How is project scope defined

Assignment Help Operation Management
Reference no: EM132029342

1 A good starting point for developing time and cost estimates is

Task analysis.

Work packages.

Work breakdown structure.

Time and motion studies.

Past experience.

2 A professional organization for project managers is the

PMI.

IPM.

AMA.

MIS.

PMBOK.

3 All of the following are disadvantages of organizing projects within a matrix arrangement EXCEPT

Dysfunctional conflict between functional managers and project managers.

Infighting.

Expensive.

Longer project duration.

Stressful.

4 Estimates are supposed to be based on normal conditions. While this is a good starting point, it rarely holds true in real life.
True
False

5 Estimating can be challenged by

Political dynamics.

Human Nature.

Difficulty in predicting the future.

All of these choices.

6 Having a strong communication plan can go a long way toward mitigating project problems. A communication plan should address all of the following EXCEPT

Which methods will be used to gather and store information.

When the information will be communicated.

What information needs to be collected and are there limits as to who has access to it.

How information should be communicated and to whom.

All of these should be addressed in a communication plan.

7 How is project scope defined?

The length of your project and how much it will cost

The deliverables or outputs during the course of the project

The range of customer expectations

What you expect to deliver to your customer when the project is complete

The range of resources you have available and their capabilities

8 In practice, estimating processes are frequently classified as

Rough/polished.

Precise/order of magnitude.

Top down/bottom up.

Draft/final.

Broad/Specific.

9 Laura is forecasting the time and cost of developing an intranet for a new customer. Her department has completed six such intranets for customers during the last two years. Although the proposed system is about the same size as the others, she estimates that it will take about 10 percent less time and money. Which of the following methods is she using?

Apportion

Learning curve

Template

Ratio

Function point

10 Project management is important to understand when people are a part of a project team because they

Need to understand project priorities so they can make independent decisions.

Need to understand the project charter or scope statement that defines the objectives and parameters of the project.

Work with others to create a schedule and budget.

Need to be able to monitor and report project progress.

All of these are reasons it is important for project team members to understand project management.

11 Project selection criteria are typically classified as

Required and optional.

Short-term and long-term.

Strategic and tactical.

Cost and schedule.

Financial and nonfinancial.

12 Reasons why estimating time and cost are important include all of the following EXCEPT

To help establish a project selection process.

To determine how long the project should take and cost.

To schedule work.

To determine how well the project is progressing.

To develop cash flow needs.

13 Refining estimates may be necessary for a number of reasons. For example, design flaws being revealed after the fact, extreme weather conditions, and accidents occurring are good examples of

Normal conditions not applying.

Changes in project scope.

Hidden interaction costs.

Things going wrong on a project.

None of these are correct.

14 The ideal approach to estimating project time and costs is to use both the top-down and the bottom-up approach.

True
False

15 The process of forecasting or approximating the time and cost of completing project deliverables is called

Guesstimating.

Estimating.

Planning.

Predicting.

Budgeting.

16 The structure that manages projects within the existing organizational structure is ________ organization.

Projectized

Balanced matrix

Weak matrix

Functional

Strong matrix

17 The tendency for the project deliverables to expand over time-usually by changing requirements, specifications, and priorities-is called

Scope erosion.

Scope creep.

Project add-ons.

Project bloat.

Scope enhancement.

18 Which of the following is an advantage of a functional project management organization?

Strong motivation of project team members

Maximum flexibility in the use of staff

Good integration across functional units

Longer project duration

Shorter project duration

19 Which of the following is true of multiweighted scoring models?

Each criterion is assigned a weight.

Will include qualitative criteria

Will include quantitative criteria

Projects with higher scores are considered more desirable.

All of these are true.

20 Which of the following is NOT one of the stages of a project life cycle?

Planning

Closing

Defining

Identifying

Executing

Reference no: EM132029342

Questions Cloud

What is the restaurant profit : How many pizzas does the restaurant produce and what is the price? What is the restaurant's profit?
Develop the processes for your project : Take the general project plan that you submitted in Week 1, and develop the processes for your project.
Which costs would you consider and why : Also, in deciding whether to drive from New York to Pittsburgh(about 1,000 miles round trip) to visit a friend, which costs would you consider and why?
Discuss and explain the concept of greening the supply chain : Discuss and explain the concept of "greening the supply chain". An answer must be presented in complete sentences, written in third person.
How is project scope defined : Estimates are supposed to be based on normal conditions. While this is a good starting point, it rarely holds true in real life.
Powering sustainable growth in emerging markets : Statement of problem or problems facing the firm - Explain why you believe it or they is important
What tools are used to analyze market research data : Answer in 150 words. What tools are used to analyze market research data? The response must be typed, single spaced.
Create an external factor analysis table for the company : Create an external factor analysis (EFAS) table for the company you researched. Use Microsoft Word, or a similar program, to create your table.
Investment with respect to real interest rates : How do we know if buyers receive a high return on investment with respect to Real Interest Rates, Nominal Interest Rates, and Inflation Rates?

Reviews

Write a Review

Operation Management Questions & Answers

  Great results with their six sigma programs

Some organizations achieve great results with their six sigma programs in terms of market and revenue growth, increased customer satisfaction, etc,

  Find the probabilities of the binary symbols 0 and 1

Consider the transition probability diagram of a binary symmetric channel shown in Figure.- Find the probabilities of the binary symbols 0 and 1 appearing at the channel output.

  Uncertainty when applying and analyzing linear regression

What are some causes of uncertainty when applying and analyzing linear regression

  What are the ethical issues and potential social

What are the ethical issues and potential social responsibilities highlighted by this change. Consider customers, employees, the current and new communities, and other stakeholders. How might these issues be dealt with most appropriately

  Conduct a swot analysis for the organization

Comprise, in the strategic objectives, the tools used by the organization to measure consumer satisfaction. Examine how these measurements could be used to enhance quality planning.

  Define organizations in need of logistic solutions

ADC is a Colorado-based logistics company that engages in consulting projects to share their expertise with organizations in need of logistic solutions. They have completed three sequential projects for customers.

  What factors were responsible for the target breach

What factors were responsible for the Target breach? Who should have been responsible for the breach?

  Evidence-based characteristics of educational leadership

What are some evidence-based characteristics of educational leadership?

  What is danger in over simplifying globalization approach

What is the danger in over simplifying the globalization approach? Would you agree with the statement that" if something is working in a big way in one market you better assume it will work in all markets"? What are the basic reasons why Country oper..

  What are reasons for the small numbers of female expatriates

What are the reasons for the small numbers of female expatriates? What more can companies do to use women as a resource for international management? Do you believe repatriation of women is different from repatriation of men? Why or Why not?

  Listing and explaining key km lessons learned

Listing and Explaining Key KM Lessons Learned

  Looking for budget-priced flight home for holidays

Given that Gabbie is looking for a budget-priced flight home for holidays, she will need to determine which flight features are most important to her.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd