Identify the critical path for the project

Assignment Help Managerial Accounting
Reference no: EM132571778

CASE STUDY - BO GARRY PRODUCTS (BGP)

Learning outcome 1: For each of the Activities A to E suggest how the risks associated with countrs -wide sourcing and the selection of other suppliers in the future may be reduced.

Learning outcome 2:
(a) Based on the intimation in Table 1:
(i) Identify the critical path for the project.
(ii) Determine the planned duration for the sourcing project.
(b) Calculate the maximum time saving that could be made on Task H in order to reduce the overall duration of the project (taking into account the fact that all other task durations will remain as in Table I). Show your calculations.

c) If the maximum time saving on Task H is achieved (and Task D is reduced by 2 weeks as suggested by BGP Managing Director) calculate:
(i) The revised overall planned duration of the project.
(ii) An approximate start date if the project is to be complete by 01 September.

Learning outcome 3:
Discuss the contract terms and clauses that BGP can use to manage the risks identified for low-cost country sourcing.

Learning outcome 4:
(a) Identify key risks for BGP's future business to be included in a risk register for BGP to address potential risks.
(b) Discuss how Ngor can ensure a successful introduction of a low-cost local supplier to BGP through good supplier transition planning.

Attachment:- Case.zip

Reference no: EM132571778

Questions Cloud

Trade for gogreen importing activities : Study the incoterms and state whether there is a more beneficial term of trade for Gogreen's importing activities. explain your reasoning.
What are the proper banking procedures for businesses : Question - What are the proper banking procedures for businesses? Are there any dilemmas that should be anticipated from an accounting perspective
Why does canadian pacific want to acquire norfolk southern : Why does Canadian Pacific want to acquire Norfolk Southern? Do you believe there is compelling economic rationale for the merger?
Explanation of the term knowledge management : A brief explanation of the term ‘Knowledge Management'. An explanation for the fast-growing interest on the part of companies to employ Knowledge Managers.
Identify the critical path for the project : Discuss how Ngor can ensure a successful introduction of a low-cost local supplier to BGP through good supplier transition planning.
Identify violations of Generally Accepted Auditing Standards : Moremoney & Associates, Chartered Acc. was hired as the auditor for Jamins Ltd, Inc.., Identify violations of Generally Accepted Auditing Standards
Trade for gogreen importing activities : Study the incoterms and state whether there is a more beneficial term of trade for Gogreen's importing activities. explain your reasoning.
Calculate the npv and irr for each type of machine : Calculate the NPV and IRR for each type of machine, and decide which to recommend.Marvin Industries must choose between an electric-powered
Calculate project payback period and internal rate of return : Calculate each project's payback period, net present value (NPV), internal rate of return (IRR), modified internal rate of return (MIRR) and profitability index

Reviews

Write a Review

Managerial Accounting Questions & Answers

  Manage budgets and financial plans

Explain the budgeting process and its importance to a business, identifying the components of different budgets, forecast estimates for inclusion in the budgets.

  Prepare a retained earnings statement

Prepare a retained earnings statement for the year and Prepare a stockholders' equity section of given case.

  Prepare a master budget for the three-month period

Prepare a master budget for the three-month period.

  Construct the companys direct labor budget

Construct the company's direct labor budget for the upcoming fiscal year, assuming that the direct labor workforce is adjusted each quarter to match the number of hours required to produce the forecasted number of units produced.

  Evaluate the predetermined overhead rate

Evaluate the Predetermined Overhead Rate

  Determine the company''s bid

Determine the company's bid if activity-based costing is used and the bid is based upon full manufacturing cost plus 30 percent.

  Compute the pool rates for the different activities

Complete the schedule to compute the pool rates for the different activities.

  Prepare Company financial statements

Prepare Company financial statements

  Prepare an analysis of terracycles

This individual assignment is based on the TerraCycle Inc.

  Discuss the ethical issues

Discuss the ethical issues

  Political resources in emerging markets

Calculate the GDP in Income Approach  and Expenditure Approach

  Management accounting - ehsan electronics company

A new plant accountant suggested that the company may be able to assign support costs to products more accurately by using an activity based costing system that relies on a separate rate for each manufacturing activity that causes support costs.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd