Problem:

You are required to perform a project appraisal of a proposed new road. The road will be a dual lane by-pass around a town centre on the outskirts of Sydney. The project is estimated to improve journey time for commuters into Sydney and reduce congestion problems in the town. There are some concerns which have been raised by local inhabitants including the increased noise and pollution caused by the new road, and the loss of a small, but ecologically important, area of National Park which the road will cut through. The town council and NSW State Government require an appraisal of the project accounting for time-savings, loss of natural environment and other factors. You have been recommended to use a social discount rate of 3%.

Initial Costs

The site of the new road will need to be purchased at a cost of $5 million, and the project will need to be planned at a cost of around $250,000. Both the purchase of the land and the planning agreement must be in place before construction can begin (i.e. at year 0). Construction is estimated to take three years. Initial construction costs estimated by the contractor, which occur in year 1, include site clearance estimated at around $750,000, and initial ground works at $2.5m. Other construction costs occur in all three years (year 1, 2, and 3) and include building materials at $3.75 million, and plant rental at $900,000. These costs have been fixed with the contractor and so remain the same for each year.

Wage costs are for 150 construction workers at $40 per hour, and a site manager at $60 per hour. Estimated staffing times are 45 hours per week all year (47 weeks) for the site manager, and 40 hours per week all year for the construction workers (47 weeks). Wages are expected to grow at an annual rate of 1%.

The other major cost incurred in the development of the road is the loss of small National Park. This should be valued in the project BCA. To do this you have been recommended to use the simple zonal travel cost method, deriving average usage figures from Table 1 below. Note there is no entry/admission cost for using the park.

Zone

Average time (hrs)

Average Distance (km)

Average No. of Visits Lost (per year)

A

0.5

10

100,000

B

1

40

60,000

C

2

100

25,000

Table 1: Zonal Travel Cost Data

Use the zonal travel cost methodology as set out here: The average hourly wage rate is $35, and marginal vehicle operating costs are $0.30 per km.

Ongoing Costs

There is a significant maintenance cost associated with the new road estimated at $250,000 per annum. This cost will begin in year 4 following the completion of the road and is expected to grow at an estimated 1.5% per year.

Benefits

The benefits of the new road include reduced congestion and subsequent time-savings, as well as some estimated accident reduction.

Time savings per year are estimated as follows:

  • Private cars and motorcycles - 6500 hours
  • Business cars - 3000 hours
  • Light commercial vehicles - 9000 hours 
  • Buses - 500
  • Trucks - 12000

Delay costs for each class of vehicle are given in Table 2.

Vehicle Type

Delay cost (Dollars/hour/vehicle)

Private cars and motorcycles

32

Business cars

78

Light commercial vehicles

49

Buses

185

Trucks

63

Source: adapted from BITRE (2009) Table T6.1

Table 2: Delay Cost Data

These savings will begin in year 4 once the road is complete, and continue until the end of the CBA appraisal period (year 28).

Estimated benefits in relation to accident reduction are as follows: a reduction in the current rate of fatalities on the road by 0.5 per year, a reduction in serious accidents by 3 per year, a reduction in accidents causing slight injury by 50 per year, and a reduction in damage only accidents of 150 per year. Costs associated with each type of accident are given in Table 3 below. These reductions will all be made in the urban area around the town. The reductions should be included from years 4 to 28.


$2.67 million per fatal accident

$266,000 per accident resulting in serious injury

$14,700 per accident resulting in slight injury

$9,950 per damage only accident

Source: BITRE (2009)

Table 3: Cost per accident type

Questions

  1. Using the data on costs and benefits provided what is the NPV and BCR associated with the project given a BCA period of twenty-eight years? 
  2. No value has been included to account for the increased noise and air pollution which will affect inhabitants close to the location of the new road. It is estimated that the average house value will decrease from its current level of $300,000 to around $250,000 as a result of the project. This will affect 150 houses close to the road. How does this affect the outcome in terms of NPV and BCR? (see note (iii) below for further information on how to incorporate this cost).
  3. Establish which variables have the biggest impact on the outcome of the analysis using some simple sensitivity analysis.
  4. Given the results of the BCA, and with differing values for certain variables, do you think the project should go ahead? Explain your answer, and discuss the limitations of the analysis with reference to your answer to question 3 and in terms of any possible impacts of the project that have not been included in the data you are provided with.

 

Reference no: EM13373238

Questions Cloud

Question corporation has provided the following production : question corporation has provided the following production and average cost data for two levels of production volume.
Measuring the economys performanceprepare a analysis by : measuring the economys performanceprepare a analysis by answering the questions below. be sure to cite your references
For purposes of this question assume that the excerpts from : for purposes of this question assume that the excerpts from the powers report shown in exhibit 3 provide accurate
Q1 during the 1990s technological advance reduced the cost : q.1 during the 1990s technological advance reduced the cost of computer chips. explain with the use supply and demand
Problemyou are required to perform a project appraisal of a : problemyou are required to perform a project appraisal of a proposed new road. the road will be a dual lane by-pass
During the period 2006 through 2010 housing production in : during the period 2006 through 2010 housing production in the united states fell from a rate of over 2.27 million
Managerial economics and quantitative analysis question : managerial economics and quantitative analysis question 1after two quarters of increasing levels of production the ceo
We want to understand the determinant factors that explain : we want to understand the determinant factors that explain students performance in fifth-grade tests. we observe a
Reisner company assembled the following information in : reisner company assembled the following information in completing its march bank reconciliation balance per bank 11460

Reviews

Write a Review

Microeconomics Questions & Answers

  A subsample from the current population survey is taken on

a subsample from the current population survey is taken on weekly earnings of individuals their age and their gender.

  Build a simple supply and demand diagram

Listen carefully to the following video and summarize the main points that he is making and to what extent is it related to Adam Smith's invisible hand

  In what sense is the price of tickets too low

In Rolling Stone magazine, several fans and rock stars, including Pearl Jam, were bemoaning the high price of concert tickets. One superstar argued, "It just isnt worth $75 to see me play.

  What is the rule of profit maximization in economics

State the Law of Supply. Why do the supply curve slopes upward? State the Law of Demand. Why do the demand curve slopes downward? Explain why normal profit is an implicit cost (i.e., subtracted from accounting profits) in our definitionof economic tr..

  Find the new nash equilibrium

can country A change the outcome of the game by burning the bridge they are crossing to invade and committing its troops to fight? expand the game tree to show this option for county A and find the new Nash equilibrium. Explain

  Why does borrowing constitute negative saving

1. Why does borrowing constitute negative saving 2. Given that a negative flow of annual national saving implies that residents of the United States are net borrowers, who must be funding this borrowing each year

  Explain centrally planned economies

Innovation lagged in the centrally planned economies because: there was too much domestic business competition. there was too much competition from foreign firms. A positive statement is one which is:

  How does the concept of opportunity cost apply to production

how the Principle of Opportunity Cost applies to your life. Think of a recent decision you made. It could be a decision as simple as whether to eat out or cook your own dinner, or it could be a decision to quit your job and go back to school.

  How does competition influence the quality of products

what is the primary requirement for a market to be competitive is competition necessary for markets to work well why or why not how does competition influence the following: (a) the cost efficiency of producer, (b) the quality of products, and (c)..

  What percentage of the variation of your dependent variable

What percentage of the variation of your dependent variable is explained by the independent? d) (10) Suppose the corruption measure was flipped. That is, the least corruption possible is rated a 10, and the highest corruption level is zero. Argenti..

  Calculate the currency-deposit ratio

Suppose the central bank conducts an unusually large open market purchase of bonds held by banks of $1,400B due to a sharp contraction in the economy. Assume the ratios you calculated in part (a) remain unchanged, what do you predict will be the e..

  Why smoking bans on bars and restaurants

Is there too much or too little smoking? Explain why smoking bans on bars and restaurants do not efficient solve an externality problem.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd