Find the production capacity of the line

Assignment Help Operation Management
Reference no: EM131396581

Producing an item requires 6 different tasks. Let tj denote the time (in seconds) to complete task j. We have: t1 = 30, t2 = 25, t3 = 35, t4 = 40, t5 = 15, t6 = 30. You would like to divide the tasks to 4 workers to constitute a production line. a. Find the production capacity of the line for the following assignment: Worker 1 → Task 1, Worker 2→ Task 2, Worker 3→Tasks 3,4, Worker 4→ Tasks 5,6. b. Find optimal assignment (to maximize the production capacity) if the task sequence should not be broken (task j should be done before task j +1). c. Find optimal assignment (to maximize the production capacity) if the task sequence can be broken (no precedence relationship between tasks). 1 d. Assume that the daily demand for this item is 400 and that each worker costs 15 TL/hr. Find the direct labor cost per item if the task sequence should not be broken. Please do not solve it with computer-aided programs.

Reference no: EM131396581

Questions Cloud

Find the production capacity of the line : Producing an item requires 6 different tasks. Let tj denote the time (in seconds) to complete task j. We have: t1 = 30, t2 = 25, t3 = 35, t4 = 40, t5 = 15, t6 = 30. You would like to divide the tasks to 4 workers to constitute a production line. Find..
Discuss steps used in determining how to select media venue : Discuss the steps used in determining how to select a media venue. Describe each of the five W’s for your media planning. Describe the three most important rules of media buying and why they apply to your client.
Just-in-time replenishment-tight inventory control systems : Office Depot sells a wide range of office supply products and services in the United States and internationally. The company tries to offer a wider range of office supplies at lower cost than other retailers by using just-in-time replenishment and ti..
Find the minimum dimensions for the receiving area. : The weekly average number of incoming palletized load units at the SISA DC at Gioia Tauro in Italy is 21 465. The average time needed to unload a vehicle is 18.3 minutes.  Find the minimum dimensions for the receiving area.
Find the production capacity of the line : Producing an item requires 6 different tasks. Let tj denote the time (in seconds) to complete task j. We have: t1 = 30, t2 = 25, t3 = 35, t4 = 40, t5 = 15, t6 = 30. You would like to divide the tasks to 4 workers to constitute a production line. Find..
Consider production system consisting of two resources : Consider a production system consisting of 2 resources M1 and M2. These resources are used to manufacture two different products A and B. Product A requires a standard time of 4 minutes on resource M1 and 3 minutes on resource M2. What would be the f..
Margins could be small but sales quantum will be huge : Present a scheme of your choice of the distribution channels for a low price, ‘Low – tech’ domestic consumption product. Margins could be small but sales quantum will be huge.
Core culture and elements of its observable culture : Using an organization with which you are familiar, identify its core culture and the elements of its observable culture as defined by Senge. What do you think would need to be changed in order to facilitate learning? What role would organizational de..
Crocs operation strategy model : The second paragraph should introduce the most important points of the case study. For example, what does Crocs manufacture and sell, and what are the most important issues identified in the case? Crocs’ Operation Strategy Model. New Product Developm..

Reviews

Write a Review

Operation Management Questions & Answers

  What type of development process

What type of development process would you expect to find in a established company successful at developing residential air-conditioning units? How about for a small company that is trying to break into the market for racing wheelchairs?

  Creating a better web that''s better for the environment

How does Google integrate the idea of creating a "better web that's better for the environment" with its strategies for creating profit and value?

  What is the direct labor cost per unit

Which process step has the highest capacity? d. If the wage rate is $ 36 per hour per person, what is the direct labor cost per unit?

  Using fama-french three-factor model

An analyst has modeled the stock of a company using a Fama-French three-factor model. The risk-free rate is 3%, the market return is 10%, the return on the SMB portfolio (rSMB) is 2.9%, and the return on the HML portfolio (rHML) is 4.5%. If ai = 0, b..

  How many kanban card sets should be authorized

Hinge Manufacturing Company employs a Kanban system for a component part. The daily demand is 900 hinges. Each container has a wait time of 0.05/day, and a processing time of 0.37 days. The Container size is 60 hinges and the safety factor (a) is ..

  Who might be liable to paul pedestrian

If Paul sues Derek, in what state(s) could he sue, and in what court (federal or state) could he properly file the suit?

  Discuss fraud and abuse in healthcare

Discuss fraud and abuse in healthcare. Provide at least three specific examples of fraudulent practices that have taken place in U.S. healthcare,

  Illustrate what result for thomas

Thomas's house is set on fire also burns to ground. Owners of massage parlour also Thomas sue Ralph for negligence.Illustrate what result for massage parlour.

  Finding the critical path for a project

When creating activities on node, and after finding the critical path for a project, if you need to crash a project, can you only choose time reductions from the critical path/paths?

  Determining the appropriateness of managerial actions

Assume your boss asks you to create a spreadsheet to evaluate the key variables that early contingency theories suggested were important for determining the appropriateness of managerial actions. Which variables would you need to include in the sprea..

  Different industries that employ jit manufacturing

Search for two companies belonging to different industries that employ JIT manufacturing. Demonstrate why the companies of your choice adopted the concept and what the result has been for each company since the change was implemented.

  What takt time would match capacity and demand

What takt time would match capacity and demand if demand is 120 units a day, there are two shifts of 480 minutes each, and workers are given three half-hour breaks during each shifts, one of which is for lunch or diner?

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd