Q. When Ray Zalinski is planning the takeover of Callahan Auto Parts he puts together a project plan for merging the two companies. Zalinski wants to make sure that they can complete project on quickly so they can close the plant in Sandusky. As a result, he wants to know the percent chance that the project will take longer than 290 days. After many painful deliberations, they have find out all of the tasks required along with optimistic, most likely also pessimistic times for each path. They have also computed the expected time for the critical path along with its standard deviation. They then computed the Z value associated with their due date also the expected time also standard deviation of the critical path. Finally, they looked this value up in the Normal Table (or computed it utilizing Excel). The number returned was: 0.0489. Specified this returned value, Illustrate what is the percent chance that the project will take longer than the assigned due date.
Currently, industry has 20 projects per year and each senior designer can handle 6 projects per year. Illustrate what is current labour utilization of senior designers. Illustrate what do you recommend.
Illustrate what are the 5 essential feature of the queuing systems at the consumer service counter, the garage also the car wash at thrifty car rental.
Compute average cycle time also normal time for each element. Then, calculate standard time for entire task. Decision Science Institute (DSI) promotes its annual national conference by mailing thousands of letters to various recipients.
Define the business research and its purpose. Discuss the business problems under investigation. Explain the data collection methods used in the research project.
This response states operations managements. The roles and goals of health care operations managers are discussed as well. References are included.
Illustrate what kinds of programs would you implement to educate your people about benefits of trade.
Stock is received 12 working days after an order has been placed. No backordering is allowed. Suppose 325 working days a yr. Illustrate what is Dotcom optimal order quantity.
Compute the productivity ratios for the old also the new production systems. You have to report to the Operations Manager on the impact to productivity of your new process. Elucidate what will you report.
Illustrate what supply challenge would Red Fish, Blue Fish, face in expanding into South America. Do you recommend expanding aggressively into South America. Explain why or why not.
Illustrate what is virtual network approach to structure. Is use of authority also responsibility different compared with o r forms of departmentalization.
Average labour cost last year was $20 per hour, kits cost %1,000 every also energy costs were $3 per kilowatt-hour. Elucidate what do you tell Mr. Munson.
This reduction in demand will push equilibrium price back down to its original level. Since equilibrium price will remain unchanged, smokers will consume same number of cigarettes." Do you agree or disagree with this view. Explain.
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +1-415-670-9521
Phone: +1-415-670-9521
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd