Q. A manufacturing firm produces 2 products, A and B. Each of these products must be processed during 2 different machines. One machine has 12 hours and the second machine has 8 hours of available capacity. Each unit of product A requires 2 hours of time on both machines. Each unit of product B requires 3 hours of time on the first machine and one hour on the second machine. The incremental profit is $6 per unit of product A and $7 per unit of product B and the firm can sell as many units of each product as it can manufacture.
a. Formulate the linear program problem.
b. Find the optimal solution using the graphical method (the number of products manufactured and maximum profit to be achieved).
c. Find the optimal solution by making use of Excell solver.
Explain how are the mean activity times and activity variances computed in probabilistic CPM/PERT analysis.
Recognise the importance of a strategic approach to the development and deployment of organisational information systems. Demonstrate an understanding of the importance of databases and their integration to the organisation's overall information mana..
Describe how would waiting time change if the Corporation decides to limit all rentals to exactly 72 hours. Suppose which if such a restriction is imposed, the number of customers requesting a phone would be reduced to 20 customers per day
Formulate linear programming model for this problem. Mention the objective function (minimize or maximize) and all model constraints. Solve this model graphically. Identify the following: each constraint line, feasible solution area, x1, x2 and Z..
The strategy of the Sherman Anti-Trust Act and other U.S. antimonopoly legislation is to ensure that each company has meaningful competitors in every product market in which it participates.
This was expected to cost a total of $8,501,000. To date they have spent $5,001,000 on the superstructure. Computes the schedule variance, schedule performance index also cost performance index for the project to date.
The shop has enough brewing capacity to brew 30 gallons of these 2 coffee blends every day. The manager wants to know Explain how many cups of every blend to sell every day in order to maximize sales.
a) Construct the product structure tree for both fans and their component parts. b) Complete the MRP for the fans and their component parts.
Suppose you were conducting the marketing research study for your company. Which of following factors: cost, culture, time, or geography, would have the greatest affect on your research? Why?
Assume a software producer is about to release a new version of its popular software. Illustrate what information do you think it would take into account in forecasting initial sales.
If the blend needs to score at least 300 points for shade tolerance, 400 points for traffic resistance also 750 points for drought resistance, describe how many pounds of every seed should be in the blend. Describe how much will the blend cost.
Why is participation considered such an effective technique for reducing resistance to change. Describe at least 3 other tactics which are also useful to reduce resistance to change.
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +1-415-670-9521
Phone: +1-415-670-9521
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd