During a project earned value analysis

Assignment Help Business Management
Reference no: EM13960542

Of the three problems below, choose and solve one problem. Show your work. Along with your answer, define each term and explain the significance (meaning) of the solution.

1. During a project, Earned Value Analysis is performed and gives the following numbers:

EV: 523,000; PV: 623,000; AC: 643,000.

Which results are correct?

A. CV: +120,000; SV: +100,000

B. CV: +100,000; SV: +120,000

C. CV: -100,000; SV: -120,000

D. CV: -120,000; SV: -100,000

2. You found the following Earned Value Analysis information for a recently closed out project:
SPI = 0.7, CPI = 1.0

A. The project has been cancelled while it was executed. At that time the project was behind schedule and on budget.

B. The project's deliverables have all been finished. The project came in ahead of schedule but on budget.

C. The project's deliverables have all been finished. The project came in on schedule but over budget.

3. You are assigned as the project manager to a project which had a one-time cost variance in the past caused by unexpected rework which has meanwhile

been finished.
You perform Earned Value Analysis and find the following results:
EV: 250,000; PV: 200,000; AC 275,000
BAC is 500,000.
What is right?
A. EAC = 550,000

B. EAC = 525,000

C. EAC = 500,000

D. EAC = 425,000

Reference no: EM13960542

Questions Cloud

What value if interet was compounded quarterly : Type of investment: 36 month CD at 2% compounded daily What value if interet was compounded quarterly? How much is investment worth after 36 months?
Reaction paper that focuses on community treatment orders : Write a 3-5 page reaction paper that focuses on your key issue. You should summarize your issue, including the debate that exists surrounding that issue, and weigh in with an informed opinion
Summarize the business research project or article : Locate a business research article. This project should be one that you perceive to be conducted in an ethical manner. Write a 700- to 1,050-word paper in which you create a set of ethical research guidelines for the research:
Determine the period for planet kep to orbit if the distance : A 2.4 gram penny is on a turntable. It starts from rest at a radius of 0.14 meters and the turntable speeds up until the penny flies off with a tangential speed of .88 m/s. What coefficient of static friction (to three decimal places) exists betwe..
During a project earned value analysis : Of the three problems below, choose and solve one problem. Show your work. Along with your answer, define each term and explain the significance (meaning) of the solution.
Calculate the percent markdown after rebate for the product : Calculate the percent markdown after rebate for the product found in part 1. List three pros and three cons to the practice of markdowns/markups. Debate these points.
How does studying humanities help society in today world : How does studying humanities help society in today's world? How did the 19th century social reformation, such as the European revolution of 1848, influence theatre in multiple countries and religions
Venture capitalists seek to maximize economic returns : Venture capitalists seek to maximize economic returns. Considering all the risks in the development or expansion of business ventures, how do venture capitalists make money? How do venture capital firms balance their portfolios to minimize risks..
What is the speed of the satellite in its orbit : A satellite of mass 150kg is launched into orbit above the surface of the Earth in a circular orbit. what is the speed of the satellite in its orbit? What is providing the centripetal force on it? Find its value.

Reviews

Write a Review

Business Management Questions & Answers

  Receive the exact amount of profit

Receive the exact amount of profit

  Based on these data select the appropriate inventory model

Based on these data select the appropriate inventory model as well as calculate the economic order quantity and reorder point. Define in a sentence how the plan would work.

  Develop your revised company mission statement

Create your revised NAB company name and explain its significance. Develop your revised company's Mission Statement and provide a rationale for its components

  Assess the way training is used in the change process

Was the training that was provided compatible with the training requirements and delivered in a way that maximized the transfer of learning to the work situation?

  Information about change managementanchoring new approaches

information about change managementanchoring new approaches in the culture of an organization is a long process. does

  What this means in a global context

The issue of responsibility is foundational to understanding organizational ethics Explain what this means in a global context.

  Evolution of managementthe evolution of managementplease

evolution of managementthe evolution of managementplease respond to the following- examine the principles behind the

  Show the alternative dispute resolution

Discuss an instance where it has been used by an employer with which you are familiar

  Original assignment topic

Original Assignment Topic

  Small businesses importance in the american economy

Small Businesses Importance in the American Economy- What are the growth trends for small businesses? What are the reasons behind these trends?

  Explain the functions of management

There are six functions of management. Understanding your organization, or one of which you are familiar

  Develop your strategy for new product

Based on the scenario with Max Games, answer the following questions based on what your decisions are and why you made that decision. Develop your strategy for new product

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd