COURSE DESIGN PROJECT

- Mine Planning And Optimisation Using NPV Method

Project information and requirements

Deposit Description

The deposit is coal seam of averaging 7m in thickness, 12 m deep and nearly horizontal (Fig. 1). This deposit is part of a tropical coal basin of Late Permian age of fluviatile and lacustrine origin, with good coking coal. The delineated reserves, to date, total around 109 Mt of high quality coking coal. Overburden is a typical basin sedimentation stratigraphy, and all bedding is nearly parallel to the coal seam.

The lease is located approximately three hundred kilometres, by road, from a suitable port facility, and fifteen kilometres from a railway. Infrastructure in the area is minimal, with only one small pastoral village within a fifty-kilometre radius. Local government has offered large subsidies for services to encourage development in the area.

992_figure.jpg

Figure 1. Cross-sectional view of the deposit (after Mayes, 2019)

Design requirements

Based on the information for the mineral deposit given, design a suitable mining system in detail for the shallow part of the deposit. The student should include in their answer the following:

a. Select and justify an optimal mining system
b. Design and optimise the annual production rate using NPV method .
c. Design and plan in detail mine excavation.
d. Plan the rehabilitation of the spoil pile or waste dump.
e. Appraise the effects of the project designed on social, political and environmental issues.

As well as any other salient points as required by the mining system, for economic analysis refer to current market prices in A$ for the commodity as required. Accurate costing is not an essential aspect to the project but some notional economic modelling is required to illustrate the viability of the method detailed.

3. Report writing requirements

1) Two persons in a team for this design project.

2) Formal academic report.

Attachment:- Mine Planning And Optimisation Using NPV Method.rar

Reference no: EM132522128

Questions Cloud

Business costs or risks of poof data quality : What are the business costs or risks of poof data quality? What is data mining? What is text mining?
Online videos on unified communications : Find and view several online videos on unified communications. Identify the URLs for three that you think do a particularly good job illustrating characteristic
Security and architecture design : System architecture is the descriptive representation of the system's component functions and the communication flows between those components.
MNG03236 Business Professional Development Assignment : MNG03236 Business Professional Development Assignment Help and Solution, Southern Cross University - Assessment Writing Service
Mine planning and optimisation using npv method : COURSE DESIGN PROJECT Assignment Help and Solution - Mine Planning And Optimisation Using NPV Method - Project information and requirements
Data structures and algorithms assignment : Design classes which use inheritance, polymorphism, and exception handling and Analyse, design and implement multi-layered software solutions
Impact of racism on indigenous australians : Prepare a literature review on topic "impact of racism on Indigenous Australians- a review of literature - Six journals discussion for review
EPM5500 Fundamentals of Project Management Assignment : EPM5500 Fundamentals of Project Management Assignment Help and Solution, Victoria University - Assessment Writing Service
MBA603 New Venture Capital Raising Assignment : MBA603 New Venture Capital Raising Assignment Help and Solution, Kaplan Business School - Assessment Writing Service - Capital Raising Strategy for Business

Reviews

Write a Review

Other Engineering Questions & Answers

  Characterization technology for nanomaterials

Calculate the reciprocal lattice of the body-centred cubic and Show that the reciprocal of the face-centred cubic (fcc) structure is itself a bcc structure.

  Calculate the gasoline savings

How much gasoline do vehicles with the following fuel efficiencies consume in one year? Calculate the gasoline savings, in gallons per year, created by the following two options. Show all your work, and draw boxes around your answers.

  Design and modelling of adsorption chromatography

Design and modelling of adsorption chromatography based on isotherm data

  Application of mechatronics engineering

Write an essay on Application of Mechatronics Engineering

  Growth chracteristics of the organism

To examine the relationship between fermenter design and operating conditions, oxygen transfer capability and microbial growth.

  Block diagram, system performance and responses

Questions based on Block Diagram, System Performance and Responses.

  Explain the difference in a technical performance measure

good understanding of Mil-Std-499 and Mil-Std-499A

  Electrode impedances

How did this procedure affect the signal observed from the electrode and the electrode impedances?

  Write a report on environmental companies

Write a report on environmental companies

  Scanning electron microscopy

Prepare a schematic diagram below of the major parts of the SEM

  Design a pumping and piping system

creating the pumping and piping system to supply cool water to the condenser

  A repulsive potential energy should be a positive one

Using the data provided on the webvista site in the file marked vdw.txt, try to develop a mathematical equation for the vdW potential we discussed in class, U(x), that best fits the data

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd