Question 1 a gantt chart represents mainlyanswer an

Assignment Help Applied Statistics
Reference no: EM13375132

Question 1

A GANTT chart represents mainly

Answer

an immediate identification of predecessor task.

a record-keeping device used in scheduling activities.

a general identifier.

the number of workers directly involved in the project.

Question 2

A PERT/CPM activity has an optimistic time estimate of 3 days, a most likely time estimate of 8 days, and a pessimistic time estimate of 10 days. The expected time (in days) of this activity is:
Answer

7.0

7.5

8.0

8.5

Question 3

A PERT/CPM activity has an optimistic time estimate of 4 days, a most likely time estimate of 6 days, and a pessimistic time estimate of 10 days. The standard deviation of this activity is:
Answer

7/6

1/3

2/3

1.0

Question 4

A list of the tasks, broken down into modules, components, and individual tasks, is called a
Answer

work breakdown structure (WBS).

PERT.

planning matrix.

critical path.

Question 5

A work breakdown structure breaks down a project into
Answer

weeks.

areas.

arcs.

modules.

Question 6

Consider the following project.

 

What is the critical path?
Answer

ACFG

ADFG

BEG

ACDFG

Question 7

Consider the following project.

 

What is the minimum possible time for completing this project?
Answer

15 days

16 days

18 days

20 days

Question 8

Consider the following project.

Compute the slack time for activity C.
Answer

0

4

2

3

Question 9

Consider the following project.

What is the latest possible time that Activity E can be started without delaying the completion of the project?
Answer

8

3

7

9

Question 10

Consider the following project.

What is the latest time that activity B can start without delaying the project?
Answer

0

8

4

7

Question 11

Consider the following project.

What is the latest time that activity B can finish without delaying any other activities?
Answer

0

8

9

4

Question 12

Consider the following project.

Determine the critical path.
Answer

ACEH

BCEH

BDFH

BDGH

Question 13

Consider the following project.

Determine the estimated completion time of the project.
Answer

23 days

22 days

25 days

20 days

Question 14

Consider the following project.

 

Determine the slack for activity D.
Answer

2 days

4 days

6 days

5 days

Question 15

Consider the following project.

Determine the slack for activity F.
Answer

2 days

3 days

4 days

5 days

Question 16

Consider the following project.

How much can activity F be delayed without delaying the project completion?
Answer

1 day

2 days

3 days

4 days

Question 17

Elements of project planning include
Answer

defining project objectives.

identifying activities to crash.

calculating expected times and standard deviations.

conducting a "lessons learned" session.

Question 18

If an activity cannot be delayed without affecting the entire project, then it is a ________ activity.
Answer

completed

critical

crashed

normal

Question 19

If t is the expected completion time for a given activity, then:
Answer

LF = LS - t

EF = ES - t

EF = ES + t

EF = LS - t

Question 20

In a CPM/PERT network the critical path is the
Answer

lowest path through the network.

highest path through the network.

shortest path through the network.

longest path through the network.

Question 21

Joe used a project management software package and has determined the following results for a given project:

What is the probability of completing the project within 20 days?
Answer

0.3849

0.8849

0.1151

0.7642

Question 22

Joe used a project management software package and has determined the following results for a given project.:

What is the probability of completing the project over 20 days?
Answer

0.3849

0.8849

0.1151

0.7642

Question 23


Once a project is underway, the project manager is responsible for the
Answer

people.

cost.

time.

All of these

Question 24


Project control involves
Answer

crashing.

three time estimates.

a backward or forward pass.

earned value analysis.

Question 25

Project management differs from management of more traditional day-to-day activities because
Answer

it has limited time frame.

it has an unlimited budget.

it is more expensive.

it involves more of the workforce.

Question 26

The LS and LF are calculated using the
Answer

backward pass through the network.

forward pass through the network.

values for ES and EF.

backward and forward pass through the network.

Question 27


The activities that must be completed prior to the start of an activity in question are called the immediate ________ of the activity in question.
Answer

successors

predecessors

successors and predecessors

followers

Question 28

The critical path is the ________ path through the network.
Answer

longest

shortest

straightest

most expensive

Question 29


The normal cost for an activity is $7,000 and the crash cost is $12,000. The normal time to complete this activity is 8 days and crash time is 4 days. If this activity is crashed by 2 days it will cost an additional:
Answer

$1000

$1250

$2000

$2500

Question 30


Which of these statements regarding project crashing is true?
Answer

Crashing is not possible unless there are multiple critical paths.

Activities not on the critical path cannot become critical after crashing.

Crashing shortens the project duration by assigning more resources to one or more of the critical tasks.

Crashing a project often reduces the time it takes for lengthy or complex, but noncritical activities.

Save and Submit

Click Save and Submit to save and submit. Click Save All Answers to save all answers. Click Close Window to close window.

Reference no: EM13375132

Questions Cloud

Complete the following tasks and formats 1 open the final : complete the following tasks and formats 1. open the final assignment data file and save the workbook as final
Describe the structure and operations of the foreign : describe the structure and operations of the foreign exchange markets and discuss common techniques used to manage
Question no1consider a scenario of post mailbox there are : question no.1consider a scenario of post mailbox there are two processes named sender s and receiver r. both processes
I firms often face the problem of allocating an input in : i firms often face the problem of allocating an input in fixed supply among different products. nbspfind the optimal
Question 1 a gantt chart represents mainlyanswer an : question 1 a gantt chart represents mainlyanswer an immediate identification of predecessor task. a record-keeping
1 complete the following tables using hexadecimalnbsp : 1. complete the following tables using hexadecimalnbsp numbers only
Define scarcity and opportunity cost what role these two : define scarcity and opportunity cost. what role these two concepts play in the making of business decisions?a what is
Natural gas spot and future pricesthe law of one price : natural gas spot and future pricesthe law of one price implies that the spot price and the future price of a commodity
Unit 2 individual projectyou have just been asked to teach : unit 2 individual projectyou have just been asked to teach the concept of adaptation to a psychology class. you decide

Reviews

Write a Review

Applied Statistics Questions & Answers

  Briefly interpret the descriptive data analysis

List and explain the variables you would collect in this study. There must be a minimum of three variables and two must meet the assumptions for a correlational analysis.

  Find the ppv and npv for a population

Are the events of being man-made and being polluted independent and write out the sample space - Find the PPV and NPV for a population where 2% of the people have the disease.

  Evaluate the probability the sample mean

What can we say about the shape of the distribution of the sample mean?

  Q1 in a pure exchange economy with two goods g and h two

q1. in a pure exchange economy with two goods g and h two traders amos and elise have cobb-douglas utility functions.

  Participants select three numbers between 0 and 9

For the daily lottery game in Illinois, participants select three numbers between 0 and 9. A number cannot be selected more than once, so a winning ticket could be, say, 307 but not 337. Purchasing one ticket allows you to select one set of num..

  Problem1 1 using if filter the data for these students

problem1 1. using if filter the data for these students into a column which contains the heights of only female

  Population distribution in order to perform test

Construct and interpret a 95% confidence interval estimate of the difference in the mean measurements in-lineand from an analytical lab.

  What is the difference in proportions in the original data

What is the difference in proportions in the original data and what is the p-value and what does it mean in terms of this specific problem

  1 let x1 be a random variable with probability function

1 let x1 be a random variable with probability function given in the table belownbsp nbsp nbsp nbsp nbsp nbsp nbspnbsp

  Interval for the mean femininity score

Construct a 88% confidence interval for the mean femininity score of all male hotel managers and estimate the percent change amongst lactating mothers to within ± 0.5% with 99% confidence. How large a sample of nursing mothers do you need?

  Amount of time spent studying each day for local and

amount of time spent studying each day for local and overseas students aspire llp is a recruitment agency. recently

  Develop a pareto chart

Develop a Pareto chart to identify the more significant types of rejection.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd