Illustrate what would happen to during put of the line

Assignment Help Operation Management
Reference no: EM1373905

Q. This line consists of single-machine stations and is almost balanced (i.e., station rates are nearly equal). A manufacturing engineer has estimated the bottleneck rate to be 2000 cases per 16-hour day and the raw process time to be 30 min. . The line has averaged 1,700 cases per day and cycle time has averaged 3.5 hours.

a) Illustrate what is the estimated average WIP level?

b) Explain how does this performance compare to the practical worst case?

c) Illustrate what would happen to during put of the line if we increased the capacity of non-bottleneck station and held the WIP at its current level?

d) Illustrate what would happen to during put of the line if we replaced the large single-machine at the bottleneck station with four smaller machines and held WIP at its current level? (The total capacity of the four smaller machines is equal to the capacity of the larger machine.)

 

Reference no: EM1373905

Questions Cloud

Explain how much more expensive is the next lowest cost : Explain how much more expensive is the next lowest cost option. For the optimal order quantity, illustrate what is the inventory position immediately after an order is placed.
Compute the total cost : ssuming transportation costs are $1 per load per meter, develop a suitable layout that minimizes transportation costs using the given information. Compute the total cost.
Explain how many units should be ordered each time : To minimize total cost, explain how many units should be ordered each time an order is placed. If the holding cost per unit was $6 instead of $5, illustrate what would the optimal order quantity be.
Graphing the supply curve : Think the market for new, single family house in Miami. The general demand function for new housing in Miami is anticipated to be Qd =15 - 2P + 0.05M + 0.10R,
Illustrate what would happen to during put of the line : Illustrate what would happen to during put of the line if we replaced the large single-machine at the bottleneck station with four smaller machines and held WIP at its current level.
Illustrate at what center of gravity coordinates : illustrate at what center of gravity coordinates should the new store be located. Census tracts 103 and 105 are each projected to grow by 20% in the next year. Explain how will this influence the new store's coordinates.
Find the integer solution that will maximize her profit : With the semester almost over, Jan plans on taking a 3-month summer vacation to England and doesn't want to leave any unfinished posters behind. Find the integer solution that will maximize her profit.
Illustrate what is the total cost of this policy : Explain how many tires should Rocky Mountain order each time it places an order. Illustrate what is the total cost of this policy.
Should the company outsource design or do it in-house : A company is deciding if it should do design of a product in-house or outsource the design. If outsourced the cost for a low bidder would be $40,000 and the cost for an expensive bidder $100,000.

Reviews

Write a Review

Operation Management Questions & Answers

  Mixed integer programming

The Wiethoff Company has a contract to produce 10000 garden hoses for a customer-Because these machines are from different manufacturers and employ differing technologies, their specifications are not the same.

  Graph constraints-find optimal solution

Graph the constraints for this problem. Indicate all feasible solutions. Find out the optimal solution to LP Relaxation. Round down to find out a feasible integer solution. Is this solution optimal?

  Determining business research and methodology

How are Hypothesis Development and Theoretical Framework employed in Healthcare? How does the Measurement of Variables (Operation Definition) play a role in Healthcare Field.

  Overall description of company history

Company Research of five companies is provided in the structured manner in this response. The answer includes references employed.

  Issues and challenges that may affect contract

You have been asked to update your general counsel on 5 major issues and challenges that may affect the contract the legal team needs to write before business can begin. You decide to prepare a presentation that focuses on different areas the team..

  Elucidate what will be the cedar product demand next year

For this question suppose which all 699 of units of Cedar are sold in the Nano segment. If the competitive environment remains unchanged. Elucidate what will be the Cedar product's demand next year (in 000's).

  Elucidate what is this product availability

this product hangs up also needs resetting every 200 hours. On average about 45 minutes is needed to reset this product. Elucidate what is this product's availability.

  Operational plan in hospitality enterprise

Operational plan pertaining to a hospitality enterprise is given in detail in the solution. The operational plan is an important plan or preparation which gives guidelines regarding the role and responsibilities of each and every operation at all lev..

  Initiate an order also holding costs are based on an annual

Quarter-inch stainless-steel bolts 1 ½ inches long are consumed in a factory at a fairly steady rate of 60 per week. Bolts cost plant 2 cents every. It cost plant $12 to initiate an order also holding costs are based on an annual interest rate of ..

  Identify the major issues in given situation

Identify the major issues, discuss how the problem has been handled by the employee's supervisors to date, and evaluate how her present superior is handling the situation

  Effectiveness of planning and consulting department

Assess the performance measures by which senior management will evaluate the effectiveness of the planning and consulting department regarding the department's role in the justification of the new hospital.

  Elucidate what is the average multifactor productivity

Standard selling price is $125 per unit. Overhead is charged weekly at the rate of $1,500 plus .5 times direct labour cost. Suppose a 40-hour week also an hourly wage of $16. Material cost is $10 per foot. Elucidate what is the average multifactor..

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd