Map and draw the new supply network

Assignment Help Supply Chain Management
Reference no: EM131199272

Read the following supply chain reconfiguration case, make assumptions as necessary but do state them clearly, and answer the following questions provided at the end of the case description.

The case company (referred to as ABC) is a leading supplier of maintenance, repair and operating (MRO) products to businesses and institutions in the United States, Canada and Mexico with an expanding presence in the Japan, India, China and Panama. The company works with more than 3,000 suppliers and offers nearly 900,000 products ranging from industrial adhesive used in manufacturing, to hand tools, janitorial supplies, lighting equipment, and power tools. When something is needed by one of their 1.8 million customers, it is often needed quickly. So, quick service and product availability are key drivers to ABC's success.

Your assignment involves studying the US distribution network in ABC's supply chain. ABC works with over 250 suppliers in China and Taiwan region. The suppliers produce products to ABC's specifications and ship to the US using ocean freight carriers from four major ports in China and Taiwan. From these ports, products are shipped to US entry ports in either Seattle or Los Angeles. ABC currently has free on board (FOB) shipping contracts with Chinese and Taiwanese suppliers by which the supplier is responsible for all costs incurred until the product is delivered to the US entry ports. Approximately 40% of the containers enter in Seattle and 60% at the Los Angeles port. Containers on arrival at the port cities are inspected by federal agents. After passing through customs, products are loaded onto the 20-foot and 40-foot containers and are shipped by rail to ABC's central distribution centre in Kansas City. Variable processing costs at both Los Angeles and Seattle ports are $5 per cubic meter (CBM). The rate for shipping the containers to Kansas City is $0.0018 per CBM per mile (this rate applies to all shippings by rail).

In Kansas City, the containers are unloaded and processed through a quality assurance check. This costs $3 per CBM processed. A negligible percentage of the material may need to be sent back to the supplier. Errors in quantity and package size are often found requiring accounting adjustments. Items are stored in Kansas City distribution centre, which serves nine warehouses in the US. The nine warehouses each place orders at the distribution centre that contains all the items to be replenished. Kansas City consolidates the items on order onto pallets and ships them on 53-foot trucks to warehouses. Truck freight cost $0.0220 per CBM (this rate applies to all shippings by truck) per mile. The demand forecasts for the items purchased from China/Taiwan for next year and shipping distances are given in the table in the next page.

 

Demand (CBM)

 

Distances (Miles)

Warehouse

Average

% of total Demand

 

From Kansas City

From Los Angeles

From Seattle

Kansas City

20,900

11%

 

0

1,620

1,870

Cleveland

17,100

9%

 

800

2,350

2,410

New Jersey

24,700

13%

 

1200

2,780

2,890

Jacksonville

15,200

8%

 

1150

2,420

2,990

Chicago

22,800

12%

 

520

2,020

2,060

Greenville

15,200

8%

 

940

2,320

2,950

Memphis

17,100

9%

 

510

1,790

2,330

Dallas

22,800

12%

 

500

1,430

2,130

Los Angeles

34,200

18%

 

1620

0

1,140

Total

190,000

 

 

 

 

 

Although a high percentage of demand was from warehouses in south and east of Kansas City, the question has surfaced concerning the 18% that will be shipped to Kansas City and then shipped back to Los Angeles warehouse. This double-transportation could potentially be eliminated if ABC builds a new distribution centre in Los Angeles. The idea is to ship material arriving at the Seattle port by rail to a new Los Angeles distribution centre, which would be located at the current location of the Los Angeles warehouse.

It is estimated that the Los Angeles facility could be upgraded at a one-time cost of $1,500,000 and then operated for $350,000 per year. In the new Los Angeles distribution centre, containers would be unloaded and processed through a quality assurance check, just as is now done in Kansas City. The cost for doing this would be $5 per CBM processed. The cost associated with transporting the containers from the Los Angeles port to the Los Angeles distribution centre is negligible. After the material is processed in Los Angeles, the amount needed to replenish the Los Angeles warehouse (approximately 18%) would be kept and the rest sent by rail to Kansas City. It would then be stocked in the Kansas City distribution centre and used to replenish the other warehouses.

ABC management feels that it may be possible to make the change, but they are unsure if it would actually save any money and whether it would be a good strategic change.

Questions to be addressed:

1. Map and draw the existing supply network, as well as calculate the annual cost associated with running the existing system?

Note: In the existing system 40% of the volume arrives in Seattle and 60% in Los Angeles. All material is transferred to the Kansas City distribution centre by rail, where it is unloaded and quality checked. All volume is then transferred by truck to the nine existing warehouses in the US.

2. Map and draw the new supply network as a result of the changes made in the case and calculate the annual cost associated with running the upgraded system?

Note: In the new system, the Los Angeles warehouse is upgraded to include a distribution centre capable of processing all the volume coming into the US. Containers coming into Seattle would be inspected by federal officials (it needs to be done at all port locations) and then immediately shipped by rail in their original containers to Los Angeles. All volume would be unloaded and quality checked in Los Angeles. 18% of the volume would then be kept in Los Angeles for distribution through that warehouse and the rest transhipped by rail to the Kansas City warehouse. The material sent to Kansas City would not need to go through another "quality check" and would be directly stored to supply the eight remaining warehouses in the US.

3. In an essay format analyse the US supply network and explain what other SSCM strategies can be applied to optimise network costs? Using Linear/Integer or other Programming mathematical problem solving techniques research other distribution cost and network design methods and determine answers to some of the following questions Eg. What would the optimum location for the warehouses and distribution centres be? Should the new Los Angeles distribution centre be added as a new node in the network? Is this strategically something that ABC should do?  What factors have ABC not considered that might be important in moving strategically to the new SC configuration, base your arguments on academic evidences of concepts or practices that can be applied in coming up with an optimal network design and then mapping out new solutions?

Reference no: EM131199272

Questions Cloud

Explain the measurement model used by qantas : Explain whether this report supports or disproves the efficient market hypothesis. Identify the measurement model used by Qantas for its writedown of the fleet.
Construct employee policy on cell phones-social media : Social media and the Internet has become a problem in Healthcare Facilities today. Construct an employee policy on cell phones, social media, and personal activity on the Internet. Most healthcare facilities have strict policies prohibiting employees..
Determine how many bowls and mugs should be produced per day : Stoneware Pottery Company wants to determine how many bowls and mugs should be produced per day in order to maximize profit given the labor and material constraints. The unit profit value for Bowls is $40 per unit, for mugs the unit profit value is $..
What are the disadvantages of benchmarking : In order to improve processes quality, management keeps records and evaluates processes based on these records. This type of recordkeeping is considered benchmarking. Benchmarking allows an organization to analyze variances for different types of pro..
Map and draw the new supply network : Map and draw the new supply network as a result of the changes made in the case and calculate the annual cost associated with running the upgraded system
Leadership truly acknowledge critical role of the employees : Humility. Does your leadership truly acknowledge the critical role of the employees who help the organization achieve its set goals? Is such acknowledgment manifested through rewards and profit sharing or is it superficial?
What society should truly expect from the future : When technology should be paramount, and when should it be sidelined? What society should truly expect from the future? Consideration of strategic, operational, and tactical uses of technology.
Draft proposal explaining what should go into a preparedness : Draft a proposal explaining what should go into a preparedness and infrastructure protection program for the threat that was previously identified at your CIKR site.
Calculate present value of cash inflow : If project's cost of capital (discount rate) is 12.5%, what is the project's NPV? Should the project be accepted? Why or why not? Calculate present value (PV) of cash inflow (CF)

Reviews

len1199272

9/9/2016 12:38:59 AM

In this case study question use font 12 Calibri using A4 paper. If you are using hand drawn tables or pictures then scan them with a good quality. Embed these tables or pictures in your word document file – this assignment questions should be one file only. No word limit has been set, however you need to be demonstrate stages of your calculations and be correct in your calculations, as well as succinct and academically robust in your arguments, use top tier journal articles for citations as required and include them in the bibliography in Harvard Style. Assessment marking criteria for this part includes- relevance of your answer to the task set or questions, clarity of expression, clearly documented analysis and methods used, logical planning and sequence, and appropriate written presentation of the work including drawing maps.

Write a Review

Supply Chain Management Questions & Answers

  Explain the supply chain management concept

Explain the supply chain management concept, Differentiate between public and private sector organisations in terms of their supply chain objectives and strategies

  Which value chain model is being used

Describe how this organization utilizes its value chain within that country. Which value chain model is being used?

  Problem regarding the total quality management

1. Explaining to the new leadership on how Total Quality Management (TQM) would enable the organisation to develop better business functions/operations thus achieving world class excellence.

  Determine the weekly production schedule

A small compnay will be introducing a new line of lightweight bicyles frames to be made from special aluminum and steel alloys. The frames will be produced in two models, deluxe and professional, with anticipated unit profits if $10 and $15, respecti..

  Fundamental reasons for succes - zara

The Fundamental reasons for success, with a comparison to another successful and an unsuccessful company - how can Zara maintain its competitive advantage, here the concept of sustainability may be introduced?

  The pros and cons of rfid in supply chain management

The pros and cons of RFID in supply chain management

  Which disease is epidemic or endemic

Which disease is epidemic or endemic.

  Different quantity flexibility contracts

Would require all excel spreadsheets to have no author and answers to questions on a separate word document without an author as well.

  What is the different between deactivation and denaturing

what is the different between deactivation and denaturing of enzymes as it relates to temparture affects.

  Contrast and comment on the performance

1.Pasquist Water Company (PWC) operates a 24 hour facility designed to efficiently fill water hauling tanker trucks.

  Unethical business practices degrade the quality

How is the International Organization for Standardization trying to encourage ethical business behavior?

  What were the drivers for lenovo to build

What were the drivers for Lenovo to build, in 2012, a manufacturing facility in Whitsett, North Carolina instead of in low-cost regions such as Asia or Mexico?

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd