentration

Raw primary sludge at a solids concentration of 4% is mixed with waste activated sludge at a solids concentration of 0.5%. The flows are 20 and 24 gal/min, respectively. What is the resulting solids concentration

  Determine the force in each member

The truss shown consists of 9 members and is supported by a ball and socket at A, two short links at B, and one short link at G. Check that this truss is a simple truss, that it is completely constrained

  Determine the settlements having stress

The soil properties of the clay are Cc = 0.25, Cr = 0.05, gsat = 18 kN/m 3 , for the sand gsat = 18 kN/m 3 , and the water table is 2 m below the soil surface. Determine the settlements when a stress of 100 kPa is applied by the building over an a..

  Determine the cohesion and the angle of friction of the soil

Undrained shear box tests were carried out on a series of soil specimens with the following results:Total normal stress (kPa) Total shear stress at failure (kPa)

  What are the rotational velocity in rpm and linear velocitie

One form of which consists of three equal weights joined by equal length ropes. The gaucho holds on to one weight spinning the bolas overhead. When the bolas is cast the weights cause the configuration to change

  What pressure in mpa must be applied to water to reduce

At 25 C, approximately what pressure in MPa must be applied to water to reduce its volume by 2%

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd