Earned value management value management case study

Assignment Help Operation Management
Reference no: EM131698293

Earned Value Management Value Management Case Study

You are the project manager in charge of a building project. Your project is the construction of a multi-store commercial building which is 15 stories in height. Based on the project plan, the cost of the construction will be $95,000 per floor. The project will take 9 months to complete.

Three months into the project, you have spent $270,000 and completed 3 stories of the building.

You have been request to report on the performance of your project and determine how much time it will take to complete the project and how much money it will cost to complete the project. Use the approach outlined in the reading (Polaris Lessons in Risk Management, Appendix A, Earned Value Management) to determine your project's performance and report on its Earned Value.

Complete the above Earned Value Management Case Study, using EV (earned value) equations.

Questions:

1) Is the project on schedule? If not, it is behind or ahead?

2) Will the project be completed within budget? If not, will be over budget or under budget?

3) What recommendations do you have to get the project back on track?

Reference no: EM131698293

Questions Cloud

Define the actual facts about the mcdonald''s coffee case : Prepare for the debate by reading the article The Actual Facts about the McDonald's Coffee Case retrieved
Skeptical of political policies-rely upon continued growth : If we have had nearly 10 years of economic growth, then why might we be skeptical of political policies that rely upon continued growth?
What is probability that the service life of that product : What is the probability that the service life of that product is 5 years or more?
How might environmental determinism influence these factors : What factors lead to a civilization's growth, and how might environmental determinism influence these factors?
Earned value management value management case study : You are the project manager in charge of building project. Will the project be completed within budget? If not, will be over budget or under budget?
Discuss the policy of unrestricted submarine warfare : Discuss the policy of unrestricted Submarine Warfare. Should it have been practiced in the Pacific by the US during the war?
Determine the swell percentage and shrinkage percentage : A soil has a bank dry density of 100 pounds per cubic foot, a loose dry density of 90 pounds per cubic foot, and a compacted dry density of 105 pounds.
Historian sallust attribute the decline of the roman republi : To what does the historian Sallust attribute the decline of the Roman Republic? Why did Caesar believe he was justified in moving his troops into Italy?
An assembly line requires six tasks to make their product : An assembly line requires six tasks to make their product. What is the minimum and maximum number of units that can be produced per day?

Reviews

Write a Review

Operation Management Questions & Answers

  Discussed in the context of leadership-vision and purpose

I would like to examine two points discussed in the context of leadership: vision and purpose. Both can feel at times generalized and lacking of substance. Both terms carry implications organizationally as well as for membership within organizations.

  Customers and suppliers done in an automated

To what extent are transactions with your company's customers and suppliers done in an automated, paperless fashion, and where are the major savings?

  Types of control measures

A team of managers of a customer call center for timeshare vacations. Discuss, the types of control measures you would use to see how efficient and effective an employee is.

  What are the mad and mse for each method

Following are two weekly forecasts made by two different methods for the number of gallons of gasoline, in thousands, demanded at a local gasoline station. What are the MAD and MSE for each method

  What is the pros and cons of implementing such a policy

what is the pros and cons of implementing such a policy on this issue?

  Decision alternative with the maximum payoff

Choosing the decision alternative with the maximum payoff for the most likely state of nature is called:

  Law calculate the average throughput time

Utilizing Little's Law calculate the AVERAGE throughput time. Sunshine Medical Clinic serves two hundred patients in an eight hour day which equates to seeing twenty-five patients per hour. The average number of patients in the waiting room, exam roo..

  Principle of selling class

List and compare the probable functional, situational, psychological, social, and knowledge needs of (a) a large financial investment office and (b) a college student, both of whom are looking to purchase a new computer print

  Reflect the valuations of the suppliers are private

A manufacturer has just launched a second-price sealed-bid procurement auction to identify the lowest cost supplier for a key component. The manufacturer does not know what bids to expect, but assumes that the prices per component that reflect the va..

  Historical cost or schedule data from like past projects

Do any of your organizations use the historical cost or schedule data from like past projects to estimate the cost or timeline for a new project? If so, do you believe it helps reduce variances?

  Alternatives as opposed to independent project analysis

From your experience and research, would you conclude that certain industries typically analyze decisions using Mutually Exclusive (ME) Alternatives as opposed to Independent Project analysis or vice-versa?

  Average firm performance in this industry to be low

Given the following macro-environmental factors, would you expect the average firm performance in this industry to be low, mixed, or high?

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd