Outline what you believe the current status of the project

Assignment Help Operation Management
Reference no: EM13748688

1. Post-Award Activity: You bid the program with a total budget of $26 millionincluding a $2 million management reserve and a BAC of $24 million to be completed in 12 months. Although we know the expenditures will not be linear, let's assume a straight-line relationship between time and budget for this exercise. At month 5 we find we should be at $10 million (BCWS) (straight-line plan of $2 million spent each month * 5 months), we have completed enough work to justify an expenditure of $8 million (BCWP) and our actual costs accrued to date are $7 million. (ACWP)

1. Outline what you believe the current status of the project is and interpret what the projections mean to you. Using only this cost data, how can you project time to complete?

2. Outline what you believe the action plan should be to bring this project in on-schedule, on-budget and meet the customer requirements.

2. Understanding Total Cost of Quality and Risk: System Engineers are constantly trying to balance the cost of prevention and appraisal with the risk of failure. Please review the TASER Total Cost of Quality article, found in the ASQ magazine - starting on page 13- (eighth article from the bottom in the Course Documents folder), and use this as a reference:

a. You have considered your repair organization as a profit center in the past. Please develop a compelling argument on why TASER should invest more in prevention and appraisal.

b. Assuming you win the argument above, develop a detailed outline of how you would make this transition. What are the logical steps to success?

3. BPMN: This modern modeling technique from OMG can have significant impacts on all aspects of Systems Engineering:

a. In your opinion what are these Systems Engineering implications as we attempt to migrate to the Model-based Enterprise?

b. If BPMN AND BPEL ultimately do what is projected they can do, what will be the Systems Engineering implications on:

i. Requirements Definition, Requirements Capture and Requirements Creep?
ii. Configuration Management?
iii. Project Management?
iv. Risk Management?

4. Predicting Costs: The Knox predictive model shows that the more rigor an organization has (increased SEI level), the lower the total cost of the system development.

a. CoCoMo and CoSysMo take this into account in subtle ways. Please review the CoCoMo and CoSysMo methodologies and comment on how "Rigor ~ e.g. increased SEI level", is factored into the calculations. Do this ONLY from a qualitative viewpoint ~ I do NOT expect that you do this from a quantitative viewpoint nor do I expect that you show the quantitative effects of this. I am seeking a qualitative "where is rigor factored into the concepts" rather than into the equations here!

b. In CoSysMo we use the factor "A" - the calibration constant. How would you develop a verified and validated "A"?

5. Mitigating Risk:We addressed the pressure cooker FMEA exercise in class. There are various ways of mitigating risks such as: adding redundancies, reducing the impact, reducing the probability, pushing the risk to someone else, etc.As a Systems Engineer how do you propose to create an "excellent" solution for the pressure cooker risks we encountered from two perspectives? Here I am not looking for solutions, I am looking for the Systems Engineering process.

a. A Technical Perspective

b. A Business Perspective

Reference no: EM13748688

Questions Cloud

Age of confessional division produced religious war in spain : During the 16th century, The Age of Confessional Division produced religious wars in France, Spain, and the Netherlands. Choose one of these conflicts and discuss the events, causes, and outcomes.
Market value of a corporate bond : The market value of a corporate bond with a fixed interest rate will _____ if interest rates in the overall economy decrease.
What impact did the price revolution have on the governments : What impact did the Price Revolution have on the governments and people of Europe?
Sell or process further : Port Allen Chemical Company processes raw material D into joint products E and F. Raw material D costs $4 per liter. It costs $100 to convert 100 liters of D into 60 liters of E and 40 liters of F. Determine whether Product F should be sold or proces..
Outline what you believe the current status of the project : Outline what you believe the current status of the project is and interpret what the projections mean to you. Using only this cost data, how can you project time to complete
What do you think of the myth of the lost cause : what do you think of the myth of "The Lost Cause?" Do you think that the Confederacy was fighting for something honorable? Was it fighting against northern aggression or for something else?
What are the steps and what is the easiest way : Solve for X : 4x+23400-12=800x-4(x-12)How would I solve this question? What are the steps and what is the easiest way to figure it out?
How companies and countries are becoming specialised : Comparative advantage - How companies and countries are becoming specialised in certain industries to compete and expand their businesses. Compare Australia with any other country.
The product becomes less competitive and sales drop : Assume that we produce only what we sell. Let P be the selling price in dollars per gallon. Suppose that the selling price and the sales quantity Q are interrelated as follows: Q 6 106 1.1 106P. Accordingly, if we raise the price, the product becomes..

Reviews

Write a Review

Operation Management Questions & Answers

  Describe conflict causes in organizations

What causes conflict in organizations? Many of the organizational behavior topics that have been addressed in the class thus far include the opportunity for conflict to emerge.

  How much of the porfolio value in percentage

how much of the porfolio value in percentage you would have to invest in the zero-coupon bond, and how much in the perpetuity ?

  Finding the average inventory

Unimed is a manufacturer of specialty medical equipment. For one particular varety of equipment offered:Average daily demand is 25 units, with a standard deviation of 6 units.

  Stakeholder analysis & impact

This week you learned about synthesis. For this week's assignment you will review the proposal you submitted in week 6 and utilizing the scholar-practitioner approach discussed in the lecture, update the proposal using synthesis. Ensure you cite y..

  Which design type-mechanistic or organic-best fits starbucks

Managers use different types of control. Identify and define any four types of control used within Starbucks. Provide evidence from the case to support your answer. Which design type-mechanistic or organic-best fits Starbucks.

  Determine which one would be most appropriate for domino

Evaluate alternative structures to determine which one would be most appropriate for Domino's to consider and discuss likely benefits Domino's would realize from adopting that structure. Provide specific examples.

  Illustrate what will the demand level be for mark sailboat

based on this information and the multiplicative seasonal model, illustrate what will the demand level be for mark's sailboats in the spring of 2011

  Describe several measurements of supply chain performance

Describe several "measurements of supply chain performance" that can impact and drive changes or improvements to a business operations activity. Give at least two examples of the measurements.

  What are the features of standard normal distribution the

what are the characteristics of standard normal distribution? the hr department of an organization collects data on

  Algorithms in pseudocode describing the steps of program

Algorithms in pseudocode describing the steps the program will perform to handle remote capture deposits, balance transfers, and balance inquiries.

  Determine the values of the slack and surplus variables

For the linear program Max 3A + 2B s.t. A + B ? 4 3A + 4B ? 24 A ? 2 A - B ? 0 A, B ? 0 Write the problem in standard form.

  What is the reduction in work in process value

If the process makes one unit each hour on average and each unit is worth $1,500, what is the reduction in work in process value?

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd