Draw the network diagram

Assignment Help Operation Management
Reference no: EM13313753

1. The following information has been gathered for a project:
a. Draw the network diagram.
b. Calculate the slack for each activity and determine the critical path. How long will the project take?

1178_Draw the network diagram.png

2. Consider the following information for a project to add a drive-thru window at Crestview Bank.
a. Draw the network diagram for this project
b. Specify the critical path.
a. Calculate the slack for activities A and D.

1656_Draw the network diagram1.png

3. Barbara Gordon, the project manager for Web Ventures, Inc., compiled a table showing time estimates
for each of the activities of a project to upgrade the
company's Web page, including optimistic, most likely, and pessimistic.
a. Calculate the expected time, t1, for each activity.
b. Calculate the variance, cr2, for each activity.

734_Draw the network diagram2.png


Attachment:- MNG_Question.pdf

Verified Expert

Reference no: EM13313753

Questions Cloud

Compute how many ml of 0.200 m naoh : calculate how many mL of 0.200 M NaOH (aq) would be needed to react with the malic acid sample from step c.
How far from the wall should the mirror be located : A concave mirror (R = 56.0 cm) is used to project a transparent slide onto a wall. How far from the wall should the mirror be located
What fraction of the tank air mass will be consumed : The divers work at a depth of 15 m and the seawater density is 1027 kg m-3. They are known to consume 130 litres of air at the ambient temperature is 10oC over the time taken to do the job.
How far did the spring compress : A block of mass m=1.40kg slides along a horizontal table with speed Vo=2.50m/s. How far did the spring compress when the block first momentarily come to rest
Draw the network diagram : Draw the network diagram and calculate the slack for each activity and determine the critical path. How long will the project take?
Find the velocity and time when the projectile hits ground : A projectile is projected from the origin with a velocity of 30.0 m/s at an angle of 45.0 degrees above the horizontal
Explain what is the purpose of the trail titration : what is the purpose of the trail titration. describe the endpoint of the a titration. how will you know when you have reached it. explain why the walls of the flask are washed with distilled water during the titration.
How far down the road does the officer catch the speeder : A speeder is racing down the road at a constant speed of 90mi/h. A police officer is having coffee while the speeder zips past her. How Far down the road does the officer catch the speeder
Create a program that outputs the result of the formula : Create a program that uses the same formula above to output the result; this time, however, prompt the user for the values a, b, x, and y. Use appropriate variable names and naming conventions.

Reviews

Write a Review

Operation Management Questions & Answers

  Cycles to maximize the roi on building new hotels

As CEO, would you try to predict the cycles to maximize the ROI on building new hotels? It takes 2-3 years to build a hotel and another 5-10 to begin earning an ROI.

  The product was not patentable because it was too similar

The product was not patentable because it was too similar to other existing technologies. Major corporations saw his success and have now entered the market with competing products

  What does a company gain by disclosing to employees

What does a company gain by disclosing to employees its intent to initiate a monitoring policy?

  Illustrate what is meant by term service level

Illustrate what is meant by term service level. Generally speaking, explain how is service level related to amount of safety stock held.

  What factors should be considered

Identify the cost of hardware, software, and networking components for an RFID system for your company. What factors should be considered?

  Discuss strengths to the survival of military health system

Discuss strengths and threats to the survival of the military health system. Summarize the Tricare program and detail its options for enrollees.

  The probabilities associated with the states of nature

The probabilities associated with the states of nature are 0.25 for a big demand, 0.55 for an average demand, and 0.20 for a small demand.

  What was your role in strategy for that organization

What was your role in strategy for that organization?

  whAt is your overall interpretation of this result

Find the schedule and cost variances for a project that has an actual cost at month 22 of $540,000, a scheduled cost of $523,000, and an earned value of $535,000. What is your overall interpretation of this result?

  Illustrate what will be the new economic order quantity

the ordering cost can be cut to $4.00, illustrate what will be the new economic order quantity, order frequency and Yearly inventory management cost.

  What is d craig optimal strategy

D. Craig Exploration Company has been offered a lease to drill for oil on a particular piece of property. While oil has been found on nearby land, there are no assurances that D. Craig will be successful in finding oil

  Why global beverage company require the central management

Why would businesses like your chosen global beverage company require the central management of all of these various currencies by a central authority like the International Monetary Fund?

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd