International Door Slammers has an order to deliver 500 door slammers on day 130. Draw up a backward schedule under the following conditions:
a. Only one machine is assigned to each operation.
b. Schedule one 8-hour shift per day for 5 days per week.
c. All parts are to move in one lot of 500 pieces.
d. Allow 8 hours between operations for queue and move times
A slammer consists of three parts. Purchased components C and D form subassembly A. Subassembly A and component B form the final assembly. Part B is machined in three operations. No special tooling is required except for part B, operation 20. It takes 24 hours to make the tooling. Material is available for all parts.
Standard times for the lot of 500 are as follows:
A rectangular concrete channel 10 m wide has a bed slope of 1 m/km and surface roughness equivalent to a Manning n of 0.02. It is proposed to use a hump on the channel bed for the purpose of flow measurement. If the maximum discharge is 150 m3/s:
A left-turn movement has a maximum arrival rate of 200 veh/h. The saturation flow of this movement is 1400 veh/h. For this approach, the yellow time is 4 seconds, all red time is 2 seconds and total lost time is 3 seconds.
What is the terminal velocity? Include the effects of gravitational acceleration.
Vehicular access to the Toronto Island Airport now involves the use of a small ferry, capable of carrying about 8 automobiles or an equivalent number of trucks, which operates across the 150 metre wide body of water known as the Western Gap
Lake Mead has a water surface area of 65,800 hectares. In acertain month the reservoir is full, and the pan evaporation rateis 25 cm. Using a pan coefficient of 0.73, estimate theevaporation volume for the month in m3.
A closed system of 0.123kg undergoes a frictionless, quasi-static process along the path PV=C from 100kpa to a final state where the volume is twice the initial volume.
choose two research papers - one quantitative and the other qualitative - from the construction management literature. Write a paper which discusses in detail the extent to which the authors of your papers followed in their own work the principles ..
Find the total mass, quality of steam, specific volume, specific enthalpy, and specific internal energy.
Find the modal frequencies and mode shapes for the frame assuming the columns are fixed at the top and the bottom and Sketch out the first and third mode shape.
A cylindrical chimney,1 m in diameter and 2.5 m tall is exosed to a uniform 50km/hr wind at standard atmospheric conditions.End effects and gusts may be neglected.
Name the three factors that influence the degree to which martensite is formed throughout the cross section of a steel specimen. For each, tell how the extent of martensite formation may be increased.
The coefficient ofrestitution between each car is 0.8 . Determine the final velocityof each car, after all impacts, assuming (a) cars A and C hit Car Bat the same time, (b) car A hits car B before car C does.
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +1-415-670-9521
Phone: +1-415-670-9521
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd