Illustrate what is the probability that the project

Assignment Help Operation Management
Reference no: EM1373972

Q. 1- A series of activities must be completed in a coordinated fashion to complete a landscaping overhaul. The following table shows the activities their optimistic, most likely and pessimistic durations and their immediate predecessors

Activity A m b Immediate Predecessors
A 4 8 12 ---
B 4 10 13 A
C 7 14 18 B
D 9 16 20 B
E 6 9 12 B
F 2 4 6 D,E
G 4 7 13 C,F
H 3 5 7 G
I 2 3 4 G,H

A- Decide the expected times and variances for each activity

B- Construct a project ne2rk for this problem

C- Decide the EST, EFT, LST, LFT and slack for each activity. Also decide the critical path and project completion time.

D- Illustrate what is the probability that the project will be finished in less than 57 days?

E- Illustrate what is the probability that the project will desire at least 50 days?

 

Reference no: EM1373972

Questions Cloud

Should firm replace the asset : The new machine will cut operating costs by $10,000 every year for the next five years. Taylor's cost of capital is 8%. Should the firm replace the asset?
Decide the average number in the system : Vending machine dispenses hot chocolate or coffee. Service time is 30 seconds per cup and is constant. Customers arrive at a mean rate of 80 per hour and this rate is Poisson-distributed. Decide the average number in the system.
Questions about managerial economics : Assume you are the general manager of a concrete mixing and delivery facility located in Texas. Your company purchases the raw materials for concrete, mixes the concrete according to customer specifications,
How much income must dave report for tax year : How much income must Dave report for tax year and what is character of the income and evaluate what is Dave's basis in his partnership interest at the end of tax year?
Illustrate what is the probability that the project : Illustrate what is the probability that the project will be finished in less than 57 days. Illustrate what is the probability that the project will desire at least 50 days.
Illustrate what are some specific instances : Identify explain how production processes are organized in a typical manufacturing organization. Illustrate what are some specific instances.
Statement of cash flows : Johnstone Manufacturing Company has used the double-declining balance method to depreciate its machinery. During the present year, management switched to the straight-line method because they felt that it better shown the utilization of the assets..
Which shipping alternative would you recommend : Three hundred boxes are to be shipped and each box has a price of $140. Which shipping alternative would you recommend. Explain.
How might you enhance satisfaction and engagement employees : Illustrate what might be some reasons for this high level of a dissatisfaction and disengagement among young people. As a manager, explain how might you enhance satisfaction and engagement for young employees.

Reviews

Write a Review

Operation Management Questions & Answers

  Do you think this criticism of organization behaviour fair

The subject of organization behaviour is sometimes being criticized as being only common sense, when we would rarely hear such a criticism on subject such as statistics. Do you think this criticism of organization behaviour is fair.

  Elucidate what is the recommended production rate

Elucidate what is the recommended production rate if a level strategy is adopted with no backorders or stock counts. Elucidate what is the ending inventory for month 4 under this plan.

  Case study of rittenhouse medical

Case study of Rittenhouse Medical

  Elucidate what is the theoretical minimum for the smallest

Elucidate what is the theoretical minimum for the smallest number of workstations which Helms can achieve in this assembly line.

  Elucidate what is other relevant factors

Elucidate what other relevant factors which are not mentioned in this case study might play a role in team's decision.

  Elucidate what is the critical path

Elucidate what is the critical path. Suppose you need to shorten the completion time as much as possible also you have the option of shortening any or all of B, C, D also G every one week. Which would you shorten.

  What is the breakeven volume

How do the two plants compare with respect to the cost of labor for making a car? For each location, what is the breakeven volume and what is the total cost at breakeven?

  Sensitivity analysis

Sketch the results of a sensitivity analysis

  Elucidate what would you have to do to the costs to assure

The supply also demand for economy cars also the total cost of moving these vehicles between sites are shown below. Elucidate what would you have to do to the costs to assure which A always sends a car to D as part of the optimal solution.

  Statutory law or common law

Assume that Arthur Rabe is suing Anna Soto for breaching a contract in which Soto promised to sell Rabe a Van Gogh painting for $3 Million. Statutory law or the common law?

  Linear programming with decision variables and constraints

Illustrate the linear programming model with its decision variables and its constraints. Use the computer solution generated by Excel (Solve) to see which team works with which project. Provide the Excel file.

  Serious financial trouble

Your business, a closely held corporation with 4 other shareholders, is in serious financial trouble. A lender has suggested that it might provide lending if you could reduce your current debt load by 50%.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd