Earned Value Calculation
Your project has four activities. Below is the current status of each activity.
Activity A was to have cost $250,000 when complete. Its costs so far are $165,000. It is 50% complete. The activity has completed 7 weeks of a planned 15-week schedule.
Activity B is at the end of week 2 of a planned 4-week effort. It is 65% complete. It was to cost $190,000 when finished. Its costs to date are $150,000.
Activity C is finished. It finished 2 weeks late. It cost $200,000. And it was planned to have cost $250,000.
Activity D is at the end of its fourth of a planned 6-week schedule. It has cost $350,000 so far. It was estimated to cost $500,000 when finished. It is approximately 55% complete.
Using this data, calculate the following.
1. What are the PV, EV, and AC for each of the activities and the complete project?
2. Calculate the CV, SV, CPI, and SPI for each activity and the total project.
3. What is your assessment of the project at this time?
|
Challenges in the global business environment
: According to the textbook, ongoing challenges in the global business environment are mostly attributed to unethical business practices, failure to embrace technology advancements, and stiff competition among
|
|
Four behavioral approaches to job design
: The purpose of this document is to provide clear, succinct and detailed explanations of four behavioral approaches to job design. The four behavioral approaches to job design include: (a) job enlargement, (b) job rotation, (c) job enrichment, and ..
|
|
What is the value of the symmetric key
: In the Diffie-Helman protocol, what happens is x and y have the same value, that is, Alice and Bob accidentally chosen the same number?
|
|
Operating system that allows a single
: A complete operating system that works on a desktop computer, notebook computer, or mobile computing device is a operating system.
|
|
Problem regarding the earned value calculation
: Activity A was to have cost $250,000 when complete. Its costs so far are $165,000. It is 50% complete. The activity has completed 7 weeks of a planned 15-week schedule.
|
|
How much more secure is this double encryption
: Now consider a double-encryption method that adds i to each plaintext character and then adds j to the resulting ciphertext character to get another ciphertext character. Again, all calculations are modulo 256.
|
|
Problem regarding the total quality management
: 1. Explaining to the new leadership on how Total Quality Management (TQM) would enable the organisation to develop better business functions/operations thus achieving world class excellence.
|
|
How many 8-letters password are possible using all alphabets
: Using only 26 capital letters of the alphabet, how many 8-letters password are possible?
|
|
How does resulting increase in kinetic energy compare
: If twice the force is exerted over twice the distance, how does the resulting increase in kinetic energy compare with the original increase in kinetic energy?
|