Widgetco is about to introduce a new product. One unit of this product is produced by assembling subassembly 1 and subassembly 2. Before production begins on either subassembly, raw materials must be purchased and workers must be trained. Before the subassemblies can be assembled into the final product, the finished subassembly 2 must be inspected. A list of activities, their predecessors, and their durations is given in the following Table.
Activity Predecessors Duration(days)A - Train workers --------- 6B - Purchase raw materials --------- 9C - Make subassembly 1 A,B 8D - Make subassembly 2 A,B 7E - Inspect subassembly 2 D 10F - Assemble Subassemblies C,E 12
Problem:
1. Draw a project diagram (network) for this project?2. What is the total project time?3. What is the critical path?
The following data represent the cost of electricity for the period of July 2008 for a random sample of 50 one-bedroom apartments in a large city.
At the .10 significance level, can we conclude that there is a difference in the length of time the two types of treatment lasted?
Conduct a test to determine whether blood lactate level (y) is linearly related to perceived recovery (x). Use alpha = .05. Find the p-value for testing the hypotheses you gave in the previous problem. Show all decimal places in your answer.
We will test to determine if there evidence of an improvement on the final examination, at the 1% significance level. What is the alternate hypothesis?
Bougainvilleas, mean growth rate was 2.23 inches/week and sample standard deviation was 0.77 inches/week. Determine a 90% confidence interval for mean growth rate of all Bougainvilleas.
Construct a 95 percent confidence interval for the true mean.
In order to test the assumption of a Poisson distribution, a random sample of 150 ten-minute intervals was taken.
A lot of n items comprises k defectives, and m are chosen randomly and inspected. How must the value of m be selected so that probability that at least one defective item turns up is .90?
What is our decision regarding the differences between the observed and expected frequencies if the critical value of chi-square is 9.488 and the computed value is 6.079?
A state transportation official claims that the mean waiting time at exit booths from a toll road near the capitol is no more than .40 minutes. for a sample of 35 motorists exiting the toll road, it was found that the mean waiting time was .46 min..
I have a problem that wants to know the sample size of Illinois republican voters, they want to know the sample size with 95% confidence and 3% margin of error, not sure how to get started.
Develop a point estimate of the population mean number of units sold per month. Develop a point estimate of the population standard deviation
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +1-415-670-9521
Phone: +1-415-670-9521
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd