The process for renewing a driver's license at the Archer County Courthouse is as follows. First, the clerk fills out the application; then the clerk takes the driver's picture; and finally the typist types and processes the new license. It takes an average of five minutes to fill out an application, one minute to take a picture, and seven minutes to type and process the new license. If there are two clerks and three typists, where will the bottleneck in the system be? How many drivers can be processed in one hour if the clerks and typists work at 80 percent utilization rate?

Reference no: EM13227923

Questions Cloud

State the reaction between magnesium and cobalt sulfate : Write the balanced molecular, ionic and net ionic equations for the reaction between magnesium and cobalt(II) sulfate. (b) What is oxidized and what is reduced in the reaction?
A liquid start to appear on the inside of a closed flask : A liquid begins to appear on the inside of a closed flask. At first glance before the liquid began to appear, you might have thought the flask was empty
Which of these two methods has the greater accuracy : An analyst must decide between two different forecasting techniques for weekly sales of roller blades: a linear trend equation and the naive approach. The linear trend equation is Ft = 127 + 1.9t, and it was developed using data from periods 1 thr..
Present arguments that both support and refute this view : Some have argued the Six Sigma programs are merely repackaged versions of older quality improvement programs that originally accompanied TQM initiatives in the 1980s. Present arguments that both support and refute this view.
How many drivers can be processed in one hour : How many drivers can be processed in one hour if the clerks and typists work at 80 percent utilization rate?
Calculate the phase currents and the line currents : A three-phase, 400 V system has the following load connected in delta: between the red and yellow lines, a non-reactive resistor of 100; between the yellow and blue lines, a coil having a reactance of 60 and negligible resistance
Explain equilibirum with its ions in saturated solution : Solubility constant for is 8.1E-12. When is in equilibirum with its ions in saturated solution. The concentration of silver ions.
How many drivers can be processed in one hour : How many drivers can be processed in one hour if the clerks and typists work at 80 percent utilization rate?
Explain a certain reaction has an activation energy : A certain reaction has an activation energy of 70.0 kj/mol and a frequency of factor A1=7.80*10^12 M^-1 s^-1. what is the rate constant, k of this reaction at 24.0 degrees celcius.

Reviews

Write a Review

Operation Management Questions & Answers

  Define the term de facto corporation

Define the term de facto corporation and list the 3 terms that must exist in order for it to exist. Define the term corporation by estoppel.

  Describe some of the best practices that leading companies

Has any aspect of the different levels approach been negative to the customer, or to the organization? Describe some of the best practices that leading companies using unique approaches to customer service have embraced.

  Explain how were pine valley furniture projects initiated

Explain how were Pine Valley Furniture's projects initiated. Illustrate what is the focus for each of the new systems.

  Use epq to calculate the the order quantity

Use EPQ to calculate the the order quantity? What is the total annual inventory cost of the EPQ plan?

  Find out machine downtime also operator cost

Find out machine downtime represents a cost of $70 per hour; operator cost (including salary and fringe benefits) is $15 per hour. Illustrate what is optimum number of operators.

  Explain the problems of homelessness

Explain the problems of homelessness based upon the developmental, situational, and human needs perspectives

  Calculate a new mrp that improves the base mrp

The part in question, 3079, is used in two different subassemblies: no. 435, which is used in the Gemini TV stand, and no. 257, which is used in the Saturn microwave stand. One of part 3079 is used in each subassembly, and one of each subassembly ..

  What activities would be included in the value added time

What activities would be included in the value added time of fast food hamburger preparation and delivery? Why are these part of the Value Added Time?

  How many laburers are employed at the plant

If the labourer productivity at the plant is 0.15 hot water heaters per labour hour, how many laburers are employed at the plant?

  What are processes and techniques to make the budgeting

What are some processes and techniques that you would suggest to make the budgeting process work well? Start with general but also provide some specifics as relate to creating detailed project budgets. Be sure to justify why you think your recomme..

  Production scheduling information systems for ferro

Two new production scheduling information systems for Ferro Corporation could be developed at a cost of $105,000 and $135,000 respectively

  What advice might herzberg give bridget

Would Cliff Richards be categorized as a Theory X or Theory Y manager? Explain. What advice might Herzberg give Bridget about dissatisfaction among her employees?

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd