The marketing department at State University is working on a project with the following information. The Activity Time is also referred to as the Normal Activity Time and is the time it takes to complete the activity based on the normal times. The Crash Time is the time it takes to complete the activity if this activity is crashed.
Activity
Immediate Predecessors
Activity Time (Days)
Activity Cost (Total)
Crash Time (Days)
Activity Crash Cost (Total)
A
--
6
$10,000
4
$12,000
B
$5,500
2
$7,300
C
A, B
3
$6,000
$7,500
D
$4,000
$6,400
E
$3,500
$5,100
a) What is the critical path for this project, what is the project completion time, how much total work time (in days) is required for this project, and what is the cost for completing this project using the Activity Time? Also identify the slack time for each path. The slack time for each path should be based on the time to complete the critical path.
b) Suppose that the school wants to complete the project in 13 days by crashing the most economical activity. Which activity(ies) should it crash and how much will the project cost increase
c) Suppose that the school wants to complete the project in 12 days by crashing the most economical activity. Which activity(ies) should it crash and how much will the project cost increase from your answer in a)
d) Start with the original Activity Times in answering this part. In addition to the cost information provided above, indirect project costs total $600 per day. The company also incurs $300 in penalty costs for each day the project lasts beyond eleven days. What is the minimum cost schedule for this project? What is the cost of this schedule and what is the project completion time?
Explain and perform many different channel functions. have more control in the channel. can be more efficient. can save money
Discuss how the employees effectively execute the strategy and how the company can sustain this position over time.
You are the civil engineering foreman in charge of a 24-person group whose charter is to erect 3,000 tents for refugees who lost their homes in an earthquake.
Candles can be produced at a rate of 36 boxes per day. The shop operates 20 days a month. Suppose that Demand is uniform throughout the month. Setup cost is $60 for a run also holding cost is $2 per box on a monthly basis.
An analyst must decide between two different forecasting techniques for weekly sales of roller blades: a linear trendequation and the naive approach.
Determine the expected number of nonconforming units that will result from a production run of 20,000 units. Assume that all previously stated conditions regarding the process remain as described during the production run of 20,000
Illustrate what is "supermarket" as it is used in MRP. Elucidate how does it alter responsibility for dealing with lead-time offsets.
The length of each rod in the samples was decided. The results were tabulated and sample means and ranges were computed. The results were. Decide the upper and lower control limits and the overall means for ? charts and R - Charts.
What is the best approach for me to take in creating or implementing an order taking system and how do I deal with Privacy issues?
What communication concepts or theories could be used to enhance communications through personal selling, sales promotion, or relationship marketing?
Draw a decision tree showing the decisions, chance events, and their probabilities, as well as the profitability of outcomes, and solve the decision tree EVsmall expansion = $, EVlarge expansion = $
Initially, assume that Phil wants to minimize his inventory requirements. Assume that each order will be only for what is required for a single period. Using the following forms, calculate the net requirements and planned order release for the gea..
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +1-415-670-9521
Phone: +1-415-670-9521
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd