Background

The Innsmouth Central School District (the "District") in upstate New York planned to build a new athletic field, with stadium seating and other facilities (locker rooms, showers, etc.), on its property located along the Northern bank of the Miskatonic River (the "Project"). After competitive bidding, the District properly awarded the site work contract (the "Contract") to Lovecraft, Inc. ("Lovecraft") for a lump sum of $450,000.

Relevant Contract Terms

The Contract required Lovecraft to clear and excavate the site, including an area close to the Miskatonic River bank, where a rare, wild plant known as Yog-Sothoth was growing, and to level and restore the excavated area by refilling it with Yog-Sothoth-free soil and grass. Other notable provisions in the Contract are as follows:

PERMITS. Owner shall obtain all necessary permits for Contractor's Work on the Project.

CHANGE IN CONTRACT PRICE OR TIME. If Contractor wishes to make a claim for an increase in the Contract Price or an extension of time to perform the Work, Contractor shall give Owner written notice within 24 hours after the event giving rise to such claim. Such written notice shall specify the condition or circumstance on account of which such claim is asserted, and shall specify the increase in the Contract Price and/or time to perform which Contractor believes is justified on account of such condition or circumstance. Failure to strictly comply with the requirements of this paragraph shall result in a waiver of Contractor's claim.

NO DAMAGE FOR DELAY. Contractor agrees not to make any claim for delay costs, loss of productivity or efficiency, lost profits or extended home office overhead, on account of any delay, obstruction or hindrance for any cause whatsoever, whether or not foreseeable, whether or not anticipated and whether or not caused by Contractor.

Under Education Law § 3813 (a statute relating to claims against a school district), a contractor must present a written, verified notice of claim to a school district within 3 months of the date the school district rejects or denies the contractor's claim for payment under a contract. See New York Construction Law Manual, 2013 ed., § 7:18. Once the contractor has submitted its verified notice of claim, the contractor has 1 year to sue the school district to recover on the claim, running from the date of the denial or rejection of the claim.

The Dispute

Lovecraft began work on the Project on April 1, 2012. On July 1, 2012, the New York State Department of Environmental Conservation (the "DEC") ordered all work on the Project stopped because the District had failed to obtain a permit required under a Federal law that protected Yog-Sothoth. As a result, Lovecraft was prevented from working until the necessary permit was obtained. Lovecraft's equipment and personnel remained on site during the stoppage period.

On November 1, 2012, the District advised Lovecraft that it had obtained the required permit and ordered Lovecraft to recommence work. Lovecraft started working again, but by November 15, 2012, the ground was frozen and Lovecraft was unable to excavate or otherwise continue working on the Project.

On November 15, 2012, Lovecraft sent a letter to the District indicating that Lovecraft was entitled to a reasonable extension of time and compensation for the delay occasioned by the DEC's stop work order and the schedule's slippage into the winter. On December 13, 2012, the District wrote back to Lovecraft, rejecting Lovecraft's claim for an extension of time and compensation for the delay. Lovecraft kept its equipment on site, but was unable to resume work until March 15, 2013.

On April 1, 2013, the DEC issued yet another stop work order for the Project because the District had not actually obtained the necessary permit. The permit finally came on May 30, 2013. Lovecraft was back to work on June 1, 2013 and completed work on September 1, 2013.

On September 2, 2013, Lovecraft sent its final payment application to the District, which included costs due to delays (i.e., the costs to keep its equipment and personnel on site during the stoppage periods and the winter months when work was unfeasible). On September 30, 2013, the District sent notice to Lovecraft that its final payment application was rejected because "the delay costs are barred under the Contract." On October 15, 2013, Lovecraft serves a written, verified notice of claim for its contract balance and delay damages on the District.

Assume that, on December 12, 2013, Lovecraft sues the District for breach of contract, seeking its contract balance and delay damages. How will the lawsuit play out?

Verified Expert

Reference no: EM13497095

Questions Cloud

What is the initial horizontal velocity of the block : An 8.66g bullet is fired into a 260g block that is initially at rest at the edge of a table of h = 1.07 m height, What is the initial horizontal velocity of the block as it flies off the table
Determine the work done on the refrigerant in each cycle : During each cycle, a refrigerator ejects 605 kJ of energy to a high-temperature reservoir, Determine the work done on the refrigerant in each cycle
How much energy does it extract from the outside air : A heat pump has a coefficient of performance of 3.70 and operates with a power consumption of 7.15 103 W. How much energy does it extract from the outside air
What is the ending inventory value at cost : Barker Pet supply uses the conventional retail method to determine its ending inventory at cost. Assume the beginning inventory at cost (retail) were $531,200 ($653,800).
How will the lawsuit play out : Assume that, on December 12, 2013, Lovecraft sues the District for breach of contract, seeking its contract balance and delay damages. How will the lawsuit play out?
How much energy does it use in a single day : A freezer has a coefficient of performance of 6.30. It is advertised as using 446 kWh/yr. how much energy does it use in a single day
How much energy does the heat pump add to a home : A heat pump has a coefficient of performance equal to 4.35 and requires a power of 1.77 kW to operate. How much energy does the heat pump add to a home in one hour
What is the maximum efficiency possible for this engine : A heat engine operates between a reservoir at 26°C and one at 324°C. What is the maximum efficiency possible for this engine
Determine if everyone on the engagement team is independent : YOUCPA is a regional CPA firm engaged in public audit work of small- and medium-size firms in the Midwest. The YOUCPA firm has their main office in Chicago, Illinois, and regional offices in Minneapolis, Minnesota and Indianapolis, Indiana.

Reviews

Write a Review

Business Law and Ethics Questions & Answers

  Legal environment of business caselet

The assignment in Law deals with the topic "Legal Environment of Business". A case study about Mary, a newly joined employee who is working in the USA and Europe. She faces few issues at her work place in Europe and tries to talk to her manager who s..

  Business ethics & legal issues caselet

This assignment is about the concept of Business Ethics & Legal Issues. The laws relating to these can be found in Antitrust laws. These laws are concerned with those large corporations which have a majority of market share, mergers and acquisitions.

  Questions on business law and ethics

Examples of securities that are exempted from the registration provisions of the 1933 Act and involving misstatement of material facts in a prospectus.

  Discuss the doctrine of ratification of pre-incorporation

With the aid of a decided cases, discuss the doctrine of ratification of pre-incorporation contract.

  Discuss the extent of phoenixing activity

It has been estimated that about 6,000 phoenix companies operate in Australia, costing government and the community hundreds of millions of dollars per year and impacting on individuals.

  Application of law to facts

Company Law, Application of Law to Facts and Conclusion.

  Question on business law and ethics

This assignment related to business law.

  Questions on business law

Answer all the questions under business law.

  Iidentify the issue raised by the facts

Iidentify the issue(s) raised by the facts, identify the relevant legal principles, apply the relevant legal principles to the facts, reach a conclusion.

  Evaluation of software development

Prepare a report and present an evaluation of the subsequent methodologies for software development in terms of cost, resources and time.

  Business value and ethics

Business value and ethics,  Bart agrees to put Sam's Super Bowl champion-ship autographed football in his sports store to sell for $1,500. Sam agrees to pay Bart a 15% commission for selling the ball. If Joe comes in the sports store and offers Bart ..

  Explain what is meant by income by ordinary concepts

Advise what tax consequences arise in respect of the payments.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd