Paul Smith (operation manager) at the carpet company has been very concerned with the amount of time it took to complete several recent jobs. Some of her workers are very unreliable. A list of activities and their optimistic completion time, the most likely completion time, and their pessimistic completion time (all in days) for a new contract are given in the following table
Activity times and precedent relations are given below for a project.
Activity a m b Immediate Predecessor(s)
A 4 6 8 -
B 3 4 5 -
C 2 3 4 -
D 5 6 7 C
E 2 4 6 B, D
F 4 7 10 A, E
G 2 3 4 A, E
H 3 6 9 F
I 10 11 12 G
J 6 9 12 C
K 6 8 10 H, I
Manually: Draw the network diagram and show ES,EF,LS,LF and slack time of each activity in the diagram.
What do you understand of the types of measurements used in quality assurance systems, and Be able to explain why certain measurements are chosen in specific situations and Understand the importance of acting on the findings provided by measurements.
What are the pros and cons of using expatriates, host-country nationals, and third-country nationals to run overseas operations?
What are some of the guidelines for preparing oral and written research reports? Which type of report would you prefer to prepare. Why?
Smith Construction is building a warehouse for Raymond. The construction firm routinely leaves certain construction equipment at the building site overnight and on weekends. Late one night, Fred, age 10, began playing on some of Smith’s construction ..
An American commodity broker contracted with a Cuban corporation largely owned by United States residents to buy Cuban sugar. Thereafter, subsequent to the United States Government's reduction of the Cuban sugar quota, the Cuban Government expropriat..
The company started as a small family business and expanded to its current size two years ago. It has had an excellent reputation with local insurance companies and has received a great deal of business through word of mouth. Quality of work (many ca..
George has forecasted that annual demand for his sailboats in year 5 will equal 5,600 sailboats. Based on this data and the multiplicative seasonal model, what will the demand level be for George's sailboats in the spring of year 5
A production line is to be designed for a job with three tasks. The task times are 0.7 minutes, 0.9 minutes, and 0.3 minutes. The maximum cycle time in minutes is: A production line is to be designed for a job with three tasks. The task times are 0.6..
Review and critique the Corporate Social Responsibility (CSR) policies of a Fortune 100 company of your choice. What are the strengths of the strategies? Where might the corporation focus to improve their CSR strategies?
It is absolutely preferred to begin addressing risk during the planning phase of the project. I think we can all agree that the likelihood of the project's success increases when project managers and the team look at potential areas of risk early and..
About ten days in advance, demand for the high-price segment is normally distributed with a mean of 250 and a standard deviation of 100. How much production capacity should the manufacturer reserve for the last day?
Should we have an international code of ethics? Explain why or why not. Analyze and evaluate the various issues presented while arguing and debating the connections between business, law, politics, and ethics.
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +1-415-670-9521
Phone: +1-415-670-9521
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd