Problem 1
The following data were obtained from an in-house MIS project-
Activity Duration Predecessors
A 3 Days ---
B 6 Days ---
C 3 Days B
D 2 Days A
E 3 Days C,D
F 2 Days A
G 4 Days F
H 7 Days B
I 2 Days C,D
J 4 Days H,I
K 8 Days H,I
L 5 Days E,G,Ja) What are the critical path activities?
b) What is the project's scheduled completion time?
c) What is the slack or float for Activity C? Show your calculations.
d) What is the slack or float for Activity F? Show your calculations.
e) What is the slack or float for Activity E? Show your calculations.
f) What is the slack or float for Activity J? Show your calculations.
Problem 2.
A project to remodel an office area has the following activities.
|
Activity
|
Duration
|
Predecessors
|
|
A
|
3 months
|
---
|
|
B
|
2 months
|
---
|
|
C
|
3 months
|
---
|
|
D
|
4 months
|
A, B
|
|
E
|
3 months
|
A
|
|
F
|
2 months
|
B, C
|
|
G
|
2 months
|
F
|
|
H
|
1 month
|
G
|
|
I
|
4 months
|
D, E, F
|
|
J
|
5 months
|
H
|
a) What are the critical path activities?
b) What is the project's scheduled completion time?
c) What is the slack or float for Activity B? Show your calculations.
d) What is the slack or float for Activity D? Show your calculations.
e) What is the slack or float for Activity F? Show your calculations.
f) What is the slack or float for Activity I? Show your calculations.
Problem 3
Information from a room addition project:
|
|
Duration
|
Predecessors
|
|
|
A
|
2 wks
|
|
|
|
B
|
3 wks
|
|
|
|
C
|
5 wks
|
|
|
|
D
|
7 wks
|
A
|
|
|
E
|
3 wks
|
B
|
|
|
F
|
2 wks
|
C
|
|
|
G
|
4 wks
|
F
|
|
|
H
|
1 wk
|
A
|
|
|
I
|
8 wks
|
D, E, G
|
|
|
J
|
5 wks
|
F
|
|
|
K
|
2 wks
|
D, E, G, H
|
|
|
|
|
|
|
a) What are the critical path activities?
b) What is the project's scheduled completion time?
c) What is the slack or float for Activity A? Show your calculations.
d) What is the slack or float for Activity F? Show your calculations.
e) What is the slack or float for Activity H? Show your calculations.
f) What is the slack or float for Activity K? Show your calculations.
Problem 4
InformAtion from a site renovation project:
Task Duration Predecessors
A 2 wks _
B 5 WKS A
C 3 WKS B
D 15 WKS B
E 8 WKS C
F 10 WKS C
G 2 WKS D
H 6 WKS E, F, G
I 5 WKS H
a) What are the critical path activities?
b) What is the project's scheduled completion time?
c) What is the slack or float for Activity C? Show your calculations.
d) What is the slack or float for Activity F? Show your calculations.
e) What is the slack or float for Activity I? Show your calculations.
f) What is the slack or float for Activity K? Show your calculations.
|
Is the following argument valid or invalid
: Is the following argument valid or invalid? If valid, explain whether it is deductive or inductive. If invalid, explain why: "Mrs. Kelvin has accused me of intentionally denting her rear fender
|
|
What is the service level implied by ben''s reorder point
: Suppose Ben decides to reorder 35 mm film when there are 86 rolls left in stock. How much safety stock is implied by this reorder point. What is the service level implied by Ben's reorder point of 86 rolls
|
|
Decision and discuss the effects
: Explain which change model you would follow for the short-term change and which you would follow for the long-term change. Provide rationale for your decision and discuss the effects that these changes would have on the employees, managers, and ex..
|
|
How much each country consume each good
: Think of a 2 country world, say the US and the UK. Each country produces two goods, say food and cloth. Suppose 7 hours of labour are required to produce one unit of either good in the UK, whereas in the US it takes 2 hours to produce one unit food a..
|
|
Explain what are the critical path activities
: What are the critical path activities. What is the project's scheduled completion time. What is the slack or float for Activity C
|
|
About database design and methodology
: We learned about database design and methodology. You are the database administrator for your company, which has just acquired a company called SNHU Appliances. You are deciding what the best approach is. Should you merge your database with the new c..
|
|
Specify the most significant advantages and disadvantages
: Specify the most significant advantages and disadvantages that could be realized by the organization in adopting a server virtualization infrastructure. Prepare a plan for implementing Hyper-V (or an alternate solution, such as VMware) as a solution ..
|
|
General aggregate statistics: total number of tickets sold
: Present the data in a professionally formatted worksheet such that it is easily viewed/understood. Since visualization aids in understanding data, include an appropriate chart to illustrate each set of data. Lastly, analyze the data and provide any c..
|
|
What strategies could you and new soft drink company use
: According to Porter's discussion of industry analysis, is Pepsi Cola a substitute for Coca Cola? what strategies could you and your new soft drink company use to impact the dominance of Pepsi and Coke in the global marketplace? Why
|