Estimate the cost of schedule and project completion time

Assignment Help Operation Management
Reference no: EM13110892

The marketing department at State University is working on a project with the following information. The Activity Time is also referred to as the Normal Activity Time and is the time it takes to complete the activity based on the normal times.  The Crash Time is the time it takes to complete the activity if this activity is crashed.                                                                        

  

Activity

  
  

Immediate   Predecessors

  
  

Activity   Time (Days)

  
  

Activity  Cost (Total)

  
  

Crash   Time (Days)

  
  

Activity   Crash Cost (Total)

  
  

A

  
  

--

  
  

6

  
  

$10,000

  
  

4

  
  

$12,000

  
  

B

  
  

--

  
  

4

  
  

$5,500

  
  

2

  
  

$7,300

  
  

C

  
  

A, B

  
  

3

  
  

$6,000

  
  

2

  
  

$7,500

  
  

D

  
  

C

  
  

6

  
  

$4,000

  
  

4

  
  

$6,400

  
  

E

  
  

C

  
  

4

  
  

$3,500

  
  

2

  
  

$5,100

  

a)  What is the critical path for this project, what is the project completion time, how much total work time (in days) is required for this project, and what is the cost for completing this project using the Activity Time?  Also identify the slack time for each path.  The slack time for each path should be based on the time to complete the critical path.

b)  Suppose that the school wants to complete the project in 13 days by crashing the most economical activity.  Which activity(ies) should it crash and how much will the project cost increase

c)  Suppose that the school wants to complete the project in 12 days by crashing the most economical activity.  Which activity(ies) should it crash and how much will the project cost increase from your answer in a)

d)  Start with the original Activity Times in answering this part.  In addition to the cost information provided above, indirect project costs total $600 per day.  The company also incurs $300 in penalty costs for each day the project lasts beyond eleven days.  What is the minimum cost schedule for this project?  What is the cost of this schedule and what is the project completion time?      

Reference no: EM13110892

Questions Cloud

Find difference between sub therapeutic and antibiotics : What is the difference between sub therapeutic and therapeutic antibiotics?
Do elderly men has small ferritin variance than younger men : For 26 younger men sample standard deviation was 84.2 mg/L. At .01 level of significance, do these data support conclusion that ferritin distribution in elderly men has smaller variance than in younger men?
Determine at what pressure will pure h2o start to boil : determine at what pressure will pure H 2 O  start to boil if its temperature is seventy five degree Celsius
Determine how would the mw value be affected : If the gas was not pure butane but 10 mole percent propane and 90 mole percent butane then determine how would the MW value be affected?
Estimate the cost of schedule and project completion time : The marketing department at State University is working on a project with the following information. The Activity Time is also referred to as the Normal Activity Time and is the time it takes to complete the activity based on the normal times.
Illustrate audience characteristics you need to consider : Illustrate what are some considerations that you must keep in mind given the diversity of the audience? Illustrate what would you do to ensure that your message is effective?
One step tests of hypothesis : An insurance company, based on past experience, estimates the mean damage for a natural disaster in its area is $5,000. After introducing several plans to prevent loss
Draw a phylogenetic tree of photosynthetic organisms : Draw a phylogenetic tree of photosynthetic organisms. Include the following in your tree: angiosperms, photosynthetic bacteria, non-photosynthetic bacteria, animals, photosynthetic protists, non-photosynthetic protists, gymnosperms, monocots, bryo..
Determine what is the longest possible wavelength of light : Determine what is the longest possible wavelength of light that could ionize an atom of bismuth if the first ionization energy of bismuth is Ei1 = +70 kJ/mol.?

Reviews

Write a Review

Operation Management Questions & Answers

  Explain and perform many different channel functions

Explain and perform many different channel functions. have more control in the channel. can be more efficient. can save money

  How employees effectively execute the strategy

Discuss how the employees effectively execute the strategy and how the company can sustain this position over time.

  Effective communication techniques for different personality

You are the civil engineering foreman in charge of a 24-person group whose charter is to erect 3,000 tents for refugees who lost their homes in an earthquake.

  Find out the economic run size and maximum inventory

Candles can be produced at a rate of 36 boxes per day. The shop operates 20 days a month. Suppose that Demand is uniform throughout the month. Setup cost is $60 for a run also holding cost is $2 per box on a monthly basis.

  Explain two different forecasting techniques

An analyst must decide between two different forecasting techniques for weekly sales of roller blades: a linear trendequation and the naive approach.

  Determine the expected number of nonconforming units

Determine the expected number of nonconforming units that will result from a production run of 20,000 units. Assume that all previously stated conditions regarding the process remain as described during the production run of 20,000

  Illustrate what is supermarket as it is used in mrp

Illustrate what is "supermarket" as it is used in MRP. Elucidate how does it alter responsibility for dealing with lead-time offsets.

  Decide the upper and lower control limits

The length of each rod in the samples was decided. The results were tabulated and sample means and ranges were computed. The results were. Decide the upper and lower control limits and the overall means for ? charts and R - Charts.

  What is the best approach for an order taking system

What is the best approach for me to take in creating or implementing an order taking system and how do I deal with Privacy issues?

  What communication concepts or theories relationship

What communication concepts or theories could be used to enhance communications through personal selling, sales promotion, or relationship marketing?

  Draw a decision tree showing the decisions and chance events

Draw a decision tree showing the decisions, chance events, and their probabilities, as well as the profitability of outcomes, and solve the decision tree EVsmall expansion = $, EVlarge expansion = $

  Calculate the net requirements and planned order

Initially, assume that Phil wants to minimize his inventory requirements. Assume that each order will be only for what is required for a single period. Using the following forms, calculate the net requirements and planned order release for the gea..

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd