Project duration if no activities are to be interrupted

Assignment Help Operation Management
Reference no: EM131156986

A 1,500-foot subdivision street is to be constructed. The layout will be completed in three days; the fill will be brought in over the course of eight days; the compaction/grading will be completed in five days; the asphalt topping will be done in three days; and the striping will take one day to complete. Using a minimum float guideline of one day, develop a linear schedule for this project. What is the project duration if no activities are to be interrupted? Suggest ways that the duration can be shortened.

Reference no: EM131156986

Questions Cloud

What role does organizing play as function of management : What role does organizing play as a function of management? Explain how the flat organizational structure differs from other types of formal organizational structures.
What are balanced scorecard and competing forces : What are balanced scorecard/competing forces? Are measures missing? What measures are superior? What is your root cause analysis of what makes an organization high performing? What is your new idea for making the process better? Comment Comment
HR consider when developing strategic plan : Describe what strategic planning is and the associated steps in the planning process. How does HR planning fit into the overall strategic planning process? What components must HR consider when developing a strategic plan?
About balanced scorecard and competing forces : what have you learned about balanced scorecard/competing forces? Are measures missing? What measures are superior? What is your root cause analysis of what makes an organization high performing? What is your new idea for making the process better?
Project duration if no activities are to be interrupted : A 1,500-foot subdivision street is to be constructed. The layout will be completed in three days; the fill will be brought in over the course of eight days; the compaction/grading will be completed in five days; the asphalt topping will be done in th..
What factors hinder competitive advantage : Do a critical analysis, what factors hinder competitive advantage? What types of strategies are necessary for organizations to maintain competitive advantage? Why organizations have difficulty in maintaining long term competitive advantage?
Write a report which analyses a process : Write a report which analyses a process and provides recommendations on how the process can be improved.- Describe the organisation and the process you have selected.
Individual suddenly began to arrive late to work at times : This individual suddenly began to arrive late to work at times, they were increasingly negative and their performance at work was declining. Imagine this individual is on your team, how would you address the behavior change you are seeing in the indi..
Does your organization offer a group insurance policy : What are some of the flexibilities your organization allows to assist employees with achieving a good balance between work and life responsibilities? Do you think more can be done? If so, describe your perspective on what specific work/life benefi..

Reviews

Write a Review

Operation Management Questions & Answers

  Explain what are the steps in designing qc systems

What are the steps in Designing QC Systems. What are Process Improvement steps in Six Sigma Quality

  Present value of single sum problem

You are going to be given $45,000 in 7 years. Assuming an interest rate of 2.5%, what is the present value of this amount?

  Coefficient of variation of the service time

At a bank, the tellers on average take 10 minutes per customer, with a standard deviation of 7 minutes. What is the coefficient of variation of the service time?

  Average demand for particular item

Average demand for a particular item is 1,200 units per year. It costs $100 to place an order for this item, and it costs $24 to hold one unit of this item in inventory for one year. If the fixed-order-interval model is chosen in this instance, how o..

  What is the objective function

Let x1 be the number of units to make and x2 be the number of units to buy. If it costs $1.5 to make a unit and $4 to buy a unit and 4,000 units are needed, what is the objective function?

  Select a product or service that you would like to sell

Select a product or service that you would like to sell, and  start the process of finalizing a new venture business plan proposal to winbusiness support and funding. Include the following elements

  Ethical responsibilities in the accounting profession

Phil Kart works for Carmel Candy Company. He enters customer orders in the company’s accounting system. The orders are written on prepared forms by the company’s sales representatives (reps). What is the ethical issue? What problems do you see in Car..

  According to poisson distribution

Trucks arrive at a grocery store at a rate of about 3 per hour according to a Poisson distribution. The worker who is in charge of unloading the trucks takes about 15 minutes to unload a truck. Unloading time is approximately exponentially distribute..

  Draw an organizational chart of the business

Draw an organizational chart of the business school or college that you attend. Outline its major roles and functions. How differentiated is it? Do you think the distribution of authority and divisions of labor are appropriate?

  Explain the differences between the three charts

Analyze the three different charts. Write a 1-2 page paper in which you explain the differences between the three charts and which chart best represents the data and why

  Change can impact your leadership at work

List three ways in which change can impact your leadership at work and two ways change can impact your leadership at home or in your personal life

  How did composers vary the standard structure of symphony

How did composers vary the standard structure of the symphony?

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd