Find the base saturation flow rates for each lane

Assignment Help Civil Engineering
Reference no: EM131499452

Assignment: Traffic Analysis

Problem 1: Roundabouts

As part of the transport impact assessment for a proposed residential development off Zinglemann Road at Klemzig, you have been asked to evaluate the performance of a single- lane roundabout under 2018 weekday AM peak hour traffic projections as a possible intersection form to replace an existing stop-controlled cross intersection, which has been found to be inadequate for the proposed conditions. The figure below illustrates the proposed intersection form, turning movements and flow rates.

583_Figure.jpg

Figure 1 Lane allocation and control, turning movement flow rates (veh/h)

Table 1 Roundabout Parameters

The geometric characteristics of the roundabout are listed in the table below.

Criterion

Single-lane roundabout

Approach lanes

1 east and west, 1 north and south

Circulating lanes

1

Circulating lane width

6.5m

Central island diameter

10.5m

Entry lane width

4.3m

Assume that any pedestrians and cyclists (flows not shown) give way to vehicle traffic. Stating any other assumptions you need to make, conduct your roundabout intersection analysis in a spreadsheet table according to the following procedure:

(i) Calculate the conflicting flow rate past each approach to the roundabout;

(ii) Calculate the flow rate on each approach entry lane;

(iii) With the aid of your current EGB272 lecture notes, estimate the follow-on time and critical gap for each approach entry lane;

(iv) Estimate the headway distribution characteristics of the conflicting stream past each approach to the roundabout;

(v) Estimate the theoretical capacity and degree of saturation of each approach entry lane. Compare with the standard roundabout practical degree of saturation of 0.85;

(vi) Estimate the average queuing delay on each approach lane;

(vii) Estimate the maximum (95th percentile) design queue length on each approach lane;

(viii) Comment on the overall operation of the proposed roundabout for the conditions analysed, including the amount of spare capacity to accommodate traffic growth.

Other requirements
- Use a tabulated spreadsheet to complete this problem.
- Numbering of the movements in your response must be the same as those shown here. In your spreadsheet, your movement calculations must be ordered in rows from the lowest to highest movement down the page. For each movement clearly carry your calculations in rows right across the spreadsheet and be consistent with placement of these calculations for all movements.
- In your spreadsheet, your lane calculations must be ordered in rows according to the following convention: S1, E1, N1, W1.
- Use sensible rounding when displaying answers on your spreadsheet (Excel has a displayed rounding tool, while still carrying the values to a high level of significance throughout the calculations). For example, flows in whole veh/h or 0.xxx veh/s, delays to whole s, and queue lengths to the next whole veh.
- Submit clearly labelled your electronic spreadsheet via Turnitin with your hard copy
of your working so that it can be followed.

Problem 2: Signalised Intersections

As part of the transport impact assessment, you also have been asked to evaluate the performance of a signalised intersection at the cross intersection of Zinglemann Road and Old School Road under the 2018 weekday AM peak hour traffic projections shown in the following figure, as a possible replacement. The intersection geometry, movement numbers and flows, and signal phasing arrangement are shown in the following figure and table.

767_Figure1.jpg

Figure Proposed Signalised Intersection Information

The required parameters for the proposed signalised intersection control are given as follows.

Table Signalized Intersection Parameters

Criterion

Value

Environmental class: Old School Rd

A

Environmental class: Zinglemann Rd

B

Grade: Old School Rd

0%

Grade: Zinglemann Rd

-4% (south approach only)

Curve Radii (all approaches)

Nil tight

Pedestrian crossings

Nil

Heavy vehicles

8% (north approach only)

Yellow time

4s

All-red time

2s

Minimum green time

2s

Lost time (all movements)

(assume same as intergreen time)

Optimal Cycle Time k Value

0

Other requirements
- Use a tabulated spreadsheet to complete this Problem.
- Reproduce the following tables for inclusion of your calculations in your spreadsheet.
- Numbering of the movements in your response must be the same as those shown here. In your spreadsheet, your movement calculations must be ordered in rows from the lowest to highest movement down the page. For each movement clearly carry your calculations in rows right across the spreadsheet and be consistent with placement of these calculations for all movements.
- In your spreadsheet, your lane calculations must be ordered in rows according to the following convention: S1, S2...; E1, E2...; N1, N2...; W1, W2...
- Use sensible rounding when displaying answers on your spreadsheet (Excel has a displayed rounding tool, while still carrying the values to a high level of significance throughout the calculations): Display flow rate to three decimal places, probability to three decimal places; degree of saturation to two decimal places; delay to nearest whole second; queue length rounded upwards to nearest whole vehicle.
- Include all your working in your report.

(i) Find the base saturation flow rates for each lane.

(ii) Lane width and gradient factors adjustment.

(iii) Traffic composition factor adjustment.

(iv) Flow ratio calculation.

(v) Critical movement identification and intersection flow ratio.

(vi) Cycle time calculation.

Calculate optimal cycle time, practical cycle time, and cycle time to use.

(vii) Green time allocation.

(viii) Average delay time and level of service.

Attachment:- unsignalised example.xlsx

Attachment:- Template.rar

Verified Expert

Traffic from a scientific technical point of view which demands the series of variable components such as series of concepts, variables and the parameters which allow to understanding and approach the solution to solve the traffic problem. The fundamental of traffic parameters is traffic flow, speed, Density of Traffic, Traffic volume, Equivalent hour flow, Hour Flow, Peak hour flow, Daily flow, Maximum Daily Flow Traffic composition.

Reference no: EM131499452

Questions Cloud

How do you feel at present about your artistic development : How do you feel at present about your artistic development? What if anything, has happened since your childhood to influence your feelings and abilities in art?
Accounting versus economic profit : Describe the difference between accounting versus economic profit assessing in detail the different cost definitions (explicit versus implicit).
Write a case brief using the irac method : Read "The IRAC method of case study analysis".Select one legal case from the following list and discuss the case with your Learning Team.
Determination about the state of the economy : Assume the United States has a potential GDP of approximately $18 trillion. Use economic indicators from the last eight quarters to make a determination.
Find the base saturation flow rates for each lane : EGB272 Traffic and Transport Engineering - Find the base saturation flow rates for each lane and Lane width and gradient factors adjustment.
Summarize the type of study and phenomenon of interest : Locate at least 4 contemporary, peer-reviewed articles or dissertation or thesis research studies that are qualitative in nature.
Preparing for the exam whose actual exam score : For a student who spent 3.5 hours preparing for the exam whose actual exam score is 56, what is the prediction error?
Define physical evidence : Define physical evidence.Using the library, Internet, any other available materials,research the types of physical evidence that can be obtained by criminalist.
Define the strategic advantages : Do you believe that strategic advantages obtained by theeffective use of IT are sustainable? Why or why notDo you believe that strategic advantages obtained.

Reviews

inf1499452

6/13/2017 4:50:59 AM

Around tomorrow(Sunday) 10am (UTC+10:00) If it is complete one, that will be perfect. However,whether it is done or not, can I get a partial work for this order? Thank you. If it is a part work, just sent me through email () Roundabout 23496063_1Roundabout question.pdf Singalised 23496085_1Signalised intersection question.pdf Signalised solution 23496066_1Signalised intersection question solution.pdf Signalised question 2 23496011_1Signalised intersection question 2.pdf Signalised question 2 solution 23496013_1Signalised intersection question 2 solution.pdf Excel file that I send is just an example. (How it will look)That is why I titled unsignalised exmple Base on how it look, I wanted to have excel files for roundabouts and signalised intersections. (Problem 1 and 2) However, I don't get the part " which figure used for this assignment because both figures you are sending is different." Can you explain it more clearly? This is all I got. lecture slides, tutorial questions and solutions. Please, check and tell me what to do. 23496010_1lecture tutorial problem and solution.zip

len1499452

5/17/2017 8:05:23 AM

6 Your answer is mostly correct, demonstrated by: • Correct choice of equations but one minor error in use. Answer nearly correct • Solution process complete, neat and comprehensible presentation of steps • Minor inconsistencies in calculations, tabulations and/or mostly complete and presented in orderly fashion • Answer presented with nearly correct significance and correct use of units Your submission demonstrates: • A minor error in engineering documentation format • Complete details of analysis • Adherence to spelling & grammar • Conventions with few errors, where required • Neat dimensioned or scaled drawings, where required

len1499452

5/17/2017 8:04:51 AM

Problem-1 (Roundabouts): a) Neatly presented hand calculations; and b) Excel file for roundabouts. Problem-2 (Signalised Intersections): Excel file for signalised intersections.Criterion Weighting 7 1. Demonstrate an understanding of the theory of the road system elements 2. Analyse the operation of road system elements in the context of an investigation 8/10 Your answer is fully correct, demonstrated by: • Correct choice and use of equations. Answer fully correct • Solution process complete, neat and easily followed presentation of all steps • Calculations clearly and fully tabulated and/or complete and presented in an orderly fashion • Answer presented with correct significance and correct use of units 3. Demonstrate effective written communication to an audience of discipline specialists 2/10 Your submission demonstrates: • Correct engineering documentation format • Complete and comprehensive details of analysis as stipulated • Correct adherence to spelling & grammar conventions, where required • Neat scaled dimensioned drawings, where required

Write a Review

Civil Engineering Questions & Answers

  Engineering ethics and ethical issue

what is the engineering ethics course where to write about any engineering ethical case and discuss the ethical issue?

  Engineering ethics and concept and cases

what is the engineering ethics case related to civil engineering with reference and discuss all the engineering ethics issues which covered the "Engineering etics concepte and cases?

  Transportation and management

In the construction management, there is a lot of procurement route that are necessary and suitable for the construction industry.

  Supporting Investment Promotion: ERNST & YOUNG

Ernst & young is currently providing support to various sectors. In this regards it was felt that if this report is able to document good practices currently being adopted or planned in ceramic sector.

  Personalized Cancer Therapy-A step forward

Cancer is the uncontrolled growth of abnormal cells in the body resulting in tumours that can be benign or malignant (cancerous cells). A proper treatment is necessary to fight with this serious disease.

  Discuss the different environmental companies

Discuss the different agencies, institutes, centers, different environmental companies that are active in UAE.

  Develop a simple urban constructed wetland design

Develop a simple urban constructed wetland design.

  Evaluate company performance in relation to GRI standards

Evaluate company performance in relation to GRI standards and comment on Stigler's theory.

  Water system design

Determine the corresponding error in the computed discharge

  Hydraulic behaviour in open channel

Describe how test flumes and associated equipment are used to assess and confirm hydraulic behaviour in open channel

  Write a paper on steel sustainability

Write a paper on steel sustainability.

  Writing case study about bridge collapse

Writing case study about bridge collapse

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd