Project proposal on how to adjust the project schedule

Assignment Help Operation Management
Reference no: EM13724647

Individual Project: Project Proposal

Task to prepare a project proposal on how to adjust the project schedule. The proposal should include only descriptions of the ways in which you propose to modify the project schedule. Your final project (due in Week 8) will include the following:

  • A formal change request
  • An evaluation of the impact of the change (as submitted to the Change Control Board)-time and labour only. Note: It will be necessary to create the original project schedule and budget to analyse the impact of the change request. Consider that the additional wing will be built concurrently.
  • A list of all the assumptions made
  • An analysis of risk factors due to the change request
  • A new project schedule that shows:
    • The additional time required
    • The additional labour cost
    • The new completion date
  • A statement of work for one contractor
  • A contract closure process description for one contractor
  • A project closure process description

The project details are as follows:

The Smiths decide to build a house on a piece of land that they have purchased. They have consulted with an architect and have the blueprints created. You are a general contractor and have agreed to build the house for them. The Smiths inform you that they had been considering the addition of an extra wing in the house but have now decided against it as the additional space is unnecessary. The original blueprints that the Smiths gave you did not have the additional wing.

You have projected that it will take you 12 weeks to complete the house. However, you need a buffer to accommodate the uncertain weather conditions, and you tell the Smiths that you will need 14 weeks. The Smiths are really anxious to move into their new house. Although they agree for 14 weeks, they also want to put in a penalty for late completion. You agree, provided they also put in a bonus for early completion. You reach an agreement with the Smiths, and the contract is signed. You have figured the project duration and effort as follows:

Task

Duration (days)

Effort (staff days)

Comments

Get a building permit.

5

1

Clear the site.

5

20

Dig the foundation and footings.

3

9

Install forms.

3

9

Pour concrete.

1

5

Wait for the concrete to harden.

5

0

This is referred to as lag time.

Remove forms.

1

3

Build the floor.

1

5

Frame the first floor.

2

10

Build the second floor.

2

10

Frame the second floor.

3

15

Sheath the house.

3

12

Install windows and doors.

4

8

Install siding.

2

6

Put up roof framing.

2

8

Can start as soon as the second floor is framed

Shingle the roof.

1

4

Install plumbing.

4

8

Can start as soon as the roof is shingled

Inspect the plumbing.

1

0

Install wiring.

6

12

Can start as soon as the roof is shingled

Inspect the wiring.

1

0

Hang and finish sheetrock.

4

12

Can start only after the plumbing and electrical work are inspected

Paint the interior.

3

9

Lay the carpet.

2

6

Install the hardwood flooring.

3

6

Install trim.

3

6

Procure the certificate of occupancy.

5

0

Total

75

184

Just as your crew starts framing the second floor, the Smiths tell you that they would now like the additional wing in the house they mentioned previously. The Smiths present you with a new set of blueprints, containing the new wing and ask for a projected difference in price and time for the addition.

You figure that to add the extra wing the following would be required in terms of duration and effort:

Task

Duration (days)

Effort (staff days)

Comments

Dig the foundation and footings.

2

6

Install forms.

2

6

Pour concrete.

1

3

Wait for the concrete to harden.

5

0

This is referred to as lag time

Remove forms.

1

2

Build the floor.

1

4

Frame the first floor.

1

4

Build the second floor.

1

4

Frame the second floor.

2

8

Sheath the house.

2

6

Install windows and doors.

2

4

Install siding.

1

3

Put up roof framing.

2

6

Shingle the roof.

1

3

Install plumbing.

2

4

Inspect the plumbing.

Install wiring.

2

4

Inspect the wiring.

Hang and finish sheetrock.

2

6

Paint the interior.

1

3

Lay the carpet.

2

4

Install the hardwood flooring.

Install trim.

1

3

Total

34

83

This new estimate to add the wing, assumes the sheathing will go on the base house and then work will stop until the extra wing is sheathed. You believe this will be the most economical way to add the additional wing to the property. Another option would be for the project to continue as originally planned, and then add the wing after the Smiths have moved in. After considering both options, the Smiths choose to follow your recommendation to add the new wing now so that they move in when the whole house is complete. The additional work required is as follows:

Task

Duration (days)

Effort (staff days)

Comments

Procure the building permit.

5

1

Dig the foundation and footings.

2

6

Install forms.

2

6

Pour concrete.

1

3

Wait for the concrete to harden.

5

0

Remove forms.

1

2

Build the floor.

1.5

6

Frame the first floor.

1.5

6

Build the second floor.

1.5

6

Frame the second floor.

2

8

Add the sheath.

2

6

Install windows and doors.

2

4

Install the siding.

1

3

Put up roof framing.

2.5

7

Shingle the roof.

1

3

Install plumbing.

2

4

Inspect the plumbing.

1

0

Install wiring.

2

4

Inspect the wiring.

1

0

Hang and finish sheetrock.

2

6

Paint the interior.

1

3

Lay the carpet.

2

4

Install trim.

1

3

Total

38

90

The rates for the various trades (in $/hour) are as follows:

Code

Description

Rate

Comments

GC

General contractor

40.00

HE

Heavy-equipment operator

50.00

Includes equipment

C

Concrete worker

30.00

F

Framer

20.00

F

Siding installer

20.00

W

Window/door installer

30.00

R

Roofer

20.00

P

Painter

20.00

E

Electrician

35.00

FL

Flooring installer

20.00

T

Trim carpenter

35.00

PL

Plumber

35.00

In this project, you will analyse the situation and the effect of the change request on the schedule, cost, and features.

Please make sure that you cite and reference all your outside sources properly, as per the Harvard Referencing System.

Reference no: EM13724647

Questions Cloud

Explain what fournier means by having a relationship : Explain what Fournier means by "having a relationship" with a brand. Using two brands chosen from the categories below, explain whether or not you believe that customers have relationships with those brands
Normalisation : Normalisation of relations which identifies: Dependency diagram for each relation, The level of Normalisation achieved for each relation;, The reasons for any relation that is maintained NOT in 3NF.
Principles for reengineering proposed by michael hammer : What is reengineering? What are the seven principles for reengineering proposed by Michael Hammer? Explain which principle is most important in your opinion.
Create a product market matrix : Create a Product/Market Matrix. This is a table listing the various segments you identified in the Customer Analysis section for MOD01 and the products which those segments buy
Project proposal on how to adjust the project schedule : Just as your crew starts framing the second floor, the Smiths tell you that they would now like the additional wing in the house they mentioned previously. The Smiths present you with a new set of blueprints, containing the new wing and ask for a ..
Write clearly and concisely about contemporary us history : se technology and information resources to research issues in contemporary U.S. history. Write clearly and concisely about contemporary U.S. history using proper writing mechanics.
Review of customer relationship management : Case- A review of customer relationship management: successes, advances, pitfalls and futures
Discussing an organization code of ethics : Write a 1,200- to 1,400-word paper, one not using question-and-answer format, discussing an organization's code of ethics in detail. Perform the following steps:
Decision making gone awry : Sometimes social influences and societal pressures can influence decision making for the better and sometimes for the worse. In addition to these pressures, there are risks that need to be evaluated and measured when making decisions. In this assi..

Reviews

Write a Review

Operation Management Questions & Answers

  Calculate payback period

Which project do you recommend for development? Support your recommendation.

  Justify your forecast also the method you used

Develop your own forecast for bow rakes for each month of the next yr (yr 5). Justify your forecast also the method you used.

  Requirements of good research

A short discussion on the elements considered necessary for research to be considered good research.

  Give employees a choice of rewards

According to Expectancy Theory, which of the following actions would NOT alter outcome valences?

  Evaluate the service to club members

Evaluate the service to club members and casual flyers by completing a table similar to table 3.1 (see page 70 Operations Management 6xth Edition Nigel Slack)

  A leadership impact ideology for tq implementation

Spuport a leadership impact ideology for TQ implementation by synthesizing the processes necessary to provide an organization with a TQ paradigm.

  Describe the make or buy option

How might a manager go about identifying the skills that the company will need in the future? Describe the "make or buy" option and how it can be applied to HR.

  Describe the concept of organizational effectiveness as it

working with organizations to improve the interactions of members and increase productivity through collaborative

  The elements needed for successful implementation of the

the elements required for successful implementation of the jitlean philosophy include reducing setup times performing

  What are the main reasons why this happens

Everyone knows how important it is to make great people decisions, and yet we see examples all around us of failure to do so. What are the main reasons why this happens?

  Explain advantages of entering market early

What are some of the advantages of entering a market early? Are there any advantages to entering a market late?

  How many laburers are employed at the plant

If the labourer productivity at the plant is 0.15 hot water heaters per labour hour, how many laburers are employed at the plant?

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd