A company stocks a component that costs $25 per unit. Annual usage of this item is expected to be 2184 units. The firm is open for business 52 weeks per year, so weekly demand is 42 units per week, with a standard deviation of 10 units. The firm's cost accountants have estimated that it costs $30 every time an order is placed for more components, and that carrying the item in inventory costs about $10 per unit per year. Past experience with their supplier indicates that the time from ordering more items to receipt of the shipment of those items is 14 days (assume that they are open 7 days per week.)
a. What quantity should be ordered each time? (Assume that the EOQ assumptions apply.)
b. What is the minimum total annual cost (ordering + holding + purchase) for managing this inventory item?
c. If the company decided that their JIT program required frequent small orders and deliveries (assume that this would mean ordering a quantity of 42 units every week, instead of the EOQ quantity on a less frequent basis), and the costs remain the same as described above, how much higher would the total annual cost be for this item?
d. If a 93% service level is required, what reorder point should be used?
From this week's material identify and discuss 5 skills that are unique to the successful manager of the 21st century.
Analyzing the preconceptions regarding the relationship between truth and the knowledge that something is true.
managers can mitigate some of the effects of worker stress by judiciously using safety stocks and emphasizing material flows rather than worker pace.
You are a member of a group planning your neighborhood’s annual block party.
Describe in detail at least five (5) clear differences between position-based and interest-based labour relations.
Discuss whether performance evaluations in your organization(s) are primarily "rational/objective" or if they are more "political" in nature.
What is the difference between network monitoring and application performance monitoring? Why is it important to provide both?
What do you believe the HR department at your company, or company you've worked for in the past, has done to achieve those goals?
Often variables are converted to attributes and the charts for attributes are used. If we lose much of the information, such as distribution shape,
Do BIG and WGC have a contract for the bushels of wheat? Why or why not? Analyze all issues.
What were the problems/issues leading to the change project? Who were the stakeholders involved in the project? What was the timeframe involved in the project
Acting as a merchandise buyer for a fictitious store, the University Boutique.First develop the retailer's six-month buying plan. Secondly develop the retailer's merchandise assortment plan.
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +1-415-670-9521
Phone: +1-415-670-9521
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd