Estimate providing the best accuracy for total project cost

Assignment Help Operation Management
Reference no: EM131738486

1. True or False. The feasible budget region is developed by looking at the project cost profile using early start time, then seeing the difference between this and the profile using late Start times.

2. Which of the following statements are true about cost estimating (select all that are true):

a) the expert opinion method is the same as the cost engineering method

b) the anaology method require that a similar project or work task was done previously

c) it might invovle serveral method simultaneously, such as expert opinion, analogy, and cost engineering

3. A subcontractor object to an audit that is that is performed by the quality department of the main contractor. the procurement manager should explain to the subcontracto that the objective is to

a) help the subcontractor document the lessons learned on the project

b) meet the requirment for ISO 9001 accrediitation to the main contractor

c)help the subcontractor obtain six sigma levels of quality

d) ensure correctness of the subcontractor's financial statement

e) verify adherence to prescribed procedures

4. Which of the follwoing present information in order of priorty to assist focusin on the most critical ones?

a) ishikawa diagram

b)cause and effect diagram

c) cureent reality tree

d) pareto diagram

e) causual loop diagram

5) the project planning and estimating process (select all that apply)

a) relies upon work package supervisor to authorize when work package should begin

b) use a bottom up approach to prepare and check labor and cost estimate

c) use a top-down approach to disseminate information about project goals to lower levels

d)employs pricing units to decide on areas of work needed to prepare labor hours estimate

6) if the actual cost turn to be 234,000 which of the following is the most accurate estime

a. 235k

b. 237,342

c. 233,500

d. 234k

7) True or false. The top down approach to cost estimating provide greater cost accuracy than the bottom up approach

8) the estimate providing the best accuracy for total project cost come from:

a. looking at the cost of similar, completed project

b. looking at the project as a whole

c. combining estimate from all the work packages

d. the cost constraint specified by the customer

9. Which method relies on formulae and table to estimate project costs

a. prametric

b. cost engineering

c. analogy

d. expert opinion

10. True or false. The net present worth of the project derived from project expenses can be increased by delaying the start of project acitivities.

11. if the target cost is 235k, which of the following is the most precise estimate:

a. 237,342

b. 233,500

c. 234,500

d.236k

12. Quality planning should be done

a. independenly by the quality manager at the same time as scheduling is done by the project manager

b. only after scheduling the project that it would be obvious when quality action such as inspection are needed

c. by the project manager just before inspection and testing

d.as an intergrated part of project planning

e. before scope definition, scheduling and budgeting of the project

13. RPN is calculated as

a. SEVERITY + OCCURANCE + DETECTION

b. SEVERITY + OCCURANCE - DETECTION

c. SEVERITY * OCCURANCE / DETECTION

d. SEVERITY * OCCURANCE * DETECTION

Reference no: EM131738486

Questions Cloud

We shall be earning and discussing job analysis : We'll be learning and discussing job analysis. If you have seen those documents, do they accurately reflect what you do (did) on the job?
Reduce the impact of such technology failure risks : Describe a strategy an organization can use to help reduce the impact of such technology failure risks.
Serious health condition under family medical leave act : Is autism a serious health condition under family medical leave act? What is the definition of serious health condition under Americans with disabilities act?
Allocated to home loans-personal loans and automobile loans : Adirondack Savings Bank (ASB) has $1 million in new funds that must be allocated to home loans, personal loans, and automobile loans.
Estimate providing the best accuracy for total project cost : Which of the following statements are true about cost estimating. the estimate providing the best accuracy for total project cost come from.
Grand piano was damaged en route to the auditorium : provider who rents equipment and musical instruments complaining that a grand piano was damaged en route to the auditorium.
Describe the process of planned obsolescence : Describe the process of planned obsolescence. Why would a company intentionally build this into their product adoption process?
Negotiable instrument must be issued to be legally effective : A negotiable instrument must be issued to be legally effective and it must be delivered before it is deemed to be issued.
Multifaceted incentive pay system to increase sales : You have been asked to design multifaceted incentive pay system to increase sales for upcoming holiday season for employees who work in retail handbag store.

Reviews

Write a Review

Operation Management Questions & Answers

  Book review - the goal

Operations Management is about a book review. Title of the book is "Goal". This book has been written by Dr. Eliyahu Goldartt. The book has been appreciated by many as one of those books which offers an insight into the operations and strategic capac..

  Operational plan in hospitality enterprise

Operational plan pertaining to a hospitality enterprise is given in detail in the solution. The operational plan is an important plan or preparation which gives guidelines regarding the role and responsibilities of each and every operation at all lev..

  Managing operations and information

Recognise the importance of a strategic approach to the development and deployment of organisational information systems. Demonstrate an understanding of the importance of databases and their integration to the organisation's overall information mana..

  A make-or-buy analysis

An analysis of the holding costs, including the appropriate annual holding cost rate.

  Evolution and contributor of operations management

Briefly explain Evolution and contributor of Operations management.

  Functions and responsibilities of an operations manager

A number of drivers of change have transformed the roles, functions and responsibilities of an operations manager over recent years. These drivers have not only been based on technological innovations but also on the need for organisations to develop..

  Compute the optimal order quantity

Compute the Optimal Order quantity of DVD players. Determine the appropriate reorder point.

  Relationship to operations practice in the organisation

Evaluate problems in operations and identify approaches to overcoming them. Critically evaluate operating plans and identify areas for improvement. Justify, implement and evaluate changes to operations in line with modern approaches.

  A make or buy analysis

Develop a report for Figi Fabricating that will address the question of whether the company should continue to purchase the part from the supplier or begin to produce the part itself.

  Prepare a staffing plan

Prepare a staffing plan showing the change of your unit from medical/surgical staffing to oncology staffing.

  Leadership styles in different organizations

Ccompare the effectiveness of different leadership styles in different organizations

  Risk management tools and models

Be able to understand the concept of risk, roles and responsibilities for risk management and risk management tools and models.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd