1. Which of the following is not an example of a project?

Creating a website for a company

Starting-up a restaurant

Emptying the recycling everyday

Raising money for a disaster relief trip

2. Projects are identified and selected in the

closing phase

planning phase

performing phase

initiating phase

3. Resource are identified and selected in the

planning phase.

initiating phase.

closing phase.

performing phase.

4. The project plan is executed in the

planning phase.

performing phase.

closing phase.

initiating phase.

5. Projects documents are organized and archived in the

closing phase.

planning phase.

initiating phase.

performing phase.

6. It is the responsibility of the________ to make sure that the customer is satisfied that the work scope is completed in a quality manner, within budget, and on time.

project manager

stakeholders

project team members

project authority

7. The project manager has primary responsibility for_______ in planning, organizing, and controlling the work effort to accomplish the project objective.

making all the decisions

impeding

providing leadership

doing the paperwork

8. The project manager coordinates the activities of the _________ to ensure that they perform the right tasks at the proper time, as a cohesive group.

project sponsor

various team members

suppliers

stakeholders

9. The project manager clearly defines the project objective and reaches agreement with the______ on this objective.

stakeholders

customer

project team

suppliers

10. Gain experience is one of the ways to develop the skills necessary to be an effective project manager. Which of the following statements is false?

Work on as many projects as you can.

Projects aren’t all the same.

Limit project experiences to only those tasks that you can do well.

Each project presents a learning opportunity.

11. _________work groups consist of individuals who perform the same function, such as engineering or manufacturing.

A functional organizational structure

An autonomous project organizational structure

A matrix organizational structure

A project management office

12. Each _______ concentrates on performing its own activities in support of the company’s business mission.

autonomous project organizational structure

functional organizational structure

project management office

matrix organizational structure

13. A company with _______ may periodically undertake projects, but these are typically in-house projects rather than projects for external customers. For such projects, a multifunctional project team or task force is formed.

a functional organizational structure

a matrix organizational structure

an autonomous project organizational structure

a project management office

14. In _______, team members may be assigned to the project either full-time or part-time.

a matrix organizational structure

a project management office

a functional organizational structure

an autonomous project organizational structure

15. Individuals are assigned to the project for the length of time they are needed in _________.

a matrix organizational structure

a functional organizational structure

an autonomous project organizational structure

a project management office

16. Project charters are sometimes called a project authorization or project initiation document.

True

False

17. In the project charter document, the sponsor provides approval to go forward with the project and commits the funding for the project.

True

False

18. A request for proposal (RFP) is to state, comprehensively and in detail, what is required, from the sponsor’s/customer’s point of view, to address the identified need.

True

False

19. There are five steps in the project selection process.

True

False

20. The objective is the tangible end product that the project team or contractor must produce and deliver in order for the sponsor or customer to achieve the expected benefits from implementing the project.

True

False

21. The statement of work (SOW) is not contained in the project scope document.

True

False

22. A quality plan is not an essential component in project planning.

True

False

23. A statement of work (SOW) is a deliverable-oriented hierarchical decomposition of the project work scope into work packages that produce the project deliverables.

True

False

24. The work breakdown structure (WBS) defines who will be responsible for the work.

True

False

25. In project management, activities are also referred to ask tasks.

True

False

Reference no: EM132198508

Questions Cloud

How much office supplies expense should bfi recognize : BFI has $750 of office supplies on the shelf at December 31, 2016. How much office supplies expense should BFI recognize
What are some strengths and weaknesses of the proposal : Select a topic for your Topic 3 Executive Summary assignment. Post your idea and basic thoughts about the topic using the Topic 3 Executive Summary assignment.
Contractual requirements on order quantities or frequencies : When doing all calculations assume that there are 4 weeks in 1 month and there are no other contractual requirements on order quantities or frequencies.
What are potential ethical issues related to transferring : You have traditionally purchased large rolls of rubber (about 40 inches wide) and slit them into 2" strips for use in your die cutting process.
Project authorization or project initiation document : Projects documents are organized and archived. Project charters are sometimes called a project authorization or project initiation document.
What is the nature of the world around us : Write an 800-1,000-word essay on your personal worldview. Briefly discuss the various possible meanings of the term "spirituality," and your understanding.
What is their expected combined salary in their last year : They are both 30 years old. What is their expected combined salary in their last year of work if inflation averages 2.5% each year
How much arbitrage profit can you make : How much arbitrage profit can you make if you can borrow up to $1 million us dollars? (Assume there is no transaction cost in the money market
Identify three biases that can influence the outcome : Identify three biases that can influence the outcome of an analysis. Explain what they are and how they arise.

Reviews

Write a Review

Operation Management Questions & Answers

  New market segment that fits the new and improved product

Your supervisor holds a meeting one afternoon to acknowledge that the current company you work for, Construction Consultants, Inc. (CCI), needs to consider some new ideas for extending some of the current services it offers. Explain how the exercise ..

  Can all six get safely across-network analysis problem

Three mice and three cats on the right bank of the river Styx want to go to the left bank by means of a rowboat that can hold no more than two passengers at a time. If the cats outnumber the mice on either bank, the mice will be killed and eaten. Can..

  Discussed the new rules with an attorney

A new employer policy at a dental office stated that the employees were unable to leave the office except to use the restroom, even with a patient cancellation. A husband of an employee emailed the employer that he had discussed the new rules with an..

  The most likely explanation for dawn behavior

Dawn, a young single mother, found a wallet with a large amount of money inside. In the past she has always tried to return the cash to the owner, knowing it is the right thing to do.  The most likely explanation for Dawn’s behavior is

  Company manufactures product using machine cells

A company manufactures a product using machine cells. Each cell has a design capacity of 250 units per day and an effective capacity of 230 units per day.

  Contrast core competencies and core capabilities

Describe the design process for selecting effective SBD strategies. Define, compare and contrast core competencies and core capabilities.

  Discuss the two main functions of foreign exchange market

Discuss the two main functions of the foreign exchange market. Analyze, in detail, the relationship between money supply and inflation.

  Elucidate what will be the cedar product demand next year

For this question suppose which all 699 of units of Cedar are sold in the Nano segment. If the competitive environment remains unchanged. Elucidate what will be the Cedar product's demand next year (in 000's).

  The company''s main competitors for comparison purposes

Identify one of the company's main competitors for comparison purposes. You can find this information using company analysis tools such as Datamonitor.

  Why is forecasting important for an organization

Why is forecasting important for an organization? Which company do you believe to be successful at forecasting and why?

  When selling to business customers

When selling to business customers, marketers should focus on meeting the needs of:

  Why does united states adopt this ethical and legal stance

If the people accept bribery as the norm, why does the United States adopt this ethical and legal stance?

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd