Time-Cost Trade-Offs

Activity

Predecessor

Total Normal time (day)

Total Crash time (day)

Total Normal cost ($)

Total Crash cost ($)

Available crashing days

Crashing cost per day       (cost slope)

A

---

6

5

60

90

 

 

B

---

7

4

50

150

 

 

C

A

6

4

100

200

 

 

D

A

7

7

30

30

 

 

E

B

5

4

70

85

 

 

F

C

9

7

40

120

 

 

G

E, D

7

4

50

230

 

 

Overhead project costs  (Indirect costs) are $70 per day.

Please crash the project and find the project schedule with the lowest total cost (indirect cost + direct cost).

Rule of thumb:

Crash the project one period at a time.

Crash the least expensive activity that is on the critical path.

Critical path will very likely change after each crashing, find new critical path each time before crashing.

Reference no: EM13725284

Questions Cloud

Discusses era of reform and its impact on america commitment : Discusses the era of reform and its impact on America's commitment to liberty. Did this reform movement increase or decrease the nation's commitment to, and practice of liberty.
Purpose of a bia : Question 1: What is the goal and purpose of a BIA? Question 2: Why is a business impact analysis (BIA) an important first step in defining a business continuity plan (BCP)?
What is the value of fun toys equity : Fun Toy Corporation estimates that there is 25% chance of a recession economy next year, a 50% chance of a normal economy next year, and a 25% chance of a boom economy next year. The corporation will exist until the end of next year and then it will ..
Statements about the payback method : Which ONE of the following statements about the payback method is true? The payback method is consistent with the goal of shareholder wealth maximization. The payback method represents the number of years it takes a project to recover its initial inv..
Find the project schedule with the lowest total cost : Overhead project costs  (Indirect costs) are $70 per day. Please crash the project and find the project schedule with the lowest total cost (indirect cost + direct cost)
Evaluating a project-what is the npv of the project : Monroe, Inc., is evaluating a project. The company uses a 13.8 percent discount rate for this project. Cost and cash flows are shown in the table. What is the NPV of the project?
Apply the tools and techniques in research : Project objective:1.Apply the tools and techniques in research and analysis required to evaluate computer and information science products.2.Describe how pipelining and superscalar processing improve the speed at which a computer program is executed...
Concepts in the development : Select, read and analyze one (1) comprehensive case presented in the text. Please apply all aspects of the course concepts in the development of your case solution.
Write an essay on martin luther : If Martin Luther King was alive today, do you think he would say his dream of racial equality in the United States has been realized? Why or why not?

Reviews

Write a Review

Operation Management Questions & Answers

  Discuss the two methods of integration as leadership tools

discuss the two methods of integration as leadership tools and how each method can effectively be implemented in a MNC environment.

  Maximize the game girl market share

Bill is worried about competing toy stores gaining share during the Christmas buying season. He has seen many companies lose their share by failing to keep prices in line with the performance of their products. He would like to maximize the Game ..

  What is the level production rate with no ending inventory

What is the ending inventory for month 4 under this plan? B) What is the level production rate with no ending inventory for month 4?

  Creating control p chart

A professor records the number of students who complain each week throughout the semester. If the class size is forty students, what are 3-sigma control limits for this class?

  Calculate the labor-force participation rate

Suppose that the country of Bigu has a population of 127 million, of which 83 million are in working- age population. of those, 2.5 million are not in the labor force and 52 million are employed.

  Explain and evaluate the business-level strategy

Research the corporate-level of strategies and evaluate the business-level strategy do you believe is appropriate to offset forces in the industry for Victory Motorcycles.

  Which license enables anyone on the network

Which license enables anyone on the network to install and use the software?

  Create a decision tree and analyze the data

You are the captain of basketball team and have to make decision of playing five. Four players are already selected and you have to make decision among three players named Andrew, Jack and Matt. Assume that only one will be selected and others won..

  Based on this data and the multiplicative seasonal model

Based on this data and the multiplicative seasonal model, what will the demand level be for Mark's sailboats in the spring of 2011?

  Choose a publicy traded corporation and determine the impact

Choose a publicy traded corporation and determine the impact of the company's mission, vision, and primary stakeholders on its overall success.

  Illustrate what other factors are relevant to this issue

Illustrate what o r factors are relevant to this issue. Elucidate how do changes in assumptions mentioned by o r managers affect proposal. Illustrate what position should Jim take.

  Concept of interactive design mean for service

What does the concept of interactive design mean for a service such as the adventure playground described here?

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd