How would you recommend the planned order release

Assignment Help Supply Chain Management
Reference no: EM131194140

Assembly Line Balancing:

PROJECT-Spring 2016

La-Z-Man Furniture is competing in a high-tech market by launching a living room product that has presumably a steady demand in next few years. The product is simple but one of its sub-assembly systems, called Base-plate combo, needs the following 11 assembly operations to be completed before it is sent to the main assembly line. The precedence constraints and the processing times (in minutes) of these assembly operations are shown in Figure 1. The demand of the base-plate combo is forecasted as 40, 25, 30, 35, and 30 units each working day of a 5-day week. The furniture factory works on an 8-hour single shift per day schedule.

1447_Fig5.jpg

Figure 1. Precedence diagram and operation times

Currently the company is facing various problems of manpower imbalance, component stock-outs, excess inventory and other associated coordination problems. Most of the time the manager cannot meet the weekly demand for this inefficient planning and management. As a small businessman, the manager/owner sought your expertise help in using your IE knowledge to solve this problem.

Earlier the manager used to produce about 25 items a day on the average. The manager heard that by implementing an assembly line balancing technique he could improve its productivity and balance the manpower. How will you advise and plan for him to design a well-balanced assembly line? What is your effective production rate? What is the expected efficiency of the line? Show your proposed line configuration as well.

B. Material Requirement Planning

Some of the assembly operations require components that have to be ordered from outside and the number of sub-assembly components (W, X, Y and Z) needed for the different 11 assembly operations is given in Table 1. Acceptable ordering practices (fixed, variable or lot-for-lot) and leadtimes for the sub-assembly components are shown in the Table 1 and the MRP tree for the sub-assembly components (W, X, Y, and Z) is given in Figure 2.

How would you recommend the planned order release (POR) and bill of materials (BOM) for all components for a week? Draw the feeder lines and show the arrangement of feeding components for assembly.

Table 1. Feeding components needed for assembly operations

Sub-assembly Component

Ordering practice

Leadtime (day)

Number of sub-assembly components needed for assembly operations

1

2

3

4

5

6

7

8

9

10

11

W

LFT

1

-

-

1

-

-

-

1

-

2

-

-

X

LFT

3

2

-

-

-

-

1

-

-

2

-

-

Y

F=100

3

-

1

-

-

2

-

-

3

-

1

-

Z

V=150

1

-

1

-

-

1

-

-

-

1

-

-

284_Fig6.jpg

Figure 2. MRP Tree for feeding components

C. Optimal ordering policy:
The simple BOM procedure does not consider the economic perspectives of the operation. In reality, placing an order costs money and manpower. On the other hand, holding the inventory also incurs warehouse/carrying cost. How would you give an economic plan for BOM for the company such that the total cost of ordering and carrying is minimized? Assume any reasonable data you need.
REPORT/RESEARCH PAPER:
The project must contain at least the following ingredients:
- Cover page: Title of the project, your name(s), course number and date of submission.
- Abstract page
- Introduction
- Description of the system or material flow
- Goal and objective of study
- Solution methodology
- Results
- Discussion and conclusion
- Recommendation
- References, and
- Appendices (if any).

You may use any kind of figure or picture to explain the proposal better. You can email me it.

Reference no: EM131194140

Questions Cloud

Principal kafele talks school climate and culture : Review the video titled "Principal Kafele Talks School Climate and Culture in U.S. Education"- Propose at least two (2) steps that you could take in order to help to build a positive school climate in your home school district.
Discuss issues that are included with us drug policy reform : Identify and discuss the issues that are included with US DRUG POLICY REFORM. Provide a narrative timeline describing how the reform has evolved over the past 50 years.
How much charge can the battery supply : What must be the area of a parallel plate capacitor, with plates separated a distance d = 0.01 mm and relative permittivity of 4 for the dielectric between the plates to supply the same charge as the battery in (a)?
Binary number handled by computer : Use the repeated subtraction method to convert the number 91 to binary (show your conversion steps clearly). What would be the representation of (-91)10 in an 8-bit binary signed magnitude form?
How would you recommend the planned order release : How would you recommend the planned order release (POR) and bill of materials (BOM) for all components for a week? Draw the feeder lines and show the arrangement of feeding components for assembly.
Why investing in any health care organizations technology : Justify the primary reasons why investing in any health care organization's technology and information system should align with the overall organization's strategic goals.
Discuss the problems of getting survey data in real world : Discuss the problems of getting survey data in the real world, also discuss ethics you need to consider when gathering survey data. Also give an example of a real world product and give suitable survey questions
What is the conductivity of the silicon used : If the velocity of the carriers is 2000 m/s, how many free charges (electrons) must be present in the device at all times?
Nursing practices use to promote patient rights : Discussion: The Nurse's Role in Promoting Patient Rights- What are some nursing practices you could use to promote patient rights and responsibilities?

Reviews

Write a Review

Supply Chain Management Questions & Answers

  Supply chain network design for cwc

This assignment explain the supply chain management process of cwc. What is the current annual supply chain cost?

  Criteria when making new location decisions

Identify a number of the typical criteria used when making new location decisions

  Draw the project network

Determine the mean critical path for Brent's job search process. What is the variance of the project duration?

  Compare and contrast economic - market, and relevancy

Please compare and contrast economic, market, and relevancy value.

  Brushing up on inventory control

Health system in Pennsylvania

  Supply chain strategy

Supply chain strategy

  What is the economic order quantity for fans in units

Nittany Fans of Lewistown, Pennsylvania, is a distributor of industrial fans used in plants, warehouses, and other industrial facilities.

  What factors reduce the capacity of the organization

What factors reduce the capacity of the organization to get its objectives?

  What is the total annual cost

What is the total annual cost

  Supply chain management questions

Briefly define the following two supply chain metrics: (i) inventory turnover ratio and (ii) supply chain velocity.

  Explain the supply chain management concept

Explain the supply chain management concept, Differentiate between public and private sector organisations in terms of their supply chain objectives and strategies

  How warehouses can add value in the supply chain

How warehouses can add value in the supply chain

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd